Fluence Energy's filing shows backlog up 39% to a record $8.9 billion in the quarter it cut guidance twice
The same filing shows its commitments to buy battery cells more than doubled in a year, to $2.7 billion. Shareholders have paid the higher cell prices so far, through a negative gross margin; customers pay only if the $3.5 billion of new orders were priced above what the cells will cost.
Vincent Jiangthree-minute read
Fluence Energy+20.79% — Fluence Energy, up 20.79 percent today (Nasdaq: FLNC), which builds grid-scale batteries for utilities, filed its annual report on Monday 1, four days before the November 27 deadline for investors to apply to lead a securities class action against it 2. Its backlog, the revenue under signed contracts not yet delivered, stood at $8.9 billion on September 30, the highest in its history 3: up 39.1% from $6.4 billion on June 30 and 67.9% from $5.3 billion a year earlier 4.
At Monday's close of $3.80 the company was worth about $700 million, roughly 8% of those signed orders 54. The shares traded at $4.19 after hours, up 9.9% after the 4:05 PM report 36.
The filing says who has paid so far
The annual report attributes the fourth quarter's negative 5.0% gross margin to penalties for late projects, cost overruns on its newer Gridstack Pro and Smartstack systems, and higher estimated costs on certain projects as battery prices rose 13.
Fluence cut its fiscal 2026 revenue outlook twice in that quarter, on August 5 and September 16, each time blaming production delays at contract manufacturing plants, with Houston the primary cause by September 78, as The Inference reported on November 20. The year closed with revenue of $2.3 billion, a gross margin of 2.8% against 13.1% a year earlier, and a net loss of $273.9 million 3.
Gross margin fell from 13.7% to negative 5.0% in four quarters
Fluence sold its systems below cost in the quarter it cut guidance a second time
Data
| GAAP gross margin | |
|---|---|
| Dec 2024 | 11.4% |
| Mar 2025 | 9.9% |
| Jun 2025 | 14.8% |
| Sep 2025 | 13.7% |
| Dec 2025 | 4.9% |
| Mar 2026 | 10% |
| Jun 2026 | 5.1% |
| Sep 2026 | -5% |
The new number is what Fluence promised to buy
Commitments to buy battery cells and modules under minimum-volume supply contracts reached $2.7 billion: up 125.8% from $1.2 billion a year earlier, though down 7.4% from $2.9 billion in June 41. Buying less than promised would cost Fluence penalties of $364.1 million, and $888 million of the purchases fall due in fiscal 2027 1. Committed purchases equal about 30% of backlog, up from roughly 23% a year earlier 4.
Battery purchase commitments more than doubled in a year while backlog rose 68%
Committed cell buys rose from about 23% to 30% of backlog in a year
- Backlog
- Purchase commitments (mostly cells)
Data
| Backlog | Purchase commitments (mostly cells) | |
|---|---|---|
| Sep 2025 | $5.3B | $1.2B |
| Jun 2026 | $6.4B | $2.9B |
| Sep 2026 | $8.9B | $2.7B |
Shareholders have paid so far. The filing says some fixed-price contracts lacked raw-material index protection, so Fluence absorbed the battery price rise, and that it has not historically hedged commodity risk 1. Customers pay only if the $3.5 billion of orders signed in the September quarter were priced above what the cells will cost, and the filing does not say 3.
Bank guarantees, letters of credit and surety bonds posted on customer projects total $7.2 billion, up 23.5% from $5.8 billion a year earlier 41.
The suit's question is not in the filing
Hatweek v. Fluence Energy, filed September 28 in the Manhattan federal court against the company, former chief executive Julian Nebreda and former finance chief Ahmed Pasha, alleges the guidance rested on plants that were not finished and on corrective measures that were failing 12. The 10-K confirms the Houston shortfall and says nothing about what management knew before the cuts; Fluence calls the claims without merit 1.
The December quarter decides it
Under the interim chief executive installed this month, as The Inference reported on November 12, Fluence offered no numeric outlook for fiscal 2027 10, and lead-plaintiff motions in the suit are due November 27 2.
Fluence expects to recognize about 37% of its backlog, some $3.3 billion, within 12 months, though customers can terminate or defer under some circumstances 1. The test is the December quarter, the first of a fiscal year in which $888 million of cell purchases fall due: whether that backlog turns into revenue at a positive margin 1.