Power

Vistra CEO calls data-center power queues overstated as Texas logs 194 GW of requests against a 91 GW peak

James Burke says the queues behind America's data-center load forecasts are inflated by developer speculation, and wants higher collateral and take-or-pay transmission contracts. The filings behind the words show a company split in two: contracted nuclear megawatts that need no queue, and a merchant 2028 with a fifth of its output unsold.

Vincent JiangVincent Jiangthree-minute read

Drafted with AI from the documents listed under Sources, then edited and fact-checked by Vincent Jiang. How we work

Share
James Burke, chief executive of Vistra, seated in a navy suit and blue tie during a CERAWeek interview
James Burke, Vistra's chief executive, interviewed at CERAWeek 2026 in Houston.

The queue is inflated, says the company selling into it

Vistra+0.52% — Vistra, up 0.52 percent today chief executive James Burke told investors on November 6 that the interconnection queues behind forecasts of American data-center load growth are overstated 1. "Load interconnect queues were overstated across the country and especially in [ERCOT], driven by speculation from developers," he said, in remarks Utility Dive reported on November 24 1. He asked for guardrails in the same breath: tougher interconnection standards, higher collateral and take-or-pay transmission contracts, paying for reserved capacity even unused 1. Texas's utility commission already charges a $100,000 study fee and $50,000 per megawatt of refundable security to enter the queue 2; the chief executive wants the bar higher.

"The pacing was already being impacted ahead of the election," he said, "but our plans have always had a more conservative view of the AI build-out" 3. His growth outlook did not move: 4 to 6 percent a year in ERCOT, the Texas grid, through 2030 1.

A record quarter, with a bigger 2027 promised

The quarter behind the remarks was Vistra's biggest: adjusted EBITDA up more than 50 percent to $2.378 billion, 2026 guidance raised to $7.1 billion to $7.5 billion, and a first 2027 range of $7.7 billion to $8.5 billion 4. That range already counts the 5,500 megawatts of Cogentrix gas plants closed on October 30 for $2.2 billion in cash plus five million shares 5.

Half the fleet needs no queue: Meta holds 2,609 megawatts

Half the company does not need the queue: Meta+2.66% — Meta, up 2.66 percent today holds 20-year nuclear contracts for 2,609 megawatts from the Perry and Davis-Besse plants, first delivery late 2026, full by end-2027, with the 433 megawatts of uprates only delivering from 2031 5. The same filing carries a $1 billion commitment to KKR's Helix AI-infrastructure fund, its second half payable at Vistra's election whether or not milestones are met 5. The merchant half is the exposed one, and its armor is the hedge book 4.

Two cooling towers of the Perry Nuclear Power Plant in Ohio, one venting steam, seen from the plant entrance road
Perry Nuclear Power Plant in Ohio, one of the two Vistra plants whose output Meta has contracted for 20 years. Its 2,609 megawatts need no interconnection queue.Cards84664, CC BY-SA 4.0

Vistra has sold forward 98% of 2027 output, and only 78% of 2028

The unpriced year is 2028, where a Texas moratorium would land

0%50%100%20262027202878%
Data
Hedged share of expected generation
2026100%
202798%
202878%
Hedged share of Vistra's expected generation volumes as of October 30, 2026, by delivery year, from the company's third-quarter earnings release of November 6, 2026. Figures are approximate as reported.4

194 gigawatts of requests against a 91-gigawatt peak

The Texas numbers back the skepticism. ERCOT's audit has conditionally classed 204 large-load projects totaling 66.4 gigawatts as base load and 158 more, 127.9 gigawatts, as studied: about 194 gigawatts of requests against a record 91-gigawatt peak set this year 61.

