Power

PG&E freezes $2 billion of grid spending as California's wildfire liability law stalls

California's utility regulator now calls the liability rule underneath PG&E's hardening boom unsustainable, and a November 19 vote could cut its 5,000-mile burial plan to about 1,100 miles. PCG shareholders are forgoing rate-base growth to protect the balance sheet; ratepayers may pay either way.

Vincent JiangVincent Jiangthree-minute read
Share
Patti Poppe, chief executive of PG&E Corporation, smiling in a company portrait
1 / 6Slide 1 of 6
Patti Poppe, chief executive of PG&E Corporation, told analysts she is optimistic Newsom will call a special session on wildfire liability before he leaves office in January.

25,000 hookups put on hold, some for six months

Pacific Gas and Electric has warned about 25,000 prospective customers, from housing developments to data centers, that they could wait up to six months past their scheduled dates to get power, because the utility is holding back $2 billion in planned spending 1. More than 60 renewable-energy projects, including battery storage, could slip by as much as a year, about 15 percent of what the company planned to spend 2. PG&E says it is not delaying safety work and is protecting existing customers from unnecessary long-term rate increases 1.

The company also cut its 2027 capital budget to $11.4 billion, down $2 billion, to borrow less at the higher interest rates wildfire risk has already added more than $4 billion of 23. That is the first hard money consequence of September's legislative collapse, and it lands squarely on the growth story PCG sells investors: regulated returns on a rising rate base.

A liability rule the state's own regulator calls unsustainable

Under California law, a utility pays the full cost of any fire its equipment starts, even if it acted reasonably and followed its wildfire plan, a rule the state's own regulator calls unusual among states 4. PG&E−0.76% — PG&E, down 0.76 percent today has already paid at least $11 billion for insurance claims from the 2017 and 2018 fires, the Camp Fire among them 2.

The California Public Utilities Commission's report, released last week at Gov. Gavin Newsom's request, says the system places tens of billions of dollars on utilities and ratepayers, drags down the utilities' credit ratings and may leave the state's support fund short of future claims 4. Newsom's fix, which would have trimmed what insurers can recover from utilities, died in September; fire-victim groups and Consumer Watchdog called it a bailout 48.

A real build, and a draft that would cut three quarters of it

The physical program is real. PG&E has buried 1,500 miles of line in high fire-threat districts since 2021, 325 of them in 2026, and says undergrounding cuts ignition risk about 98 percent and outages about 90 percent on those lines 5. Butte County, where the Camp Fire burned, leads the state with 427 miles 9.

PG&E's grid buildout outran operating cash in ten of the last twelve quarters

  • Capital expenditures
  • Operating cash flow
$0B$1B$2B$3B$4BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$3.3B$2.5B
Data
Capital expendituresOperating cash flow
Q4 '23$2.61B$0.48B
Q1 '24$2.64B$2.26B
Q2 '24$2.3B$0.71B
Q3 '24$2.61B$3.13B
Q4 '24$2.83B$1.93B
Q1 '25$2.64B$2.85B
Q2 '25$3.07B$1.06B
Q3 '25$2.93B$2.85B
Q4 '25$3.16B$1.96B
Q1 '26$3.36B$2.43B
Q2 '26$2.97B$0.91B
Q3 '26$3.3B$2.5B
PG&E's quarterly capital spending against the cash its operations generated, Q4 2023 through Q3 2026. Capex exceeded operating cash flow in ten of the twelve quarters, and has climbed from $2.6 billion to $3.3 billion. Source: PG&E's quarterly SEC filings, in billions of dollars.10,11

The 10-year Electrical Undergrounding Plan filed in October proposes 5,000 more miles across more than 30 counties in 2028 through 2037, roughly $16 billion of work that PG&E values at $117 billion in avoided wildfire and outage costs, about $9 a month for the average customer 67. The same regulator is now drafting rules, up for a vote on November 19, that PG&E says would cut eligible miles to about 1,100 by steering utilities toward cheaper overhead alternatives like covered conductors 7.

