Power

Constellation's 18.5-year nuclear contracts meet the November 3 midterms and the grid cost fight

Constellation signed a 20-year Google deal and a multi-decade PPA book that bets on uninterrupted data-center growth. If Democrats take the House on November 3, its customers face bigger grid bills and tighter permits, and regulators face pressure to cap returns on its contracts.

Richard TangRichard Tang · 2 min read
Share
Aerial view of the Clinton nuclear power station in Illinois
1 / 6Slide 1 of 6
The Clinton nuclear power station in Illinois, which Constellation contracts to Meta under a 20-year deal.

Constellation Energy−0.82% — Constellation Energy, down 0.82 percent today signed a 20-year nuclear power deal with Google on Tuesday, and ten days before the November 3 midterms it sits on both sides of the election trade 12. Lee Seung-hun of IBK Investment Securities and Choi Bo-won of Korea Investment Securities put power producers like Constellation among the winners, on long-term electricity demand. The same analysts put data-center operators among the losers, facing tighter permitting and bigger grid bills if Democrats take the House. 12

Constellation's contracted nuclear book sits on both ends: its revenue comes from the customers the other side wants to tax. 2

The contracts assume two decades without a repricing

Google signed for 20 years; Constellation added roughly 920 MW of nuclear PPAs in the second quarter alone, averaging about 18.5 years in duration, with Microsoft+0.64% — Microsoft, up 0.64 percent today backing the Crane restart and Meta−1.36% — Meta, down 1.36 percent today taking Clinton. 2 These are not bets on next year's power price. They are bets that the customers behind them can build and run data centers for two decades without regulators repricing the deal in between.

Revenue jumped 63.8% in Q1 '26 as the contracted nuclear book swelled

  • Revenue
  • Operating income
$0B$5B$10B$15BQ3 '24Q4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26$7.5B
Data
RevenueOperating income
Q3 '24$6.55B$1.47B
Q4 '24$5.38B$0.97B
Q1 '25$6.79B$0.45B
Q2 '25$6.1B$0.95B
Q3 '25$6.57B$1.09B
Q4 '25$6.07B$0.6B
Q1 '26$11.12B$2.33B
Q2 '26$7.5B$0.58B
Constellation Energy quarterly revenue and operating income from its SEC filings, in USD billions, retrieved October 25, 2026.3

A Democratic Congress that makes operators pay more of grid-upgrade costs and tightens permits would likely slow exactly that build-out. New York's temporary moratorium on large data centers is the template researchers say could spread to the Northeast and Midwest if Democrats win decisively. 1

The valuation already carries the risk

The stock already prices some of this.

CEG is down 26% this year, though it has returned 146% over three years. 2

Three years of gains, one year of doubt at Constellation

-50%0%50%100%150%3-year TSR146.36%1-year TSR-22.23%Year to date-26.08%
Data
Value
3-year TSR146.36%
1-year TSR-22.23%
Year to date-26.08%
Total shareholder return (TSR) for Constellation Energy, the share price change plus dividends, as reported by Simply Wall St, October 22, 2026.2

The most-followed valuation narrative calls it 23% undervalued at a $350 fair value, and names the real risk: regulators capping returns on long-dated nuclear contracts. 2

What to watch after November 3

Demand for Constellation's power is likely durable even if Democrats win: AI build-outs need firm, carbon-free supply, and a single election is unlikely to end that. What can change is who pays for the grid between the plant and the server hall. If data centers shoulder their own grid costs and permitting holds, Constellation's contracted book keeps its value; if permitting freezes projects, the backlog waits longer to convert to cash flow. Which of those binds depends on how decisively Democrats win and how far regulators go.

Until the vote, CEG shareholders are holding an unresolved question about who pays for the grid. Two markers tell you first: whether the moratorium logic spreads beyond New York, and whether any state utility commission moves to reprice a co-located data-center contract, long before any PPA is renegotiated.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading CEG…

Reader comments

0 comments

    Power

    Centrus paid $116 million for its centrifuge casing maker as the stock hit a 52-week low

    The only US company with a licensed centrifuge route to advanced-reactor fuel spent $116 million to own its casing supplier, and the stock hit a 52-week low the same week. The November 4 third-quarter report is the first reading on whether the build-out turns into enrichment revenue.

    Power

    Evergy reports November 5 before Missouri hearings on its 710-megawatt gas plant

    Evergy reports Q3 on November 5, three weeks before Missouri hearings on its 710-megawatt gas plant. Data centers are supposed to pay for the buildout through an extra charge; Kansas counties are still writing the rules, and the street is split.

    Power

    New Jersey's biggest AI campus brings its own power, and PSEG's growth now rests on its nuclear fleet

    Bloom Energy says the first fuel-cell block at Nebius's 300 MW Vineland campus is ready, so New Jersey's most visible AI load arrives with its own power instead of as demand for the local utility, PSEG. Broker targets fell through October to between $69 and $85 against an $82.58 consensus, and third-quarter results on November 2 will test what growth is left to pay for.

    Power

    PG&E has energized 174 megawatts of its 12.87-gigawatt data center pipeline and cut $2 billion of capex

    PG&E's Q3 deck shows a 12.87-gigawatt data-center pipeline against 174 megawatts actually energized, while a $2 billion capital cut pushes new large load behind the initial 1.8-gigawatt tranche. The AI load growth story and the wildfire liability problem now share one choke point: the California Public Utilities Commission.

    Power

    PPL's 31.8 GW pipeline in advanced planning waits on a transmission tariff; plan update November 6

    PPL Electric proposed 16 miles of line for a data center near Mount Carmel and picked its Allenwood route, while Governor Shapiro's PUC petition challenges exactly the layer of the grid those projects occupy. The annual business plan update on November 6 is the first hard number on the buildout, and the stock's premium to every utility peer has to be earned by it.

    Power

    Fluence's AI power bet faces a securities-fraud suit after three guidance breaks and a 73% fall

    A securities-fraud class action alleges Fluence's fiscal 2026 guidance rested on contract factories that were never ready, and the company's own disclosures back the timeline: three guidance breaks in eight months took the stock down about 73%.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.