Power

FirstEnergy reserved Siemens turbines for a $2.7 billion plant whose customer has not signed

FirstEnergy reserved Siemens turbines for 2030 and asked bids on 3 GW more gas plants, for a data-center customer that has not signed. The transmission plan grows 25% in February, most of it is not for the AI load, and up to $2 billion of new equity stands behind the bet.

Vincent JiangVincent Jiang · 3 min read
Share
Brian X. Tierney, board chair, president and chief executive of FirstEnergy
1 / 7Slide 1 of 7
FirstEnergy board chair, president and chief executive Brian X. Tierney, who told investors the giant cloud operators are looking well beyond 2030

On October 28 FirstEnergy+1.31% — FirstEnergy, up 1.31 percent today told investors it has reserved Siemens gas turbines, due in 2030, for a 1,200 MW plant at Maidsville, West Virginia, and asked for bids on 3 GW of additional gas plants 4. The customer meant to take that output is unnamed, and the offtake deal is under negotiation, not signed 2.

A Siemens worker inspects the rotor of a large gas turbine
A Siemens worker checks the rotor of an SGT5-4000F heavy-duty gas turbine. FirstEnergy has reserved Siemens turbines due in 2030 for a 1,200 MW plant at Maidsville, West Virginia, before any customer has signed. · Siemens Pressebild

The company gave no cost for the plant on its earnings call 1; trade reporting puts the project near $2.7 billion 4. A certificate can be approved before the customer signs: the utility expects the West Virginia commission to issue it in the fourth quarter of 2026, while the offtake remains in talks 4.

The quarter that paid for it

Third-quarter profit rose to $557 million from $441 million a year earlier, on revenue of $4.56 billion, up 9.9% 1. But 10 of the 15-cent rise in core earnings came from the corporate segment, mainly income-tax benefits 1. The engine underneath is capital: $36 billion committed for 2026 through 2030, targeting 10.4% annual rate-base growth (growth in the utility's invested capital base, which is what regulated rates pay a return on), with $4.9 billion invested in the first nine months, 23% more than a year earlier 1.

FirstEnergy's capital spending is climbing steadily toward its $36 billion plan

  • Revenue
  • Net income
  • Capital spending
-$2B$0B$2B$4B$6BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$4.56B$1.59B
Data
RevenueNet incomeCapital spending
Q4 '23$3.15B$0.18B$1.09B
Q1 '24$3.29B$0.25B$0.79B
Q2 '24$3.28B$0.05B$0.94B
Q3 '24$3.73B$0.42B$1B
Q4 '24$3.18B$0.26B$1.29B
Q1 '25$3.77B$0.36B$1.01B
Q2 '25$3.38B$0.27B$1.23B
Q3 '25$4.15B$0.44B$1.31B
Q4 '25$3.8B-$0.05B$1.17B
Q1 '26$4.2B$0.41B$1.26B
Q2 '26$3.68B$0.29B$1.35B
Q3 '26$4.56B$0.56B$1.59B
FirstEnergy quarterly revenue, net income and capital spending, in billions of dollars, from its SEC filings, Q4 2023 through Q3 2026. Capital spending climbed to $1.59 billion in Q3 2026 while net income moves on tax and regulatory items. Source: FirstEnergy quarterly figures from its SEC filings, retrieved November 2, 2026 [5].5

The load is a forecast, the wire is a bill

Here is the awkward number. FirstEnergy expects its transmission plan to rise at least 25%, from $19 billion to $23.75 billion or more, when the plan rolls forward to 2027 through 2031 in February 1. Most of that extra money is reliability work on the existing network, with very little tied to contracted data-center demand, and upgrades for contracts signed since February 2026 are not in the plan at all 1.

The AI load is mostly not here yet. Contracted demand sits at 2,190 MW for 2026, 6,730 MW for 2031 and 7,880 MW for 2036, against 19,070 MW of pipeline; Utility Dive counts the combined queue at 26 GW this quarter, up from 6.4 GW contracted in the second 24.

