CenterPoint's $70.7 billion capital plan hangs on 12 GW Texas froze until a December audit

The utility told investors 12 GW of large-load demand will energize on its Houston grid by 2030 and lifted its ten-year capital plan to $70.7 billion. AEP's 10-Q, filed a day later, shows ERCOT has paused the review that decides whether any of it connects.

Richard TangRichard Tangthree-minute read
Share
High-voltage transmission towers over a Texas pasture
Transmission lines in East Texas. CenterPoint's $70.7 billion plan prices 12 GW of new large load onto its Houston Electric grid, pending ERCOT's December audit.

CenterPoint's+0.59% — CenterPoint, up 0.59 percent as of its last quote newly raised $70.7 billion capital plan rests on demand Texas has ordered verified and nobody has checked yet 2. Its third-quarter investor update, filed October 27, expects about 12 GW of new large load energizing on its Houston Electric grid by 2030, against a system peak of 21 GW today, a jump of more than 55% 1.

A day later, American Electric Power+0.02% — American Electric Power, up 0.02 percent as of its last quote, another utility that wires parts of Texas, described the same queue from the other side in its quarterly filing. Governor Greg Abbott ordered every Batch Zero load verified and every data-center project above 25 MW audited, and ERCOT, the grid operator for most of Texas, has paused the classification and study work that decides who connects 2. The spending is committed before anyone has confirmed the megawatts.

CenterPoint's ramp to 12 GW clears only if ERCOT's audit keeps the queue standing

ERCOT paused the study behind this ramp; December decides what stands

  • Expected cumulative energization
  • Estimate
0GW5GW10GW15GW2027202820292030Queue paused since August; auditreports due December 10
Data
Expected cumulative energization
2027 (estimate)3GW
2028 (estimate)8GW
2029 (estimate)11GW
2030 (estimate)12GW
CenterPoint forecast of October 27, 2026; figures are guidance, not reported energization. Source: investor update, slide 12.1

Only part of the queue even qualifies

Batch Zero is the one-time process ERCOT set up to review large-load interconnection requests, primarily loads of 75 MW or greater, ahead of a recurring batch framework 2. It splits requests into two categories, and the split decides timing.

Base load is capacity ERCOT counts on for planning; the amount included is set in a determination expected in December 2026 1. Studied load is the slower path: further study, allocations in April 2027 that can come in below what a project asked for, and reclassification into the category can delay a project's energization 1.

CenterPoint sorted its own 17 GW of submissions ahead of ERCOT's ruling 3, and its base-load bar already requires completed studies plus a security deposit covering the interconnection 4. About 10 GW meets that bar; 5 GW qualifies for neither category 1. The slides never mention the pause; their endnotes concede that actual customer demand may run below the load interconnected 1.

Ten of CenterPoint's 17 submitted gigawatts meet its base-load bar

0 GW5 GW10 GW15 GW20 GWSubmitted to ERCOT17 GWMeets base-load bar10 GWQualifies for neither5 GW
Data
Value
Submitted to ERCOT17 GW
Meets base-load bar10 GW
Qualifies for neither5 GW
CenterPoint's own sorting of its Batch Zero submissions ahead of ERCOT's determination; the remainder sits between the two. Sources: CenterPoint investor update; Utility Dive; Colocation Scout.1,3,4

The audit now sets the schedule

ERCOT's July operations report shows what the state is checking: of the large loads approved to energize, under half their approved capacity showed up at the month's peak 5. New data-center halls fill slowly 5, so that gap is timing as much as intent, but it is measurable and Texas is measuring it.

Every Batch Zero developer must answer a formal information request within ten business days, notarized, on pain of exclusion from the process, and ERCOT files its verification and community-impact reports with the state commission on December 10 5. Abbott ordered the freeze in August, with about 474 GW of connection requests pending, roughly 90% of them data centers 6. Until verification finishes, no large load in the queue will be authorized to energize 2.

The money is posted, and ratepayers hold the other side

Standing in this queue now costs real money. AEP Texas received about $2 billion of financial security from developers behind 45 GW of requests 2. A state rule adopted in September requires $50,000 per MW before a project even enters a study, under a law written to reduce stranded infrastructure costs 2. If the load survives the audit, CenterPoint's shareholders own the growth; if it does not, Houston ratepayers still own the wires.

Indiana, which CenterPoint also serves, previews the politics: the Hoosier Environmental Council told the Indiana Utility Regulatory Commission that a roughly 700 MW data-center deal there sends the economic benefit out of state while Hoosiers keep the pollution and the grid costs 7.

December's survival rate is what the plan is worth

If most of the queue survives, Texas has to find that much new supply; if it shrinks, the wires already in the plan still have to be paid for by someone 5. CenterPoint is already preparing a Batch One submission for next year 3. Watch ERCOT's base-load determination, then the state commission's December 17 meeting, where the audit reports are discussed 5. The survival rate, how many requested megawatts are still standing, is the number that reprices the plan and decides when Houston's queued load can plug in.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AEP

Reader comments

0 comments

    Power

    Evergy Sees $4 Billion of Generation Behind a Deal Digital Realty Has Not Signed

    A 1.4-gigawatt letter of intent at a former Kansas ammunition plant is the durable news in a weather-inflated quarter. The funding decisions that come first are a Missouri rate order in December and a new capital plan in February; the contract is not expected until the first half of 2027.

    Power

    China's turbine export push aims at GE Vernova's 122-gigawatt queue as Dongfang books 30 in Canada

    Beijing wants an independently controlled gas-turbine supply chain by 2030, and Dongfang Electric booked 30 turbines for Canadian data centers in late October. The five-year queue GE Vernova monetizes, 122 reserved gigawatts inside a $197 billion backlog, sits on the other side of that plan.

    Power

    Michigan AG asks regulators to reopen DTE Energy's 1-gigawatt Google deal, with $44.2 billion riding on it

    Dana Nessel's November 2 petition attacks the protections behind Michigan's October approval of DTE's Google contracts; the utility's $44.2 billion capital plan and roughly $1 billion a year of new equity ride on that gigawatt.

    Power

    Virginia Democrats ask regulators to reject NextEra's $67 billion Dominion takeover

    The comment window closed with commission staff, the governor and five House Democrats against the deal, and Dominion's own 10-K shows the data-center risk priced thinner than the marketing: 28% of sales, a conditional 2027 contract regime, and $463 million of new rider recovery on the table.

    Power

    Siemens orders jump 58% to a record €34.8 billion as AI data centers wait five years for power gear

    Data-center orders doubled in Siemens's record quarter, and the backlog behind it rests on customers waiting more than five years for power equipment. Beijing has told its turbine makers to use that shortage to break Western dominance by 2030, which is what investors in Siemens, GE Vernova and Mitsubishi Heavy now have to price.

    Power

    Centrus begins commercial HALEU sales as revenue falls 26% and contingent fuel orders reach $5.4 billion

    The output runs on rights the Department of Energy granted and can revisit, even as DOE's own purchases shrink. Centrus enters its December 7 investor day with about $2.2 billion of cash, a widening gross loss, and a $5.4 billion order book that is mostly contingent and mostly conventional reactor fuel.

    Subscribe to TheInference for free