Riot Platforms rents its Corsicana campus to Anthropic for 15 years at $28 billion and carries the build risk
The bitcoin miner's $28 billion, 910 MW Corsicana lease makes Riot a landlord paid in Anthropic's future cash, while Riot itself sells bitcoin and bridges debt to build the site. Two dated tests decide whether the stock's 50% discount closes: a December 31 loan maturity and February's report on the project financing.
Vincent Jiangtwo-minute read
Riot Platforms+6.66% — Riot Platforms, up 6.66 percent today, a bitcoin miner, has rented its entire Corsicana, Texas campus to Anthropic$350B — Anthropic, private, latest valuation $350B for 15 years: 910 megawatts of critical IT load, signed October 28 and effective November 4, worth about $28 billion over the initial term 1. The tenant pays $130 per kilowatt per month, up 3% a year, roughly $1.42 billion a year across the full site, and rent is due on every megawatt whether Anthropic fills it or not 12. Together with the 191 MW Rockdale lease and 50 MW from AMD+4.62% — AMD, up 4.62 percent today, Riot now carries about $38 billion of contracted data center revenue 13.
The landlord carries the build, the tenant carries no guarantee
The filing shows who pays for the buildout. Riot funds about $2 million per megawatt itself inside a $5.5 billion project, and must reimburse Anthropic up to $4.0 million per megawatt achieved, $3.64 billion if all 910 land, if it raises financing on acceptable market terms 2. If it cannot, the obligation becomes rent credits amortized at 12% a year 2.
The 10-Q describes no guarantee or credit support from Anthropic 2. The tenant's own books are the collateral: Anthropic prices its IPO at up to $1.4 trillion this week with $900.9 billion in multi-year compute commitments, $70.7 billion of it due within a year 5.
Riot's $13.1B enterprise value sits far below the $38B of rent it has under contract
Data
| Value | |
|---|---|
| Contracted DC revenue | $38B |
| Bernstein implied NOI value | $25.9B |
| Enterprise value | $13.1B |
Bitcoin pays for the AI campus until the debt arrives
Meanwhile the old business funds the new one. Riot sold 20,264 bitcoin for about $1.5 billion in nine months to pay for construction, and holds 2,418 coins and $669.1 million in cash 2. Mining revenue fell 28% to $116.0 million in the third quarter; total revenue was $181.4 million 1.
Riot's revenue has grown while operating cash has gone negative every quarter since 2024
- Revenue
- Operating cash flow
Data
| Revenue | Operating cash flow | |
|---|---|---|
| Q2 '24 | $70.02M | -$42.51M |
| Q3 '24 | $84.79M | -$56.33M |
| Q4 '24 | $142.56M | -$98.36M |
| Q1 '25 | $161.39M | -$122.06M |
| Q2 '25 | $152.99M | -$231.32M |
| Q3 '25 | $180.23M | -$114.01M |
| Q4 '25 | $152.83M | -$105.53M |
| Q1 '26 | $167.22M | -$182.65M |
| Q2 '26 | $174.24M | -$90.14M |
| Q3 '26 | $181.43M | -$214.33M |
The $573 million Rockdale bridge matures December 31, repayable from project financing for which the company reports "no assurance" 2. Bernstein values the contracted net operating income at about $25.9 billion against a $13.1 billion enterprise value and rates the stock Outperform with a $30 target; Jefferies−0.59% — Jefferies, down 0.59 percent today upgraded to Buy on November 10, saying Corsicana alone is worth about $16 a share 13.
On Rockdale itself, commissioning is on schedule: AMD's second 25 MW hit 35 MW in November, with 50 MW targeted for May 2027 4.
The trade works only if the debt lands. Watch December 31, when the bridge comes due, and February's fourth-quarter report, which should show whether Corsicana's non-recourse financing is real 12.