NuScale moved a Doosan reactor part into production with no buyer: Q2 revenue was $75,000

The Oct 29 Doosan contract puts NuScale's first production hardware in motion, yet Q2 revenue was $75,000, $507.4 million has already gone to its exclusive partner for a non-binding deal, and a binding TVA PPA would trigger a roughly $1.2 billion payment out of $1.9 billion in cash.

Vincent JiangVincent Jiang · 3 min read
Share
Full-scale mockup of the upper one third of a NuScale Power Module under a cloudy sky
1 / 6Slide 1 of 6
A full-scale mockup of the upper third of the NuScale Power Module, the section of the first article now moving into production at Doosan Enerbility's plant in Changwon, Korea.

The supply chain moved on Oct 29 1. NuScale Power−3.91% — NuScale Power, down 3.91 percent today (NYSE: SMR), the only small modular reactor (SMR) developer with a design approved by the US Nuclear Regulatory Commission, signed a contract that moves the first article of its upper reactor coolant system from preparation into production at Doosan Enerbility's reactor plant in Changwon, Korea, ending a manufacturing partnership that began in 2019 1. Investors bid the stock up 7% on the news, ahead of Oklo's−5.07% — Oklo, down 5.07 percent today 2% and BWX Technologies'−0.11% — BWX Technologies, down 0.11 percent today 3% 2. No value, quantity, delivery date or customer was named 1.

The demand side is still a non-binding framework

The buyer's side has not moved. The program driving the stock covers up to 6 gigawatts, about 72 of NuScale's 77-megawatt modules, under a September 2025 agreement between the Tennessee Valley Authority (TVA), the federal utility serving seven southern states, and ENTRA1 Energy, NuScale's exclusive commercialization partner 3. That agreement is non-binding 3. No power purchase agreement (PPA), the binding contract that would commit TVA to buy the output, no site and no NRC application has been announced, and the design approval NuScale holds licenses no plant 3.

The shareholder pays twice

Meanwhile the money runs toward the partner, not from the customer. NuScale recorded a $507.4 million expense because ENTRA1 signed that non-binding framework, and it has already paid the full amount, the last of it in the first quarter of 2026 2. A binding PPA would trigger a second tranche of about $1.2 billion if the 72-module scope holds, against $1.9 billion of cash and investments at June 30 2. Second-quarter revenue was $75,000, down from $8.1 million a year earlier 2.

Quarterly revenue has slid from $8M to $75,000 in a year

$0M$5M$10MQ2 '25Q3 '25Q4 '25Q1 '26Q2 '26$0.08M
Data
Revenue
Q2 '25$8.05M
Q3 '25$8.24M
Q4 '25$1.81M
Q1 '26$0.56M
Q2 '26$0.08M
US dollars, millions. NuScale's quarterly revenue as reported in its SEC filings, retrieved 2 November 2026; the $0.08M quarter is the $75,000 second quarter the story cites. Source: NuScale Power, quarterly figures from its SEC filings.7

The wait is also funded in shares: Class A shares plus Class B units rose to 429.7 million at mid-2026 from 231.4 million at the end of 2023 2, and about $962 million of the cash on hand came from selling new stock in the second quarter alone 5. ENTRA1 keeps sole discretion over whether to order modules from NuScale at all, at a capped price per module 5.

A binding PPA would hand ENTRA1 about $1.2B of NuScale's $1.9B in cash

  • Estimate
0B0.5B1B1.5B2BCash and investments, June 30, 2026$1.9BAlready paid to ENTRA1$507.4MNext tranche if a binding PPA lands$1.2B
Data
Value
Cash and investments, June 30, 2026$1.9B
Already paid to ENTRA1$507.4M
Next tranche if a binding PPA lands (estimate)$1.2B
US dollars, billions. Cash and investments at June 30, 2026, and the $507.4M first milestone paid to ENTRA1 from NuScale's quarterly filings as reported by TIKR and The Motley Fool; the 35% second tranche of about $1.2B is an estimate from the 72-module scope, not a reported figure. Sources: TIKR, Voltgrid News, The Motley Fool.2,3,5

The suit, and the Nov. 5 checkpoint

Shareholder Thomas Harwood III is suing, alleging NuScale misrepresented the ENTRA1 partnership and that management conceded on a November 2025 call that ENTRA1 lacks build-own-operate experience; the stock lost roughly 70% of its value from its March high after that call 4. Multiple shareholder-rights firms are now investigating 6. NuScale denies wrongdoing and points to its regulatory lead, the only approved SMR design 46.

The bull case still needs a signed order

The bullish case is real: $1.9 billion of cash, the only approved design, and analysts' $236 million revenue estimate for 2028 2. But that ramp needs a signed order, and the Doosan first article is not one 2.

Thursday, Nov. 5, at 5:00 p.m 3. ET, the third-quarter call answers the only question that matters: is a PPA signed, near, or still nothing 3? A signing would be bullish for revenue and hand ENTRA1 about $1.2 billion in the same breath 3. Both sides of the trade need that number.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading SMR

Reader comments

0 comments

    Power

    FirstEnergy reserved Siemens turbines for a $2.7 billion plant whose customer has not signed

    FirstEnergy reserved Siemens turbines for 2030 and asked bids on 3 GW more gas plants, for a data-center customer that has not signed. The transmission plan grows 25% in February, most of it is not for the AI load, and up to $2 billion of new equity stands behind the bet.

    Power

    Williams Reports Q3 With Its $1 Billion Northeast Pipeline Stuck in Court

    The gas pipeline giant moves a third of US natural gas and pays a $2.10 dividend. Its courts keep erasing its Northeast expansions, while the money migrates to data-center country; Tuesday's call decides what replaces them.

    Power

    NextEra's three federally backed hubs: 16.5 GW of AI power funded with $5.7 billion of other people's money

    Three federally backed hubs hand NextEra about 16.5 GW of AI-serving generation funded with $5.7 billion of other people's money, for fees worth at least half of outright ownership. The $66.8 billion Dominion takeover is the claim that still needs Virginia's blessing, and the state's own staff says deny.

    Power

    Xcel adds $2 billion of 2027 converts to a $70 billion AI grid plan that runs to 2031

    Today's 8-K puts $2.0 billion of convertible notes due 2027 on the stack, earmarked for commercial paper, not the build. Whether existing customers or new data centers repay the $70 billion plan is a ruling Minnesota and New Mexico regulators have yet to make.

    Power

    Baker Hughes banked $1.45 billion from Hexagon's Waygate buy as its $46.4 billion backlog waits for 2027

    Baker Hughes closed the $1.45 billion Waygate sale to Hexagon on November 2, days after raising its AI-era order target past $50 billion. But GAAP net income fell 33% and its own CFO says the record backlog converts to revenue only slowly in 2027.

    Power

    Vistra's 5,500 megawatts of new gas skipped Texas. Friday's report prices them.

    The Cogentrix plants Vistra closed on October 30 landed almost entirely in PJM and New England, not ERCOT. Friday's guidance is the first test of whether the $4 billion deal still pays what it promised.