Every signed gigawatt is a line on someone's bill

Only 7.9 of 27 GW of FirstEnergy's data-center queue is contracted

  • Contracted demand
  • Pipeline demand
05,00010,00015,00020,000202620312036
Data
Contracted demandPipeline demand
20262,190—
20316,7306,390
20367,88019,070
Cumulative data-center demand forecasts on FirstEnergy's system, in megawatts, as of October 27, 2026. Contracted means a construction contract and/or electric service agreement; pipeline is not contracted. Company-claimed figures from the Form 8-K Exhibit 99.2 presentation. Source: Colocation Scout analysis of Form 8-K Exhibit 99.2, October 27, 2026.2

At the company's own rule of thumb, about $250 million of network upgrades per gigawatt 24, every contracted gigawatt is a line on someone's bill. Ohio ratepayers have noticed: a discussion thread on FirstEnergy's latest rate increase drew 273 upvotes in a week 3.

Management's answer, from CEO Brian Tierney, is that the giant cloud operators (the hyperscalers) are looking well beyond 2030, with demand broad across the six-state territory 4. That is a bet on load that has not contracted yet.

Who carries the equity

The financing terms are already on the page. The current plan allows up to $2 billion of equity or equity-like financing, new common stock should run about 1% of market value a year, and any extra West Virginia and transmission spending through 2030 is to be funded with up to 35% equity or equity-like securities 1.

If the buyer pays part of the Maidsville plant through a surcharge, the plant still needs about 35% equity or equity-like funding 1. Shareholders, not the customer, absorb the first tranche of risk on a deal that has not been signed.

Three dates settle it

Three dated events will decide whether the queue becomes billable. Ohio's staff report on the rate case lands November 30 1. West Virginia's commission is expected to rule on the Maidsville certificate by December 31 1.

In February, the roll-forward lifts the transmission plan at least 25% and shows how much of the 27 GW queue becomes rate base, and how much new stock it takes 1. The decision rule: hold the stock only if the February plan ties the extra transmission money to contracts that are actually signed, and treat an unsigned offtake after the West Virginia order as a signal to wait.

Deeper dive: our October 30 piece on the 7.9 GW demand count is here.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading FE

Reader comments

0 comments

    Power

    NuScale moved a Doosan reactor part into production with no buyer: Q2 revenue was $75,000

    The Oct 29 Doosan contract puts NuScale's first production hardware in motion, yet Q2 revenue was $75,000, $507.4 million has already gone to its exclusive partner for a non-binding deal, and a binding TVA PPA would trigger a roughly $1.2 billion payment out of $1.9 billion in cash.

    Power

    Williams Reports Q3 With Its $1 Billion Northeast Pipeline Stuck in Court

    The gas pipeline giant moves a third of US natural gas and pays a $2.10 dividend. Its courts keep erasing its Northeast expansions, while the money migrates to data-center country; Tuesday's call decides what replaces them.

    Power

    NextEra's three federally backed hubs: 16.5 GW of AI power funded with $5.7 billion of other people's money

    Three federally backed hubs hand NextEra about 16.5 GW of AI-serving generation funded with $5.7 billion of other people's money, for fees worth at least half of outright ownership. The $66.8 billion Dominion takeover is the claim that still needs Virginia's blessing, and the state's own staff says deny.

    Power

    Xcel adds $2 billion of 2027 converts to a $70 billion AI grid plan that runs to 2031

    Today's 8-K puts $2.0 billion of convertible notes due 2027 on the stack, earmarked for commercial paper, not the build. Whether existing customers or new data centers repay the $70 billion plan is a ruling Minnesota and New Mexico regulators have yet to make.

    Power

    Baker Hughes banked $1.45 billion from Hexagon's Waygate buy as its $46.4 billion backlog waits for 2027

    Baker Hughes closed the $1.45 billion Waygate sale to Hexagon on November 2, days after raising its AI-era order target past $50 billion. But GAAP net income fell 33% and its own CFO says the record backlog converts to revenue only slowly in 2027.

    Power

    Vistra's 5,500 megawatts of new gas skipped Texas. Friday's report prices them.

    The Cogentrix plants Vistra closed on October 30 landed almost entirely in PJM and New England, not ERCOT. Friday's guidance is the first test of whether the $4 billion deal still pays what it promised.