Power

Michigan voters cut CMS Energy off from the officials deciding its $443 million rate case

Proposal 2 passed with 82% on November 3 and CMS Energy sued two days later. From about December 3 the utility cannot fund the Michigan politicians and regulators who rule on its $443 million rate case, a 1-gigawatt data center and a $27 billion buildout.

Vincent JiangVincent Jiangtwo-minute read
Share
Consumers Energy's Karn/Weadock generating plant in Hampton Township, Michigan, under a clear sky
Consumers Energy's Karn/Weadock generating station in Bay County, Michigan. Its parent CMS Energy has until about December 3 before Michigan's Proposal 2 bars it from funding the officials deciding its $443 million rate case.

Eight in ten voters said yes; the utilities went to court in two days

Michigan passed Proposal 2 on November 3, 2026, with 3,549,433 yes votes against 805,411, about 82% 1. Section 30a, the provision it added, bars electric and gas utilities, their executives, their family members and their affiliates from contributing to state candidates, party committees and members of the Michigan Public Service Commission, the appointed board that rules on utility rates, while unions and advocacy groups keep that right 2.

A tenfold fine, no cure, and a federal suit in two days

A violation carries a fine of up to 10 times the contribution, with no safe harbour and no cure by returning the money 2. On November 5 CMS Energy−2.12% — CMS Energy, down 2.12 percent today, Consumers Energy, DTE Energy+0.16% — DTE Energy, up 0.16 percent today and its subsidiaries, two political action committees and two individuals sued in federal court in Grand Rapids to block it 2. One plaintiff is DTE's treasurer; the other is his mother, covered solely because the law reaches executives' immediate family 2.

The other side is ready. Samuel Bagenstos, the University of Michigan law professor defending the measure, says it was drafted with existing court decisions in mind; campaign manager Maura Cowley called the suit no surprise 3.

The decisions that matter next all sit inside the ban's blast radius

Consumers Energy wants $443 million of added electric revenue at a 10.25% return on equity; commission staff back $265 million at 9.85%, and the year's approved gas order landed at $139 million, about 60% of that ask 4. Meanwhile an up-to-1-gigawatt data center Consumers agreed to serve, reported as Microsoft−0.86% — Microsoft, down 0.86 percent today, still works through zoning in multiple locations, outside the 745 MW of new contracts signed and 450 MW already energized 567. Chief executive Garrick Rochow blames campaign "spin" for the opposition 5.

Consumers' data center pipeline: 450 MW on now, up to 1,000 MW in play

  • Megawatts
  • Estimate
0 MW500 MW1,000 MWReported ceilingSigned contractsEnergized450 MW
Data
Megawatts
Reported ceiling (estimate)1,000 MW
Signed contracts745 MW
Energized450 MW
Megawatts. The reported ceiling is the up-to-1-gigawatt data center Consumers Energy agreed to serve (reported as Microsoft, still working through zoning in multiple locations), shown as an estimate rather than a signed figure; alongside it, the 745 MW of new contracts signed and the 450 MW already energized. Sources: Private Wealth Daily; Data on Data Centers; FinancialSumo.5,6,7

That is the machine at stake: a 10.5% rate-base growth target, a $27 billion buildout through 2040, 2026 adjusted EPS guidance of $3.83 to $3.90, and a negative Moody's−2.02% — Moody's, down 2.02 percent today outlook on the utility 4. Third-quarter GAAP earnings fell to $0.39 a share from $0.92 7. Investors marked CMS down 2.12% on Friday 8.

CMS asked for $443 million; the regulator's staff sits $178 million lower

The case CMS must now argue without funding the people who rule on it

$0M$100M$200M$300M$400M$500MCMS electric ask$443MStaff recommendation$265MApproved gas order$139M
Data
Value
CMS electric ask$443M
Staff recommendation$265M
Approved gas order$139M
Electric rate case request and staff recommendation from CMS Energy's revised filing, plus the approved 2026 gas rate order, in millions of US dollars. Source: CMS Energy Q3 2026 earnings call, via Tipranks at The Globe and Mail.4

The pen now belongs to a judge

Certification lands November 23 and Section 30a takes effect around December 3 2. The Mackinac Center's parallel suit attacks the disclosure rules reaching journalists and nonprofits 9. Watch one thing: whether a federal judge freezes the ban before December 3, because that single order decides whether CMS argues its $443 million case funded or muzzled 9.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading CMS

Reader comments

0 comments

    Power

    Southern Company earned $2.05 billion as Georgia's new commission weighs who pays for its $100 billion plan

    Southern Company's $2.05 billion quarter and a potential $100 billion data-center build plan landed the same week Georgia's utility regulator flipped to Democrats, putting the question of who pays the bills back in play.

    Power

    California may cut PG&E's 5,000-mile fire-safety plan to 1,100 miles, and with it the growth engine

    A California Public Utilities Commission vote on November 19 would force PG&E's $16 billion undergrounding program to compete against cheaper covered conductor, and PG&E itself says the plan could fall from 5,000 miles to 1,100. For a utility that earns by deploying approved capital, that is a vote on the size of its growth engine.

    Power

    Duke Energy cut Florida's 2027 rates with a tax maneuver; the $103 billion build lands in the Carolinas

    The same Florida commission that rejected Duke's data-center tariff 5-0 approved a 2027 rate cut funded by a tax maneuver. With the Florida ask gone, recovering the cost of Duke's build now falls to the Carolinas rate reviews and to county votes, starting Monday in Davidson County.

    Power

    Constellation Energy reports Monday: consensus 2028 EPS of $16.80 needs 7 to 18 gigawatts, only 1.1 signed

    Constellation Energy reports Monday with consensus EPS already above its guidance midpoint, and the 2028 estimate rests on gigawatts nobody has signed. The math says roughly 7 to 18 gigawatts of new contracts; 1.1 are locked in.

    Power

    Sempra's Texas grid plan grows 20%; California's $188 million rate denial pushes 2027 toward the low end

    Oncor, the Texas grid utility majority-owned by Sempra, drove a third-quarter beat and a five-year capital plan set to rise about 20% from $47.5 billion. A proposed California decision denying a $188 million rate correction would pull 2027 toward the bottom of guidance, and at $82.90 the stock still trades below its 200-day average.

    Power

    Musk's SoftBank default claim tests GE Vernova's $5.3 billion of customer cash

    GE Vernova collected $5.3 billion of customer down payments in one quarter, its chief executive said nobody had asked to leave the turbine queue, and nine days later Elon Musk said SoftBank was walking away. The 130 gigawatt year-end figure now decides what the order book is worth.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.