Power

Segra bet 22.5% of its fund on X-Energy. The prize is a fuel factory, not a permit

Segra Capital finished the third quarter holding $222 million of X-Energy, its biggest position, days after the NRC handed the first US small-reactor construction permit to a GE Vernova design. What the concentrated buyers own is the fuel chain: a licensed TRISO plant in Oak Ridge and a HALEU supply deal with Centrus.

Vincent JiangVincent Jiangthree-minute read

Drafted with AI from the documents listed under Sources, then edited and fact-checked by Vincent Jiang. How we work

Share
A researcher in safety glasses and purple gloves pours TRISO nuclear fuel particles into a steel tray at Oak Ridge National Laboratory
1 / 6Slide 1 of 6
TRISO fuel research at Oak Ridge National Laboratory. X-Energy's licensed TRISO-X plant, TX-1, is set to be the first commercial-scale advanced nuclear fuel plant built in the United States in more than 50 years.

One fund has 22.5% of its book in a single reactor stock

Segra Capital Management bought 1,202,283 more shares of X-Energy$1B — X-Energy, private, latest valuation $1B in the third quarter and finished holding 15,678,017, worth $222.3 million 1. That is 3.86% of the company and 22.5% of Segra's portfolio, its biggest position 1. Filing arithmetic marks the stake at about $14.18 a share, below the stock's $17.48 fifty-day average 12.

Segra's $222M stake dwarfs X-Energy's other recent 13F buyers

$0M$50M$100M$150M$200M$250MSegra Capital (Q3 '26)$222.3M22.5% of the fund's bookTwo Seas Capital (Q3 '26)$19.8MState Street (Q2 '26)$8.5MBlueCrest (Q2 '26)$7.4MTidal Investments (Q2 '26)$3.3M
Data
Value
Segra Capital (Q3 '26)$222.3M
Two Seas Capital (Q3 '26)$19.8M
State Street (Q2 '26)$8.5M
BlueCrest (Q2 '26)$7.4M
Tidal Investments (Q2 '26)$3.3M
Disclosed X-Energy positions from 13F filings as reported by MarketBeat on October 6, 2026; each bar's as-of quarter is marked on its label. US$ millions.1,2,5

Two Seas Capital lifted its own stake 39.4% to 1,394,413 shares, about $19.8 million 2. A quarter earlier, filings showed Peter Thiel's Thiel Macro buying 200,000 Class A shares, the smallest line in a rebuilt $419 million book 34. X-Energy rose 6.6% on October 6 to about $15.27, still 59% below its $37.10 twelve-month high, with Piper Sandler at $9 underweight against Guggenheim's $57 buy 52.

From $9 to $57: analyst targets bracket a $15.27 close

  • Share price
  • Estimate
$0$20$40$60Piper targetFiling basisOct 6 close50-day avg12-mo highGuggenheim target$37.1$15.27
Data
Share price
Piper target (estimate)$9
Filing basis$14.18
Oct 6 close$15.27
50-day avg$17.48
12-mo high$37.1
Guggenheim target (estimate)$57
X-Energy share-price reference points, US dollars per share. Filing basis is Segra's implied 13F cost; close, average and twelve-month high as reported by MarketBeat, October 6, 2026. Analyst targets are estimates.1,2,5

The first permit went elsewhere. The fuel line did not

On September 29 the Nuclear Regulatory Commission issued the country's first small-reactor construction permit, to the Tennessee Valley Authority for GE Vernova's 300-megawatt BWRX-300 at Clinch River, after a 14-month review 67. NuScale holds the only NRC-certified SMR design, yet no utility has applied to build one, and it booked $75,000 of second-quarter revenue 6. The tape prices these stocks by permits; this week's filings are pricing one by fuel.

X-Energy's TRISO-X unit holds a 40-year NRC license to fabricate high-assay fuel, and on September 24 it finished the shell of the 214,000-square-foot TX-1 plant in Oak Ridge, set to be the first commercial-scale advanced nuclear fuel plant built in the United States in more than 50 years 89. Interior build-out has begun, on the schedule the company laid out in August 1013.

One plant, 700,000 pebbles, eleven reactors

At capacity TX-1 is designed to produce about 700,000 pebbles a year, five tonnes of uranium, enough for up to 11 of the company's 80-megawatt reactors 89. Centrus signed the definitive supply contract on August 6, with X-Energy paying prepayments up the chain, while the supplier carries a $900 million DOE award, a $4.5 billion backlog and an Oklo deal on the same shelf 1112.

