Oracle's $165 billion New Mexico campus permit slipped past December 7 as lenders sell the debt

Oracle's $664 billion backlog assumes its biggest Stargate campus switches on. The New Mexico air-permit decision just slipped past December 7, the project's lenders are heading for the exits, and the stock's 8% drop was blamed on politics instead.

Richard TangRichard Tang · 2 min read
Share
A large modern natural gas-fired power plant beside water
1 / 6Slide 1 of 6
The air permit for the gas-fired plant that would power Oracle's New Mexico campus now waits on a December 7 hearing. Shown: a modern natural gas-fired power station.

The calendar on Oracle's+1.31% — Oracle, up 1.31 percent today largest data center just moved, and the market has not priced it. Bloomberg reported on November 5 that Yucca Growth Infrastructure LLC, the power developer behind Oracle's planned $165 billion New Mexico complex, waived its right to a November 23 decision deadline on the state air permit its gas-fired plant needs 1. The decision now follows a public hearing on December 7 1.

Oracle's stock fell about 8% the same day, but the wire blamed the Democratic sweep and Oracle's capital intensity, not the schedule 34. That split is the trade.

Three parties now hold the switch-on date

The permit is not a local detail. Oracle is the main tenant at Project Jupiter, the New Mexico campus in the OpenAI$1.18T — OpenAI, private, latest valuation $1.18T-Oracle-SoftBank Stargate venture, and its $664 billion backlog is a promise about campuses that switch on and keep switching on 2. Three parties now hold the date: the state air regulator, the lenders selling the project's debt, and Oracle itself, which in September served the developer a force majeure notice, a clause that could let it delay payments if the campus misses its 2028 start 2.

Lenders are already voting. An unnamed holder is auctioning about $500 million of data-center loans, including a $25 million slice backing Project Jupiter, with bids due November 19 2. The site's $18 billion of loans were quoted at 89 to 91 cents on the dollar in September 2.

Oracle has already paid for the build

Free cash flow ran to negative $23.7 billion in fiscal 2026, total debt with leases stood at $169.1 billion on August 31, and this week's $20 billion raise exhausted its cap through fiscal 2030 3. Any delay means collecting later on money already spent 3.

Oracle's capex has climbed tenfold in two years as its debt pile followed

  • Capex
  • Total debt
0B50B100B150B200BQ3 '24Q1 '25Q3 '25Q1 '26Q3 '26155.93B
Data
CapexTotal debt
Q2 '242.8B93.12B
Q3 '242.3B84.52B
Q4 '243.97B88.62B
Q1 '255.86B96.28B
Q2 '259.08B104.1B
Q3 '258.5B105.41B
Q4 '2512.03B124.39B
Q1 '2618.64B153.12B
Q2 '2616.49B156.19B
Q3 '2628.5B155.93B
Quarterly capex and total debt in billions of dollars, from Oracle's SEC filings; debt includes leases. The draft reports free cash flow of negative $23.7 billion for fiscal 2026 and total debt with leases of $169.1 billion on August 31, 2026. Source: Oracle, quarterly figures from its SEC filings, retrieved 6 November 2026.5

The stock trades at 14 times forward earnings against a five-year average of 21x 3. Wait for December 7 3. If the permit clears, the cheap multiple is the story. If it slips again, the force majeure clause goes live and the project's loans reprice before Oracle's mid-December results do it for you.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading ORCL

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Fermi's ousted CEO sold $13 million of stock into a 52-week low, then said it 'should be soaring'

    Toby Neugebauer, ousted as Fermi's chief executive in April, sold 7,657,800 shares for about $13 million in three sessions, 5 million of them on the day the stock touched its 52-week low. The next morning he demanded the company be sold, with its only tenant lease unsigned and $62.5 million of cash against a $737.9 million trailing loss.

    Data Center

    Data-center orders tripled at Carrier, and the cost of rolling its debt doubled

    On November 4 Carrier sold $1.5 billion of notes at more than double the coupon of the paper they retire, between record data-center orders and a $3.1 billion European write-down. The coupon is the market's new price for financing the AI buildout's supply chain.

    Data Center

    Microsoft is paying for its $170 billion AI build with jobs and invisible Copilot limits

    The buyout landed two days before earnings showing capex of $45.2 billion against $18.6 billion of free cash flow, and from November 9 the invisible Copilot Chat caps reach every Microsoft 365 organization above 2,000 seats: employees pay in jobs, customers in predictability or a license, and the $170 billion build collects.

    Data Center

    Core Scientific and IREN expect to end bitcoin mining by December 31, 2026; contracts price them from January

    Core Scientific and IREN both set December 31, 2026, as mining's end in the same day's earnings. From January their equities price on contracted power, credit and construction instead of the coin.

    Data Center

    Microsoft supplier IREN tripled AI cloud revenue to $200 million; its $4 billion target slips to January

    AI Cloud revenue tripled sequentially to $200 million and the backlog stands at $20.3 billion, yet the $4 billion run-rate target slipped to January or February. The build converts on schedule; the calendar and the uncommitted $6 billion are the open questions.

    Data Center

    Nebius has 5 GW of power signed and about 200 MW billing: the ladder that sets its ARR guide

    Nebius's capacity is counted in gigawatts while its revenue arrives in megawatts. Working the ladder from contracted to connected to billing power shows what the December guide really assumes, what a customer prepayment is, and why the debt market already ranks the neoclouds.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.