Power

Pinnacle West's Arizona Public Service asks regulators for a 25-year TSMC deal covering 1.9 gigawatts

TSMC's north Phoenix fabs would draw the electricity of roughly 300,000 Arizona homes under the first deal on APS's subscription model for power-hungry users. The terms go before a state commission that just changed hands, set the yardstick for every data center that follows, and commit TSMC, on the filing's terms, to pay for new generation whether or not the fabs reach full buildout.

Vincent JiangVincent Jiangfour-minute read
Share
A natural gas-fired power plant in the Arizona desert near Gila Bend
1 / 7Slide 1 of 7
The Gila River Power Station near Gila Bend, Arizona. APS's proposed Desert Sun plant would rise west of the same desert town, its cost underwritten by TSMC's contracted rates, on the filing's terms.

On November 6, 2026, Arizona Public Service (APS), Arizona's largest electric utility and the main subsidiary of Pinnacle West Capital+2.10% — Pinnacle West Capital, up 2.10 percent today (NYSE: PNW), asked the Arizona Corporation Commission to approve a 25-year Direct Pricing Contract with TSMC+2.40% — TSMC, up 2.40 percent today Arizona 12. The Direct Pricing Contract is a long-term agreement designed for customers with extra-large energy needs 2.

TSMC (NYSE: TSM), the world's largest contract chipmaker 3, would be the first customer on APS's subscription model for power-hungry users 1. The filing puts a number on its appetite: about 1.9 gigawatts at full buildout, the electricity use of roughly 300,000 homes 1.

The charge: growth that pays for itself

The claim on file is that TSMC's growth pays for itself. The filing states that TSMC Arizona will make long-term financial commitments tied to new generation resources and service infrastructure, so the cost of its expansion is not shifted onto the utility's other 1.5 million homes and businesses 2. To serve the load, APS is adding renewable resources and natural gas generation, including the proposed Desert Sun plant west of Gila Bend, and says TSMC's contracted rates would cover the cost of building it 1.

The evidence: the small bar in a very big queue

TSMC's own fabs are the small bar beside the campuses its chips are meant to fuel. In Cochise County, rocket company SpaceX−3.35% — SpaceX, down 3.35 percent today is behind a proposed 6-gigawatt supercomputing campus that would rank third nationally, behind developer Fermi America's 11-gigawatt Project Matador and investor Kevin O'Leary's 9-gigawatt Stratos project 56.

TSMC's 1.9-gigawatt fab load is dwarfed by the data-center campuses its chips fuel

TSMC's fabs are the small bar: its customers' campuses want 6 to 11 gigawatts

  • Estimate
0 GW5 GW10 GW15 GWProject Matador (proposed)11 GWStratos (proposed)9 GWCochise campus (proposed)6 GWSpaceX is behind the proposalTSMC Arizona (contracted)1.9 GW
Data
Value
Project Matador (proposed) (estimate)11 GW
Stratos (proposed) (estimate)9 GW
Cochise campus (proposed) (estimate)6 GW
TSMC Arizona (contracted)1.9 GW
Full-buildout electricity demand, gigawatts. TSMC's figure is the estimate in the APS filing to the Arizona Corporation Commission; the other three are proposed design loads, uncontracted. Sources: KJZZ, 11, November 10 and 3, 2026 [1][5][6].1,5,6

The money moves at the same pace. TSMC's board approved about $40.9 billion of capital spending on November 10, and Goldman Sachs+1.63% — Goldman Sachs, up 1.63 percent today forecasts annual spending of $85 billion in 2027 and $98 billion in 2028 3. Capacity is so tight that Anthropic$350B — Anthropic, private, latest valuation $350B, an artificial intelligence lab, says in its IPO filing that TSMC's constraints have at times delayed scheduled chip deliveries 3.

TSMC's quarterly capital spending has more than doubled since early 2024

Capex hit a record $15.6B in Q2 2026, up 53% on the year

$5B$10B$15B$20BQ4 '23Q2 '24Q4 '24Q2 '25Q4 '25Q2 '26$15.55B
Data
Quarterly capital expenditure
Q3 '23$7.02B
Q4 '23$5.53B
Q1 '24$5.66B
Q2 '24$6.32B
Q3 '24$6.55B
Q4 '24$11.13B
Q1 '25$10.02B
Q2 '25$10.17B
Q3 '25$9.43B
Q4 '25$11.4B
Q1 '26$10.9B
Q2 '26$15.55B
Capital expenditure as reported in TSMC's quarterly SEC filings, US dollar billions; Q2 2026 is the latest reported quarter. Source: TSMC SEC filings, retrieved November 11, 2026 [9].9

The exhibits: three claims with no numbers attached

APS's case leans on statements nothing yet quantifies: that TSMC's rates cover Desert Sun's cost, that the plant serves the grid beyond TSMC, and that capacity stays reserved for "existing homes, hospitals, schools, businesses, and communities" 2. The public description of the deal carries no rate level and no plant cost. The commission will vote on those words.