A utility bucket truck works overhead power lines among burned, leafless trees after a wildfire
PG&E crews rebuild distribution lines through burned trees after the 2021 Salt Fire in Northern California. Overhead conductors in high fire-threat districts are the cheaper alternative the CPUC draft would steer the utility toward.USFS, via InciWeb

The CPUC draft would cut PG&E's burial plan from 5,000 miles to about 1,100

  • Estimate
0 mi1,000 mi2,000 mi3,000 mi4,000 mi5,000 miBuried since 20211,500 mi10-year plan5,000 miCPUC draft cap1,100 mi
Data
Value
Buried since 20211,500 mi
10-year plan (estimate)5,000 mi
CPUC draft cap (estimate)1,100 mi
Miles of line: what PG&E has buried since 2021, what its 10-year plan proposes for 2028 through 2037, and what the CPUC's draft rule would leave eligible. The plan and the draft cap are proposals, not reported results. Sources: PG&E's 1,500-mile announcement and the SB 884 implementation report.5,7

Blackmail, or a risk no utility can price?

Consumer Watchdog's Jamie Court calls the hookup delays "bailout blackmail" and argues ratepayer advocates are right that much of the deferred money is already built into existing rates 18. There is a real argument on his side: liability is what makes shareholders, not victims, eat the cost of negligence. But PG&E's answer is that a utility strictly liable even when it follows its own safety plan is carrying a risk it cannot price, and the deferral shows capital will not chase growth the state keeps repricing 24.

Three dates decide it, starting November 19

Three dated events decide it: the CPUC vote on the undergrounding rule on November 19 7; the company's December list of exactly which projects slip 2; and whether Newsom, term-limited out in January, calls a special session before then, which CEO Patti Poppe told analysts she is optimistic about 8. If the draft rule holds, PG&E's compounding capex story shrinks by three quarters on paper. If reform passes, the tail gets priced and the boom resumes. The ratepayer funds the shovel; the shareholder still carries the fire.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading PCG

Reader comments

0 comments

    Power

    MARA sold 13,597 bitcoin for $1.1 billion after FERC cleared its $1.5 billion Long Ridge gas plant buy

    FERC's clearance turns December into a double deadline for MARA: close the $1.5 billion Long Ridge gas plant, and sign the AI leases it still lacks. Analysts are split from $11 to $20 on what the unsigned megawatts are worth.

    Power

    Southern Company can sell 12 million shares at any moment as its capital plan could reach $100 billion

    Southern Company, Georgia Power's parent, can now sell stock the moment it chooses after filing an automatic shelf on November 10. The capital plan behind the filing could approach $100 billion, its remaining equity is unpriced, and in January a new Democratic majority arrives on Georgia's utility commission with authority over who pays.

    Power

    Duke Energy asks Florida for 300 MW of solar and a $1 billion savings claim, six days after a data-center loss

    The filing claims $1 billion of lifetime customer savings, but that number is avoided fuel cost, not a bill credit, and it lands six days after the same commission unanimously rejected Duke's data-center cost plan. For Duke shareholders, commissions reading this arithmetic decide whether the $103 billion build gets paid.

    Power

    Talen Energy sells 750 MW of capacity for $100 million a year, keeps the power merchant

    The seven-year Guernsey deal locks in the leg of the business Talen can price and leaves the electricity merchant, in a zone its own 10-Q shows trading far below the PJM market. It de-risks the leveraged AI-power trade that TLN holders own.

    Power

    Gov. Spanberger moves to force NextEra's sealed fitness memo into the $67 billion Dominion merger hearing

    The State Corporation Commission's evidentiary hearing starts November 17 with a ruling due by January 11, while traders who bet on deal spreads treat approval as near-certain. A rate freeze, a rate cap or a fitness finding would reprice both stocks.

    Power

    Entergy tells Louisiana regulators its Meta deal may not save customers a penny, amid a $33 billion buildout

    Sworn testimony in Louisiana shows Entergy's "data centers pay their own way" pledge is a promise, not a guarantee, while the company's $33 billion buildout is financed on the strength of that claim. Households and ETR shareholders are betting on the same good case.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.