Digital Realty filed a 1GW Indiana campus as Bernstein says only 35% of announced US capacity gets built

The $64 billion REIT just filed a 1GW campus in Kokomo, its third giant land bet at once, while Bernstein's 'bragawatts' study and an October 29 earnings print test whether announced campuses ever become signed leases.

Vincent JiangVincent Jiang · 2 min read
Share
Server racks in a commercial data hall, the kind of capacity Digital Realty leases to AI tenants
1 / 6Slide 1 of 6
Digital Realty's business is floors of racks like these: the Kokomo, Indiana filing would add roughly 1GW of IT capacity across three buildings by 2033.

Digital Realty−3.58% — Digital Realty, down 3.58 percent today, the $64 billion data center landlord, picked Kokomo, Indiana this week as its newest gigawatt bet: three buildings, 476 acres, roughly 1GW of IT capacity and 3 million square feet, complete by 2033, drawing 1.5GW from Duke Energy+3.21% — Duke Energy, up 3.21 percent today at an estimated $1.4 billion to $1.7 billion 1. It is the third giant campus on its desk at once, and the market is asking the same question at all three: does announced land become signed leases?

The landlord of the AI boom is filing campuses faster than tenants sign

In De Soto, Kansas, the company has pledged $20 million, up to $1,000 a year per household for ten years, to win support for a campus where phase one alone is 280 acres and nine buildings 2. Details with the city are not final, and neighbors have petitioned against it 2.

In Forest Park, Georgia, Hunterbrook reported that crews on its $3 billion campus on a $120 million former Army dump unearthed combustible white phosphorus in December 2025, five 30-gallon drums removed, with remediation tagged above $100 million 3. Kokomo, by contrast, comes with no tax abatement sought, but a residents' group notes its noise and water commitments are voluntary 1.

Bernstein scores Digital Realty a top-credibility builder, unlike the bragawatts

0 / 51 / 52 / 53 / 54 / 55 / 5Digital Realty5 / 5Joule Capital2.05 / 5Vermaland0.75 / 5O'Leary Digital0.35 / 5
Data
Value
Digital Realty5 / 5
Joule Capital2.05 / 5
Vermaland0.75 / 5
O'Leary Digital0.35 / 5
Bernstein Research credibility scores out of 5, from an analysis of 5,000+ planned North American data centers using Aterio construction-tracking data, as reported by Business Insider, October 2026.4

The receipts arrive Thursday

Bernstein's "bragawatts" study gives the counterweight: only about 35% of roughly 500GW of announced US capacity is likely to be built, yet it scores Digital Realty at the top of its credibility table, alongside Amazon−4.45% — Amazon, down 4.45 percent today and Google 4. That matters because shareholders are funding the build ahead of leases: EUR 1 billion of new 5.125% notes due 2036 5, a Q2 revenue beat at $1.92 billion, up 28.9%, beside an EPS miss at $1.21 against $1.98 expected, and a dividend payout ratio near 237% 6.

Revenue growth accelerated through 2026, hitting 28.9% year over year in Q2

$0B$0.5B$1B$1.5B$2BQ3 '24Q4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26$1.92B
Data
Revenue
Q3 '24$1.43B
Q4 '24$1.44B
Q1 '25$1.41B
Q2 '25$1.49B
Q3 '25$1.58B
Q4 '25$1.64B
Q1 '26$1.64B
Q2 '26$1.92B
Digital Realty quarterly revenue, US dollars in billions, calendar quarters, from its SEC filings, retrieved 22 October 2026.7

Q3 lands after the close on October 29, with analysts at $0.527 EPS on $1.75 billion 6. The print, not the press release, tells whether Kokomo, De Soto and Forest Park convert. Watch the backlog.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading DLR…

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Jane Street and Citadel each crossed 5% of Cipher Digital in the week it sold $850 million of 0% notes

    Cipher Digital sold $850 million of 0% convertible notes, and October 21 filings show Jane Street and Kenneth Griffin's Citadel entities each hold more than 5% of the stock, built during deal week. The counterparties to the miner-turned-AI-landlord's bet are now on record before the November 2 earnings print.

    Data Center

    Carrier Bets $600 Million That Its Factories, Not AI Demand, Are the Bottleneck

    Carrier's $600 million Fort Worth chiller plant, the biggest investment in its history, lands a week before earnings and a month into a wave of analyst target cuts. Gitlin is betting the constraint is his factories, not demand; the October 29 print shows whose number is real.

    Data Center

    Trane buys its own coil supplier the day Nvidia promises near-zero-water AI factories

    Trane Technologies agreed on October 21 to buy Cancoil Thermal, the family firm that already supplies its heat-rejection coils, the same day Nvidia showcased an AI-factory blueprint it says needs almost no water. Both announcements value the same layer: the hardware that carries heat out of the building.

    Data Center

    Corning just bet $585 million that the AI fiber shortage lasts for years

    Corning will spend $585 million and add 414 jobs at the Wilmington, North Carolina campus that made the world's first optical fiber. Because the new capacity ramps in phases to 2028, it is a wager that the AI fiber shortage endures, placed five days before the October 27 earnings test.

    Data Center

    Everpure's raised outlook comes from storage, not the platform it renamed itself for

    Everpure has nearly doubled this year on hyperscale storage wins, and its raised fiscal 2028 outlook comes from hardware. The case for the data platform it renamed itself for rests on a survey it commissioned and savings its own architect calls unmeasured.

    Data Center

    Vertiv rose 7% on Nvidia's 14-day AI factory design, but 17 partners including Eaton build the same box

    Nvidia's DSX POD standard, unveiled at GTC Berlin, cuts AI factory deployment to as little as 14 days and helped end Vertiv's record 11-session losing streak. But Eaton, Schneider Electric and 14 other partners build the same box, and the October 28 backlog print prices what sharing it costs.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.