New Jersey's biggest AI campus brings its own power, and PSEG's growth now rests on its nuclear fleet

Bloom Energy says the first fuel-cell block at Nebius's 300 MW Vineland campus is ready, so New Jersey's most visible AI load arrives with its own power instead of as demand for the local utility, PSEG. Broker targets fell through October to between $69 and $85 against an $82.58 consensus, and third-quarter results on November 2 will test what growth is left to pay for.

Richard TangRichard Tang · 3 min read
Share
The Salem and Hope Creek nuclear plant on Artificial Island, New Jersey, seen across Delaware Bay, its cooling tower venting steam
1 / 6Slide 1 of 6
PSEG's Salem reactors, right, and Hope Creek on Artificial Island in New Jersey. With AI campuses bringing their own power, the merchant nuclear fleet is the growth story the market is waiting on.

On October 23 Bloom Energy−11.99% — Bloom Energy, down 11.99 percent today said the first fuel-cell power block at Nebius's 300-megawatt campus in Vineland, New Jersey, is ready for customer use 1. Nebius−0.89% — Nebius, down 0.89 percent today is an AI cloud provider building Vineland under a multiyear Microsoft+0.64% — Microsoft, up 0.64 percent today agreement, and because the fuel cells sit on site, the state's most visible AI project shows up as its own power plant 1.

For Public Service Enterprise Group (PSEG−1.06% — PSEG, down 1.06 percent today), which owns New Jersey's regulated power and gas networks along with a merchant nuclear fleet, that pattern explains a five-week run of broker target cuts, followed on October 22 by HSBC starting coverage at Hold 23.

The load arrives behind the utility's meter

Nebius signed with Bloom in May for about 250 megawatts of guaranteed capacity, in three ten-year phases, with service fees of up to $2.6 billion 1. Planning approvals took three months, and the first block was ready two months after them 1. Bloom installs, operates and maintains the fuel cells on site, so each block of power reaches the campus directly instead of arriving as new demand on PSE&G's wires 1.

PJM, the regional grid operator, is writing the pattern into its rules: under its pending Bring Your Own New Capacity filing, a new large load that brings new generation can avoid exposure to PJM's proposed resource-adequacy charges 4. Bloom's own quarter shows who already gets paid for that work, with revenue more than doubling year over year 1.

The target cuts have a cause beyond elections and rates

HSBC's new analyst Meike Becker wrote that the firm does "not see data center load growth as a significant part of PSEG's investment case" 2. The growth HSBC does model is modest, with rate base and earnings per share both compounding at 7% to 2030, below the peer average 2.

The other houses kept cutting between September 18 and October 20 anyway 3, and BTIG kept its Buy while blaming political uncertainty and interest-rate pressure 5. Politics points the same way, since analysts expect a Democratic Congress to push more grid-upgrade cost onto data-center operators, and at least 47 large projects have already been delayed or withdrawn this year 7.

Where PSEG does pursue wires, the clock is slow: Maryland estimated about 30 months just to assess the application for its proposed 67-mile transmission line 8.

PSEG targets fell through late September and October, and the newest sits almost at the share price

$0$20$40$60$80$100Jefferies, 9 Oct$69HSBC, 22 Oct$72.5New coverage at Hold, not a cutBarclays, 12 Oct$76Scotiabank, 30 Sep$77Deepest cut, from $92Goldman Sachs, 15 Oct$83BTIG, 20 Oct$84Morgan Stanley, 20 Oct$85Argus, 29 Sep$86PSEG close, $72.02, 23 Oct
Data
Value
Jefferies, 9 Oct$69
HSBC, 22 Oct$72.5
Barclays, 12 Oct$76
Scotiabank, 30 Sep$77
Goldman Sachs, 15 Oct$83
BTIG, 20 Oct$84
Morgan Stanley, 20 Oct$85
Argus, 29 Sep$86
Price targets from broker notes dated September 29 to October 22, 2026, US dollars; HSBC's is a new Hold rating and the rest are cuts. Sources: MT Newswires via MarketScreener, StreetInsider, ad-hoc-news.2,3,5

A signed nuclear contract is the asset worth underwriting

What PSEG can sell into an AI power market is reactor output, and HSBC flags exactly that upside from contracting similar to recent independent-power deals 2. The template already touches Salem, the southern New Jersey plant PSEG operates and owns 57% of: Google's 20-year agreement with Constellation backs $4.3 billion of uprates across 11 PJM reactors, Salem is expected to be among the sites, as we reported on October 15, and PSEG plans stretch uprate applications for Salem Units 1 and 2 in the second quarter of 2027 4.

HSBC expects PSEG's capital plan to reach about $5.3 billion a year by 2030, with the entire increase in the networks business 2.

Results land on November 2, with management guiding to $4.28 to $4.40 a share 6. If PSEG Nuclear signs a data-center contract of its own, the AI boom reaches the utility as a sale of nuclear power. Until it does, the consensus target has no engine, and the cuts continue.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading PEG…

Reader comments

0 comments

    Power

    Centrus paid $116 million for its centrifuge casing maker as the stock hit a 52-week low

    The only US company with a licensed centrifuge route to advanced-reactor fuel spent $116 million to own its casing supplier, and the stock hit a 52-week low the same week. The November 4 third-quarter report is the first reading on whether the build-out turns into enrichment revenue.

    Power

    Evergy reports November 5 before Missouri hearings on its 710-megawatt gas plant

    Evergy reports Q3 on November 5, three weeks before Missouri hearings on its 710-megawatt gas plant. Data centers are supposed to pay for the buildout through an extra charge; Kansas counties are still writing the rules, and the street is split.

    Power

    PG&E has energized 174 megawatts of its 12.87-gigawatt data center pipeline and cut $2 billion of capex

    PG&E's Q3 deck shows a 12.87-gigawatt data-center pipeline against 174 megawatts actually energized, while a $2 billion capital cut pushes new large load behind the initial 1.8-gigawatt tranche. The AI load growth story and the wildfire liability problem now share one choke point: the California Public Utilities Commission.

    Power

    Constellation's 18.5-year nuclear contracts meet the November 3 midterms and the grid cost fight

    Constellation signed a 20-year Google deal and a multi-decade PPA book that bets on uninterrupted data-center growth. If Democrats take the House on November 3, its customers face bigger grid bills and tighter permits, and regulators face pressure to cap returns on its contracts.

    Power

    PPL's 31.8 GW pipeline in advanced planning waits on a transmission tariff; plan update November 6

    PPL Electric proposed 16 miles of line for a data center near Mount Carmel and picked its Allenwood route, while Governor Shapiro's PUC petition challenges exactly the layer of the grid those projects occupy. The annual business plan update on November 6 is the first hard number on the buildout, and the stock's premium to every utility peer has to be earned by it.

    Power

    Fluence's AI power bet faces a securities-fraud suit after three guidance breaks and a 73% fall

    A securities-fraud class action alleges Fluence's fiscal 2026 guidance rested on contract factories that were never ready, and the company's own disclosures back the timeline: three guidance breaks in eight months took the stock down about 73%.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.