A hand holds a black graphite fuel pebble for a pebble-bed nuclear reactor, 60 millimetres across
A graphite fuel pebble for a pebble-bed reactor, 60 millimetres across; at capacity TX-1 is designed to produce about 700,000 pebbles a year.Weirdmeister

The bill lands on this year's IPO cash

X-Energy's quarter shows who pays: $54.6 million of revenue and grant income, up 154%, against a $105.3 million net loss, funded by $1.9 billion of liquidity from an April IPO that raised about $1.1 billion, with no debt 13. The Energy Information Administration prices SMR power at more than six times solar, and the only helium-cooled power reactors running, two in China, have struggled to stay online 14.

The permit queue decides who may build; the fuel line decides who gets to run. Watch the Dow project in Texas, the federal cost-share running to March 2027 13, and whether TX-1's equipment keeps its 2028 completion date 14.

Sources

  1. 1MarketBeat, Segra Capital Management LLC Acquires 1,202,283 Shares of X-Energy, Inc. $XE, 6 October 2026
  2. 2MarketBeat, Two Seas Capital LP Increases Position in X-Energy, Inc. $XE, 6 October 2026
  3. 3X, @topsecretstocks: Peter Thiel is betting on nuclear power, 4 October 2026
  4. 4The Motley Fool, Palantir Billionaire Peter Thiel Just Put 33% of His Portfolio Into These 3 Energy Stocks, 28 August 2026
  5. 5MarketBeat, X-Energy (NASDAQ:XE) Shares Climb 6% - Here's Why, 6 October 2026
  6. 6The Motley Fool via The Globe and Mail, Regulators Cleared a Small Modular Reactor for Construction. It Isn't a NuScale Design., 7 October 2026
  7. 7RTO Insider, NRC Authorizes TVA to Build 1st U.S. Small Modular Reactor, 29 September 2026
  8. 8World Nuclear News, Milestone for X-Energy's TRISO-X fuel facility, 25 September 2026
  9. 9Interesting Engineering, US nuclear fuel plant with 5-metric-ton uranium capacity moves closer to operations, 24 September 2026
  10. 10EnergyPulse via OpenSentiment, X-energy Starts Interior Work at TX-1 Advanced Nuclear Fuel Plant in Tennessee, 7 October 2026
  11. 11Centrus Energy via PR Newswire/Morningstar, Centrus Energy Signs LEU and HALEU Supply Agreement with X-energy, 6 August 2026
  12. 12SquawkNews, Transcript: Centrus Energy Q2 2026 Earnings Conference Call, 6 August 2026
  13. 13X-Energy, Inc. via GlobeNewswire/Finanznachrichten, X-energy Reports Second Quarter 2026 Results, 13 August 2026
  14. 14MIT Technology Review via Pipedot, X-energy and its helium-cooled nuclear reactors, 7 October 2026

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Reader comments

0 comments

    Power

    Taiwan's binding nuclear referendum passed with 62% of votes, and TSMC's Taiwan risk waits for 2028

    Taiwan's nine-in-one elections ended in a split: the KMT held Greater Taipei, the DPP took Taichung and the nuclear referendum passed as binding. For AI and chip investors the status quo holds, and the real decision waits for the early-2028 presidential vote.

    Power

    Taiwan votes 7 million to 4 million to end its nuclear-free policy as TSMC pledges $265 billion in the US

    The yes count cleared the turnout rule on Saturday night, but the first restarted reactor is years away, and TSMC's answer to Taiwan's power ceiling is already rising in Arizona and sitting in a Texas filing.

    Power

    Generac's $4.5 billion data center backlog earns about half the margin of its home business

    The data center order book tripled to $4.5 billion and the sell side says $295 a share; the fine print in the same outlook says each AI dollar converts at about half the profit of the home business. February's report settles which one the stock has been priced on.

    Power

    Virginia's commission rules by Jan. 11 on NextEra's $67 billion Dominion deal with the Robo Memo sealed

    The evidentiary record closed Nov. 24 with the Robo Memo sealed and NextEra's CEO putting the merger's case on demand that must be built, not load already contracted. Investors in NextEra and Dominion now hold a fixed Jan. 11 ruling date and a record they cannot read.

    Power

    Malaysia moved its 21% data-center forecast from 2030 to 2050; TNB meters show 850 MW of 4.5 GW drawn

    The same ministry told Parliament on November 4 that data centers would reach 21% of demand by 2030, and on November 26 that the same share arrives by 2050, while TNB's meters show 4.5 gigawatts connected and only 850 megawatts drawn. The gap lands on the merchants who built ahead of the load, YTL Power first.

    Power

    Benson keeps a DTE Energy director on her council as a $474 million rate ruling nears

    A DTE Energy director co-chairs Michigan's governor-elect transition while the utility sues to keep its political money, and in February the commission the new administration will help shape rules on DTE Electric's $474 million rate request. That single order carries the next two years of the company's regulated revenue.