Comfort Systems grew revenue 53.7%, backlog nearly doubled to $17.8 billion, and the stock fell

The contractor that cools and wires AI data centers grew revenue 54% and nearly doubled its backlog in a year, and the stock still fell. The filing shows what the market is arguing about: growth is arriving as estimate revisions and customer prepayments while gross margin sits still.

Richard TangRichard Tangtwo-minute read
Share
Workers install overhead ductwork and HVAC pipe in a mechanical room under construction
1 / 6Slide 1 of 6
The work the quarter was built on: mechanical crews installing ductwork and cooling pipe. Comfort Systems' technology customers, mostly data centers, produced 61% of third-quarter revenue.

Comfort Systems USA+5.45% — Comfort Systems USA, up 5.45 percent today, the Houston contractor that cools and wires AI data centers, filed the biggest quarter in its history on October 22 1. Revenue grew 53.7% from a year earlier, to a record $3.77 billion 1. Its backlog of contracted work nearly doubled in twelve months, to $17.8 billion 1. Earnings and revenue beat Wall Street's estimates for the sixth quarter running 2.

The stock still fell the morning after, to $1,146, in a slide tied to anxiety over who funds AI capital spending 3, and it now trades about 45% below its June high 3. The quarter is evidence that the buildout's binding constraint has moved downstream, from chips to the crews that install cooling and power. The market's complaint is that the margin line has not yet charged for it.

Quarterly revenue has nearly tripled since 2023 as data-center work took over

$1B$2B$3B$4BQ3 '23Q1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26Tech customers now 61% of revenue
Data
Revenue
Q3 '23$1.38B
Q4 '23$1.36B
Q1 '24$1.54B
Q2 '24$1.81B
Q3 '24$1.81B
Q4 '24$1.87B
Q1 '25$1.83B
Q2 '25$2.17B
Q3 '25$2.45B
Q4 '25$2.65B
Q1 '26$2.87B
Q2 '26$3.27B
Q3 '26$3.77B
Quarterly revenue has nearly tripled since 2023 as data-center work took over1,9

The chain now runs from a GPU to a pipefitter

AI models need compute, compute needs buildings, and buildings need cooling, switchgear and wiring, which is mechanical and electrical contracting. Technology customers, mostly data centers, produced 61% of this quarter's revenue 1. A year ago the share was 46% 1. The backlog doubling was organic: same-store backlog reached $17.4 billion 4, and chief executive Brian Lane called the demand "relentless" 4.

Growth is arriving as revisions and prepayments, not price

Gross margin held flat at 24.8% 5. Comfort Systems recognizes revenue as costs are incurred, so upward revisions on jobs already underway added 4.5% to the quarter 1. The cash line is sharper. Nine-month operating cash flow reached $2.54 billion 1. Most of it, $1.69 billion, was customers paying before the work is done 1.

Gross margin climbed for two years, then flattened near 25% as revenue took off

15%20%25%30%Q2 '23Q4 '23Q2 '24Q4 '24Q2 '25Q4 '25Q2 '2625.9%
Data
Gross margin
Q2 '2317.6%
Q3 '2320.1%
Q4 '2320.6%
Q1 '2419.3%
Q2 '2420.1%
Q3 '2421.1%
Q4 '2423.2%
Q1 '2522%
Q2 '2523.5%
Q3 '2524.8%
Q4 '2525.5%
Q1 '2626.3%
Q2 '2625.9%
Gross margin as a percent of revenue, by quarter. It climbed for two years, then stalled near 25% even as revenue grew 50% a year. Source: Comfort Systems USA quarterly figures from SEC filings [9].9

Advance payment is what scarcity looks like from the buyer's side. The 10-Q expects demand to stay high through 2027 while labor costs and supply delays persist 1, and the company spent $211 million in the quarter on capacity, including a Texas modular builder that shifts work from job site to factory 21.

Succession lands on top of the open question

No forward guidance came with the release 6. Bill George, chief financial officer since 2005 and a founder of the company, retires once the annual report is filed, and chief accounting officer Julie Shaeff takes over 7. Friday morning's conference call is the first test of both. The bear case is that backlog can be canceled, and the company itself warns it has limited predictive value 8.

Customers do not prepay on this scale for work they expect to cancel. The projection, and it is one: flat margin turns into pricing power as the labor constraint binds. The prepayment line is the evidence, and the call is where it gets tested.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading FIX

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    NetApp counts 350 AI deals instead of reporting AI revenue, and insiders sold 33 times without buying

    NetApp closed its Peak:AIO purchase with no price disclosed, in the same week the books closed on a period of insider selling: 33 sales in six months, not one purchase. The stock's premium rests on an AI business the company has never reported as a revenue line.

    Data Center

    Microsoft can wait out data-center protests; its landlord Pure Data Centres cannot, with $1 billion at stake

    Activists broke into Microsoft's Amsterdam data-center site at the start of a 16-country protest weekend. The exposure is not Microsoft's; it belongs to the developers and miners paying interest before revenue, and Texas just moved against them.

    Data Center

    Texas Governor-elect Gina Hinojosa wants a SpaceX pause as Goldman syndicates $40 billion of chip debt

    Goldman and Apollo are syndicating $40 billion of SpaceX chip debt secured against a Texas buildout that the state's new governor-elect wants paused. Lenders bought pre-election terms into a post-election state.

    Data Center

    Fermi's ousted CEO sold $13 million of stock into a 52-week low, then said it 'should be soaring'

    Toby Neugebauer, ousted as Fermi's chief executive in April, sold 7,657,800 shares for about $13 million in three sessions, 5 million of them on the day the stock touched its 52-week low. The next morning he demanded the company be sold, with its only tenant lease unsigned and $62.5 million of cash against a $737.9 million trailing loss.

    Data Center

    Data-center orders tripled at Carrier, and the cost of rolling its debt doubled

    On November 4 Carrier sold $1.5 billion of notes at more than double the coupon of the paper they retire, between record data-center orders and a $3.1 billion European write-down. The coupon is the market's new price for financing the AI buildout's supply chain.

    Data Center

    Oracle's $165 billion New Mexico campus permit slipped past December 7 as lenders sell the debt

    Oracle's $664 billion backlog assumes its biggest Stargate campus switches on. The New Mexico air-permit decision just slipped past December 7, the project's lenders are heading for the exits, and the stock's 8% drop was blamed on politics instead.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.