Google signed a 20-year deal to add 890 megawatts to 11 Constellation nuclear reactors

Google signed a 20-year deal today that funds 890 megawatts of uprates at 11 Constellation reactors and locks 15 years of output from 2,700 more, six days after Amazon signed at Calvert Cliffs. Google says households pay nothing; the same grid's last capacity auctions cleared at the federal cap.

Vincent JiangVincent Jiangthree-minute read
Share
The Byron Nuclear Generating Station in Ogle County, Illinois, its two cooling towers over a cornfield
1 / 6Slide 1 of 6
Byron, in Illinois, takes about $2 billion of the uprate money Google is funding at Constellation's reactors

The cheapest reactor is one you already own

The cheapest reactor in America is an old reactor with new turbines, and Google just bought the next 890 megawatts of it. Today's 20-year power purchase agreement funds new turbines, steam generators and digital controls at 11 Constellation nuclear units across Illinois, Pennsylvania and New Jersey, capacity the companies describe as entirely new and equal to a large conventional reactor. 1

Revenue signed before the steel is cut

Constellation puts more than $4.3 billion into the work, sustaining roughly 4,400 jobs and creating about 7,200 construction jobs, with the first uprate due by 2028; a separate 15-year agreement contracts 2,700 megawatts of existing fleet output besides. 1 A report ahead of the announcement put Google's payment at $1 billion or more over the deal's life 3, and Constellation shares traded about 5 percent higher premarket. 6 It is the second hyperscaler contract in six days. On September 30, Amazon signed for 690 megawatts at Calvert Cliffs in Maryland, including a 190-megawatt uprate due online between 2030 and 2032, unlocking more than $3 billion of investment and Amazon's−1.19% — Amazon, down 1.19 percent today first uprate funding. 27 Chief executive Joe Dominguez calls it a model for how technology companies and the energy industry can develop the digital economy together. 1

The Calvert Cliffs Nuclear Power Plant seen across the water in Maryland
Calvert Cliffs in Maryland, where Amazon signed a 20-year deal with Constellation on September 30Peretz Partensky

Ratepayer-neutral, says the seller

Google frames the structure as a direct answer to PJM's "Bring Your Own Power" proposal and the White House Ratepayer Protection Pledge: new supply "without passing on costs to residential customers." 1 That is the seller's claim, and nothing in the record tests it. The grid underneath has been clearing at its ceiling; PJM's two most recent capacity auctions settled at the regulator-approved cap above $329 per megawatt-day 4, and consultants to Illinois regulators say the state's grid must double to 120 gigawatts by 2045, mostly for data centers. 5 About $2 billion of the uprate money lands at Byron, Braidwood, LaSalle and Quad Cities. 5

Two ways to fund the same megawatt

Two private tech deals in six days now match Washington's nuclear loan book

$0B$1B$2B$3B$4B$5BGoogle + Constellation PPA$4.3BVistra via DOE loan$4.2BConditional commitment, up to this amountAmazon + Constellation PPA$3B
Data
Value
Google + Constellation PPA$4.3B
Vistra via DOE loan$4.2B
Amazon + Constellation PPA$3B
Announced funding for US nuclear uprates, October 2026. Google and Amazon figures from company announcements, Amazon a stated minimum; Vistra is a conditional DOE loan commitment of up to the amount shown. US$ billions.1,2,4

The rival model arrived a day earlier. The Energy Department's financing office offered Vistra−2.58% — Vistra, down 2.58 percent today a conditional loan of up to $4.2 billion to uprate Beaver Valley, Davis-Besse and Perry: 433 new megawatts arriving between 2031 and 2034, carried on the federal balance sheet, with Meta−0.79% — Meta, down 0.79 percent today already contracted for that output plus 2,176 megawatts of existing generation. 4 Washington is not idle; the same office closed a $26.5 billion package for Southern Co. that includes uprates. 4 The difference is sequence. Constellation's revenue is contracted before construction starts, and its first new megawatt is due three years before Perry's.

Google's 890 megawatts is the largest uprate package yet

0 MW500 MW1,000 MWGoogle + ConstellationAmazon + ConstellationVistra via DOE433 MW890 MW690 MW
Data
New megawatts
Google + Constellation890 MW
Amazon + Constellation690 MW
Vistra via DOE433 MW
New megawatts from announced nuclear uprate deals, October 2026. Google and Amazon from company announcements; Vistra from the DOE conditional loan package. Megawatts.1,2,4

Watch the 2028 date

If the first Google-funded uprate slips past 2028, the contracted-annuity story and the ratepayer argument get repriced together, because PJM keeps clearing at the cap until the megawatts arrive. 14 The reactors were already running. The first uprate is due by 2028, and everything priced this morning rests on that date holding.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AMZN

Reader comments

0 comments

    Power

    Fluence Energy's filing shows backlog up 39% to a record $8.9 billion in the quarter it cut guidance twice

    The same filing shows its commitments to buy battery cells more than doubled in a year, to $2.7 billion. Shareholders have paid the higher cell prices so far, through a negative gross margin; customers pay only if the $3.5 billion of new orders were priced above what the cells will cost.

    Power

    LIPA holds up to $1.1 million of PSEG Long Island's pay to a customer bill of rights

    PSEG Long Island's president Scott Jennings accepted 10 service standards and a 12-point bill of rights on November 18, and shut-offs stay barred through April 15. For PEG holders the bonus is tiny; the hold now runs through a contract to 2030 and an open statewide review.

    Power

    Chile's power tribunal sides with Enel over Engie, ordering a count of the desert's stability needs

    The tribunal upheld Enel's demand for a quantified voltage-control requirement and rejected Engie's push to declare a deficit now. A number would become tenders and tariffs, and Enel already has grid-forming batteries rising in the desert.

    Power

    An Indiana county asks American Electric Power to suspend a 75-mile line behind its $100 billion plan

    AEP's growth case, 84 gigawatts of new contracted load and $100 billion of spending through 2031, needs land, ballots and regulators to say yes. On Nov. 17 an Indiana county board asked the utility to suspend one of the transmission lines behind it, two weeks after voters restricted data centers in 40 of 41 ballot contests.

    Power

    Southern Company closed a $2 billion equity-unit sale at 8.625%, a third of it paid in stock

    Underwriters took their option in full on November 17, and only 5.50 of the 8.625 points is cash interest; the rest is paid in stock out of Southern's equity. Three days later Alabama Power handed $160 million of the same data-center revenue back to ratepayers.

    Power

    Ameren asks Missouri to bill customers for its 2,100 MW gas plant while it is built, cost still redacted

    Ameren pressed the request at a Nov. 18 hearing, with the plant's cost still redacted in its own filings. The financing ruling decides who pays during construction: Missouri bills if it is granted, Ameren's $38.1 billion plan and $5 billion of new equity if it is refused.