Power

FERC Approved $5.2 Billion of Gas Pipe on Data-Center Forecasts. A Court Will Now Ask Who Needs It.

Landowners and community groups asked the D.C. Circuit on 1 October to overturn FERC's certificates for the South System Expansion 4 and Mississippi Crossing pipelines, and to test the data-center demand forecasts underneath them. Kinder Morgan calls the work on schedule; the next 150 miles enter pre-filing this quarter.

Vincent JiangVincent Jiangthree-minute read
Share
Laura Swett, chairman of the Federal Energy Regulatory Commission
1 / 7Slide 1 of 7
FERC Chairman Laura Swett says the Southeast has a clear need for the pipe. Her commission's 31 July certificates for the two pipelines are what the petitioners asked the D.C. Circuit to take back.

The suit lands before the first weld

On 1 October, landowners and community groups asked the U.S. Court of Appeals for the D.C. Circuit to take back 500 miles of approved pipeline 1. The target is FERC's 31 July certificate for the South System Expansion 4 and Mississippi Crossing projects, an estimated $5.2 billion of gas pipe across Georgia, Alabama and Mississippi, with the fuel bill for utility customers on top 12.

Kinder Morgan−1.74% — Kinder Morgan, down 1.74 percent today says the work is on budget and on schedule, with rights of way still being acquired and construction not yet started 3. Mississippi landowner Tony Hinton watched the route drawn through his pines: "I'd rather have the trees than the check. But that's sentiment" 4.

The need case is two reports against a forecast

The petition argues FERC certified the pair without testing demand. London Economics International, commissioned by the challengers, found plausible support for 16.4 percent of SSE4's capacity and no credible demand for more than 76 percent of it, or 83 percent of Mississippi Crossing 2. An IEEFA study filed at the commission called the projects "an attempt by utilities to force their customers into subsidizing data centers" 5.

Challengers' consultants found no credible demand for 76 to 83 percent of the capacity

  • No credible demand found
  • Plausible support found
0%50%100%SSE4Mississippi Crossing83%
Data
No credible demand foundPlausible support found
SSE476%16.4%
Mississippi Crossing83%—
Share of each pipeline's contracted capacity, as found by London Economics International for the challengers: no more than 76 percent of South System Expansion 4 and 83 percent of Mississippi Crossing lack credible demand, while 16.4 percent of SSE4 has plausible support. Source: Columbus Ledger-Enquirer via MSN.2

The buyers are the sellers' relatives. Southern Natural Gas, owned 50/50 by Kinder Morgan and Southern Company+0.11% — Southern Company, up 0.11 percent today, would carry gas for Georgia Power, Alabama Power, Mississippi Power and Atlanta Gas Light 2, under capacity contracts whose prices are confidential and passed through to ratepayers 5.

The buildout is booked; the demand is a forecast

Kinder Morgan carries SSE4 at about $3.5 billion and Mississippi Crossing at $1.7 billion inside a $9.6 billion backlog, more than 60 percent of it tied to power generation and local distribution companies, with first service due from 2028 6.

The two contested projects are $5.2 billion of Kinder Morgan's $9.6 billion backlog

  • South System Expansion 4$3.5B36.5%
  • Mississippi Crossing$1.7B17.7%
  • All other projects$4.4B45.8%
Data
SliceValueShare
South System Expansion 4$3.5B36.5%
Mississippi Crossing$1.7B17.7%
All other projects$4.4B45.8%
Kinder Morgan project backlog at second-quarter 2026, US$ billions. More than 60 percent of the backlog is tied to power generation and local distribution companies, with first service due from 2028. Source: Kinder Morgan Q2 2026 results, Business Wire.6

Southern builds ahead of its sales: second-quarter capital spending of $3.13 billion, up 19 percent on the year, against revenue up 0.1 percent 7. Its shares touched a 52-week low of $83.73 on 23 September 8.

The same demand forecast lands on two bills. Google volunteered to fund 96 megawatts of nuclear uprates at Vogtle and Hatch through the proposed NU-1 tariff, which Georgia Power says shields customers who do not subscribe 8. The reservation charges for contracted gas capacity ride the fuel line on residential and small-business bills, by Georgia Power's own testimony 2.