ERCOT's queue holds 194 GW of requests, more than twice the record peak

0 GW50 GW100 GW150 GWRecord peak demandClassed as base loadUnder study127.9 GW
Data
Gigawatts
Record peak demand91 GW
Classed as base load66.4 GW
Under study127.9 GW
Large-load interconnection requests in ERCOT by audit status, gigawatts, against the grid's record peak demand set in 2026. The 66.4 GW conditionally classed as base load and the 127.9 GW under study total about 194 GW. Sources: Gibson Dunn client alert, November 18, 2026, and Utility Dive, November 24, 2026.6,1

The audit, the inauguration and the fourth quarter will settle it

The audit report lands on December 10; environmental permit reviews resumed on November 16, energization approvals stay paused, and Governor-elect Gina Hinojosa, who pledges a moratorium until the legislature passes protections, takes office on January 19 6. Vertiv is selling the wait too: its outdoor medium-voltage UPS, built to speed grid connections, ships from mid-2027 7. The late-February fourth-quarter report should show how much of 2028, 78 percent hedged 4, has been sold 3. The shares closed at $120 on November 24, 14 percent below Election Day's roughly $140 1, and slid further the next day 8. At about 13 times forward earnings 3, the price pays for the megawatts under contract, not the queue its own chief executive calls inflated.

Sources

  1. 1Utility Dive (via Yahoo Finance), Midterms provide clarity on data center development: Vistra CEO, 24 November 2026
  2. 2Steptoe & Johnson via JD Supra, Texas Raises the Bar for Large Load Interconnections: What 16 TAC §25.194 Means for Your Next Project, 20 October 2026
  3. 3EnergyPressWire (TIKR), Vistra Just Dropped 16% in a Month, but Its Plans Always Had a More Conservative View of the AI Build-Out, 19 November 2026
  4. 4Vistra Corp. news release, Vistra Reports Third Quarter 2026 Results, 6 November 2026 (SEC Form 8-K, Exhibit 99.1)
  5. 5Vistra Corp., Form 10-Q for the quarterly period ended 30 September 2026, filed 9 November 2026
  6. 6Gibson Dunn client alert, Updated: Texas Data Center Critical Dates and Procedures Following the 2026 Elections, 18 November 2026
  7. 7Engineering News, Vertiv Introduces Medium-Voltage Power System to Help AI Data Centres Connect to the Grid Faster, 23 November 2026
  8. 8Blockchain.news, Vistra (VST) Stock Price Prediction: Bearish momentum meets analyst support after a sharp pullback, 25 November 2026

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading VST

Reader comments

0 comments

    Power

    Investors sue NuScale as quarterly revenue falls to $281,000 and the stock trades below its cash pile

    Quarterly revenue has fallen to $281,000, the equity now trades below its own $1.86 billion cash pile, and the January 11, 2027, lead-plaintiff deadline puts class-period holders on the clock.

    Power

    X-energy wins NRC permit for four reactors at Dow's Texas plant, first US nuclear build at an industrial site

    The NRC's first high-temperature gas-cooled permit in over 50 years proves the Xe-100 can be built at a chemical plant. The money gate now sits with Dow in 2027, while X-energy burns $123 million a quarter and the whole nuclear sector de-rates.

    Power

    Bloom Energy locks $123 million of outsourced fuel-cell supply through 2027 in a Korean filing

    A Korean regulatory filing disclosed November 25, for a purchase order dated November 24, shows Bloom locking outsourced fuel-cell production at Seojin System's Vietnam plant on 45-day payment terms, while the stock trades below half its $351.28 peak and bulls and bears fight over the same $181 million of quarterly cash burn.

    Power

    Pennsylvania's consumer advocate asks regulators to bill data centers, not PPL customers, $157 million

    The complaint against PPL Electric would move a $157 million power-line bill onto the data center that caused it, and this week Gov. Shapiro's office, environmental groups, residents, Amazon and the industry coalition all formally picked sides. The commission's ruling, due July 2027, will set the price of connecting every future Pennsylvania data center.

    Power

    PG&E customers prepay for wildfire costs, but the $18 billion fund for new fires is empty

    Ratepayers prepay wildfire costs today while shareholders' $300 million a year into the new $18 billion account does not start until 2029, and the account sunsets if never activated. That leaves PG&E's equity, already rated below investment grade, as the first loss on any major new fire.

    Power

    Google offers to pay American Electric Power $10.8 million to speed power to its Columbus data center

    The first voluntary, corporate-funded transmission upgrade on a US regulated grid now sits before Ohio regulators. How they rule decides whether hyperscalers can buy speed on the grid, and whose bills fund the rest of AEP's $100 billion buildout.

    Subscribe to TheInference for free