TeraWulf pays up to $12 million a megawatt to build AI campuses its tenants don't fund

AI leases are 83% of TeraWulf's revenue, but each megawatt of new campus costs $10–12 million to build and the company, not its tenants, pays it. The next lease's rent and the first bond's coupon will decide who keeps the profit.

Richard TangRichard Tangthree-minute read
Share
TeraWulf chief executive Paul Prager
1 / 7Slide 1 of 7
TeraWulf chief executive Paul Prager. His company signs the AI leases and carries the construction bill for the campuses behind them.

TeraWulf's−5.69% — TeraWulf, down 5.69 percent today turn from bitcoin miner into AI landlord is now an income-statement fact: 83% of third-quarter revenue came from AI leases 25. The number that decides whether shareholders keep any of it came from chief operating officer Naz Khan on November 11 1. Building the Justified campus in Hawesville, Kentucky now costs $10–12 million per megawatt, up from $8–10 million at Lake Mariner, its New York campus 16. The leases are signed. The open question is who pays for the buildings, and at what cost of debt.

Tenants bring the chips, TeraWulf carries the shell

Anthropic$350B — Anthropic, private, latest valuation $350B signed the anchor lease at Justified: 20 years, about 401 megawatts, roughly $19 billion 56. Under TeraWulf's colocation model the tenant supplies its own chips 4. Core Scientific−0.70% — Core Scientific, down 0.70 percent today, the other big bitcoin-to-AI conversion, works out to roughly $9.3 million per megawatt on projects leased to CoreWeave−8.55% — CoreWeave, down 8.55 percent today, the GPU-cloud company 3. Its contracts let the customer fund up to $1.5 million per megawatt of facility cost and recover it through hosting credits, the backlog accounting we counted in megawatts on November 13 3. TeraWulf's tenants bring only chips; the shell, and the debt behind it, are TeraWulf's 4.

Justified costs up to $12 million a megawatt, above Lake Mariner's $8–10 million

$0M$5M$10M$15MLake MarinerCore ScientificJustified$11M
Data
Build cost per megawatt
Lake Mariner$9M ($8–10M)
Core Scientific$9.3M
Justified$11M ($10–12M)
Build cost per megawatt of campus, US$ millions. Ranges are the low and high ends TeraWulf and Coinpaper give; Core Scientific is a single estimate across its CoreWeave-leased projects. Bars sit at the midpoint where a range is given.1,3,6

What is signed is funded, the next 250 to 500 megawatts are not

Of 839 contracted megawatts, 102 were billing at quarter-end, and third-quarter adjusted EBITDA was negative $12.8 million 2. Management says it can fund the remaining Lake Mariner commitments, the Justified equity and interim letters of credit "all without accessing the equity capital markets" 2. That covers what is signed. Contracting 250–500 new megawatts a year, which needs $5–6 billion of cash at the top end against $2.4 billion on hand, is not 12.

TeraWulf's construction spend now towers over its revenue

The bill for building the campuses has outrun revenue every quarter since the pivot began

  • Capex
  • Revenue
$0M$500M$1,000MQ4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '2683% of revenue now AI leases
Data
CapexRevenue
Q4 '24$130.31M$34.99M
Q1 '25$93.69M$34.41M
Q2 '25$118.06M$47.64M
Q3 '25$224.62M$50.58M
Q4 '25$612.17M$35.84M
Q1 '26$522.95M$34.01M
Q2 '26$855.49M$44.77M
Q3 '26$851.9M$76.23M
Quarterly capital expenditure and revenue, US$ millions, from TeraWulf's SEC filings.8

The rent is fixed for 20 years, the bill is not

The Anthropic lease pays roughly $2.4 million per megawatt a year 4, the rent line we took apart on November 9. Against Justified's $10–12 million per megawatt to build, a fifth to a quarter of the bill comes back each year, and the rate is fixed for two decades 14.

Neoclouds such as Nebius−12.27% — Nebius, down 12.27 percent today, which own the chips and sell the compute, sign long-term deals at $20–25 million per megawatt, rates that bundle the GPUs' revenue, money TeraWulf's rent never touches 4. With rent locked, construction inflation lands on TeraWulf alone. Khan's answer to tenants asking a single-digit yield on cost: "go talk to someone else" 1.

Two prices will re-rate the stock

Morgan Stanley's November 12 model already charges for the gap: the discount rate on unstabilized signed sites lifted to 9% from 7%, modeled debt coupons of 8.5–12.5%, and a target cut to $47 from $65 with the Overweight rating kept 2. Google's credit backstop, signed November 4, is there to pull that coupon down; the coupon, the proceeds and the covenants remain open 267.

TeraWulf is timing its financing push for after Anthropic's IPO 1. Two numbers in that window will re-rate the stock: the rent on the next lease, and the coupon on the first bond.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading WULF

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Johnson Controls flags weak credit behind its record $23 billion AI backlog

    The same filing shows the 74% pre-tax jump had help: $149 million of firefighting-foam insurance money inside the cost lines, and a prior year flattered by the Bosch sale, so net income fell anyway. Shareholders are left pricing two things at once: earnings help the company cannot promise to repeat, and a $23.0 billion order book whose buyers need financing to pay.

    Data Center

    Hut 8's $27 billion of AI leases cover 949 megawatts; the other 6,910 need about $73 billion to build

    The Bitcoin miner's November 4 call put 949 megawatts under AI leases worth about $27 billion, against quarterly revenue of $71.1 million. Most of the 7,859-megawatt pipeline behind them has neither a tenant nor construction underway.

    Data Center

    WhiteFiber's cloud revenue grew 0.4% because a departing customer paid $3.4 million to leave

    The Q3 10-Q shows the growth was a $3.4 million exit fee from a customer who left, while lease liabilities rose 6.6 times in nine months. Whose money moves: anyone holding WYFI, which opened Friday at $10.34 against a $34.33 analyst target.

    Data Center

    Prologis sues Trenton in federal court nine days after voters banned its data center

    Nine days after Trenton voters banned large data centers, Prologis is testing in federal court whether permits issued before a vote can override it, and the answer prices political risk for every data-center landlord.

    Data Center

    S&P warns data-center cyber risk is growing against $2 trillion of assets and $10 billion of premium

    S&P Global Ratings counts insurable data-center assets passing $2 trillion by 2027 against about $10 billion of new premium in 2026, and warns one attack could hit many tenants at once. Landlords and regulators are already rationing tenants by credit rating, and the Fed is set to keep raising the cost of the debt that funds the build-out.

    Data Center

    Wistron posts a record NT$1.15 trillion AI-server quarter funded by a $1.47 billion share sale

    Wistron posted a record NT$1.149 trillion quarter and is spending NT$12.87 billion for demand expected in 2028, but the growth burns cash, a $1.47 billion September share sale funds it, and the US states that buy the racks just elected governors who ran against data centers.