Capex up 19 percent, revenue up 0.1: Southern builds while sales stall

  • Revenue
  • Capex
$2$4$6$8$10Q3 '24Q4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26$3.13demand case reaches a court
Data
RevenueCapex
Q3 '24$7.27$2.21
Q4 '24$6.34$2.52
Q1 '25$7.78$2.6
Q2 '25$6.97$2.64
Q3 '25$7.82$3.1
Q4 '25$6.98$4.05
Q1 '26$8.4$3.2
Q2 '26$6.98$3.13
Southern Company quarterly revenue and capital expenditure, US$ billions, from its SEC filings via Sharadar. Q2 2026 is the last reported quarter before the 1 October petition.7

The other side has paper

FERC chairman Laura Swett says the region has "a clear need" for the pipe, and the commission's environmental review found impacts "less than significant" with mitigation 910.

Kinder Morgan's backlog rests on binding commitments generally covering more than 90 percent of planned capacity, and utilities across the Southeast count large-load connection requests above 200 gigawatts, with more than 50 gigawatts in advanced stages or under contract 3. A queue is not a power plant, and a contract between affiliates is not a market.

The calendar that decides it

The D.C. Circuit briefing, Southern's third-quarter print on 5 November and Georgia PSC dockets 44280 and 56002, which carry the Google tariff, come first 8. The Senate holds the Ratepayer Protection Act, passed by the House 417-3, to make data centers above 100 megawatts cover the grid costs they trigger 8.

Kinder Morgan is scouting the next 150 miles across Tennessee, with a pre-filing request it will complete this quarter 11, and Southern signed a 20-year deal for two-thirds of a further 1.2 Bcf/d expansion FERC approved on 10 September 9.

Whether the forecasts or the two reports are right, nothing in the record yet says. The demand case now has a docket number.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading KMI

Reader comments

0 comments

    Power

    An Indiana county asks American Electric Power to suspend a 75-mile line behind its $100 billion plan

    AEP's growth case, 84 gigawatts of new contracted load and $100 billion of spending through 2031, needs land, ballots and regulators to say yes. On Nov. 17 an Indiana county board asked the utility to suspend one of the transmission lines behind it, two weeks after voters restricted data centers in 40 of 41 ballot contests.

    Power

    Southern Company closed a $2 billion equity-unit sale at 8.625%, a third of it paid in stock

    Underwriters took their option in full on November 17, and only 5.50 of the 8.625 points is cash interest; the rest is paid in stock out of Southern's equity. Three days later Alabama Power handed $160 million of the same data-center revenue back to ratepayers.

    Power

    Ameren asks Missouri to bill customers for its 2,100 MW gas plant while it is built, cost still redacted

    Ameren pressed the request at a Nov. 18 hearing, with the plant's cost still redacted in its own filings. The financing ruling decides who pays during construction: Missouri bills if it is granted, Ameren's $38.1 billion plan and $5 billion of new equity if it is refused.

    Power

    Alabama Power files to cut 2027 rates by $160 million, crediting data centers

    The Southern Company utility says data centers that pay their own way will cut a typical Alabama home's bill by more than $50 a year from January. It lands while US electricity inflation runs 4.4 percent and utilities elsewhere seek $23 billion of increases.

    Power

    Iberdrola says it fixes data-center power prices for 20 years in Spain, where 88% of grid requests fail

    Spain let in 12% of grid-access requests in 2025, and Iberdrola's Spain chief says the data-center money has already applied to plug in. The 20-year fixed price he described turns AI power demand into contracted cash for Iberdrola shareholders and locks the biggest cost line in a data center's budget.

    Power

    Illinois cuts WEC's Peoples Gas rate increase 72% to $40 million as 15 banks market up to $4 billion of stock

    The order is the second regulator trim of a WEC Energy utility in two weeks. It lands while 15 banks market up to $4 billion of WEC stock for a $47.5 billion data-center build whose biggest customers pay on terms no rate case can touch.

    Subscribe to TheInference for free