The prosecution: the court just changed hands

The counter-claim comes from the two winning candidates themselves: they accused the commission of being too deferential to the state's utilities 4. Voters then ended the five-member commission's all-Republican control on November 3, electing Democrats Clara Pratte, co-founder of renewable developer Navajo Power, and Jonathon Hill 4.

The commission is no rubber stamp: established under the state constitution, it must approve utility capital spending and long-term contracts, and its rulings carry the weight of law 7. The utility in front of it also plans to run the Four Corners coal plant as late as 2038 1.

The defense: the ramp is real and the money is moving

TSMC's side of the ledger is physical. Construction on its second Arizona fab finished in October, and volume production begins in the third quarter of 2027, "slightly ahead" of schedule, TSMC chief executive [C.C 8. Wei](https://theinference.org/markets/people) told investors on October 15 8. Nearly 20 facilities are under development worldwide, and Wei sent teams to inspect US data-center construction and grid capacity first-hand before committing more factory space 3.

TSMC's Fab 21 under construction in Phoenix, Arizona
TSMC's Fab 21 under construction in Phoenix in November 2023. Construction on the company's second Arizona fab finished in October 2026, with volume production slated for the third quarter of 2027.Hunter Trick (TrickHunter)

The shape of the deal suggests why Pinnacle West wants it: a 25-year commitment on this scale is the demand a regulated utility is built to serve. The Inference has covered the water and rare-earth magnets the same campus depends on.

The verdict watch: who pays if the ramp slips

Nothing in the filing spells out who carries the risk, but the shape of a 25-year deal answers it: TSMC's commitments to the new generation run whether or not the fabs reach full buildout. If the ramp slips, it pays for the power anyway.

Two dated readings show how that lands. TSMC's 2027 guidance in January is where overseas capacity, and the power behind it, gets priced. In Arizona the docket is open, and the terms APS and TSMC file there are what every later large Arizona load, including the 6-gigawatt Cochise campus, will negotiate against.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading TSM

Reader comments

0 comments

    Power

    MARA sold 13,597 bitcoin for $1.1 billion after FERC cleared its $1.5 billion Long Ridge gas plant buy

    FERC's clearance turns December into a double deadline for MARA: close the $1.5 billion Long Ridge gas plant, and sign the AI leases it still lacks. Analysts are split from $11 to $20 on what the unsigned megawatts are worth.

    Power

    Southern Company can sell 12 million shares at any moment as its capital plan could reach $100 billion

    Southern Company, Georgia Power's parent, can now sell stock the moment it chooses after filing an automatic shelf on November 10. The capital plan behind the filing could approach $100 billion, its remaining equity is unpriced, and in January a new Democratic majority arrives on Georgia's utility commission with authority over who pays.

    Power

    Duke Energy asks Florida for 300 MW of solar and a $1 billion savings claim, six days after a data-center loss

    The filing claims $1 billion of lifetime customer savings, but that number is avoided fuel cost, not a bill credit, and it lands six days after the same commission unanimously rejected Duke's data-center cost plan. For Duke shareholders, commissions reading this arithmetic decide whether the $103 billion build gets paid.

    Power

    Talen Energy sells 750 MW of capacity for $100 million a year, keeps the power merchant

    The seven-year Guernsey deal locks in the leg of the business Talen can price and leaves the electricity merchant, in a zone its own 10-Q shows trading far below the PJM market. It de-risks the leveraged AI-power trade that TLN holders own.

    Power

    Gov. Spanberger moves to force NextEra's sealed fitness memo into the $67 billion Dominion merger hearing

    The State Corporation Commission's evidentiary hearing starts November 17 with a ruling due by January 11, while traders who bet on deal spreads treat approval as near-certain. A rate freeze, a rate cap or a fitness finding would reprice both stocks.

    Power

    PG&E freezes $2 billion of grid spending as California's wildfire liability law stalls

    California's utility regulator now calls the liability rule underneath PG&E's hardening boom unsustainable, and a November 19 vote could cut its 5,000-mile burial plan to about 1,100 miles. PCG shareholders are forgoing rate-base growth to protect the balance sheet; ratepayers may pay either way.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.