Missouri hearings Nov. 18 on Ameren's 2,100 MW West Alton plant, which has no price tag

The hearings open the first public fight over who pays to build the largest plant in Ameren's $38.1 billion plan before it earns anything in 2031, a bill shareholders partially fund with roughly $5 billion of new shares.

Vincent JiangVincent Jiangtwo-minute read
Share
A combined-cycle gas power plant with a steel stack and pipework, the type of plant Ameren proposes to build at West Alton
1 / 7Slide 1 of 7
A combined-cycle gas plant: West Alton would be a 2,100 MW plant of this type, with three units running around the clock from 2031. Photo of the Otahuhu B plant in New Zealand.

A notice in the mail, a plant with no price

A St. Louis customer who received Ameren's−0.30% — Ameren, down 0.30 percent as of its last quote notice as a PDF posted it to Reddit this month with one question: is this a rate increase? 7. Missouri's Public Service Commission takes that question in public on November 18, at St 1. Charles Community College in Cottleville, and by video on November 19, under case EA-2026-0226 1. What the notice does not contain is a number: Ameren has published no construction cost for the West Alton Energy Center, citing its procurement process 1.

The biggest plant in a $38.1 billion plan

West Alton is a 2,100-megawatt combined-cycle gas plant with three units built to run around the clock, filed in July to open in 2031 beside the six-decade-old Sioux plant, which Ameren plans to retire by the end of 2035 13. It is the largest single piece of the roughly 7.7 gigawatts Ameren Missouri plans to add from 2027 through 2031, an increase of about 80% in the utility's generating capacity, inside a $38.1 billion five-year capital plan 2.

West Alton is the biggest announced plant, and it lands last

West Alton is the largest single piece of Ameren Missouri's 5.3 GW of announced plants

0 GW0.5 GW1 GW1.5 GW2 GW2.5 GWUnder construction (2027–28)2.3 GWSolar and storage (2028–29)1.0 GWWest Alton gas (2031)2.1 GWNo published cost, hearings Nov 18
Data
Value
Under construction (2027–28)2.3 GW
Solar and storage (2028–29)1.0 GW
West Alton gas (2031)2.1 GW
Gigawatts of announced Ameren Missouri generation by expected first year of service; approximate figures disclosed on the Q3 2026 earnings call, November 6, 2026. Ameren has published no construction cost for West Alton.2

Who carries four years of construction

The filing asks the commission to decide which costs can be recovered while the plant is still being built, a Construction Work in Progress approach that became legal under Missouri law in 2025 134. Ameren says collecting earlier would cut financing costs and cites a 2024 state analysis it says lowers project costs by millions 134.

Senate Bill 4 is the law in the way: large users must cover all upfront grid connection costs and a share of generation costs 1. Google and Amazon+1.60% — Amazon, up 1.60 percent today, named on last week's earnings call, sit inside the 2.8 gigawatts of signed service agreements with $25 billion of announced Missouri investment, and 5.6 gigawatts more wait behind them in the pipeline 26. Grant recovery without a fixed allocation and existing customers carry a data-center plant; refuse it and Ameren funds the build with debt and about $5 billion of new shares, of which $1.7 billion is already sold forward 2.

Capital spending jumped 45% in Q3 2026 as the buildout ramps

$0B$0.5B$1B$1.5B$2BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$1.44B
Data
Capex
Q4 '23$1.14B
Q1 '24$0.9B
Q2 '24$1.03B
Q3 '24$1.16B
Q4 '24$1.32B
Q1 '25$1.08B
Q2 '25$1.07B
Q3 '25$0.99B
Q4 '25$1.04B
Q1 '26$1.6B
Q2 '26$1.08B
Q3 '26$1.44B
Quarterly capital expenditure in US dollars from Ameren's SEC filings, retrieved November 10, 2026. The five-year plan behind the West Alton plant totals $38.1 billion, up 20%, with about $5 billion of new equity to fund it, of which $1.7 billion is already sold forward.8

The calendar decides it

The evidentiary hearing is set for April 2027 and Ameren has asked for a decision by early spring 2027 1. The commission also expects to rule by May 2027 on a separate $343 million rate request, with new rates due June 2027 5. Watch the November 18 testimony and, above all, whether a price for West Alton appears before the vote 5. The biggest plant in Ameren's plan has a hearing calendar and no price tag.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AEE

Reader comments

0 comments

    Power

    Tennessee signs BWXT grant for $714.5M uranium plant as bookings fall 76%

    Tennessee just signed the grant agreement for BWXT's $714.5 million Jonesborough uranium plant, the half of the program with a paying federal customer, four days after the company launched $500 million of 2034 notes into a quarter where bookings fell to $538 million from $2.25 billion. Investors now hold one stock funding two capital programs, and only one payer is named.

    Power

    Southern Company puts the operator of its data-center build in charge of the whole system

    Kim Greene ran Georgia Power through the AI buildout; from January 1 she runs system operations and the entire generation fleet, nuclear included, just as Southern's five-year plan heads toward $100 billion and Georgia's utility regulator flips Democratic. The AI boom's binding constraint is now the grid, and Southern promoted the person who builds for it.

    Power

    PSEG raises its five-year regulated investment plan to $22.5-25.5 billion

    The November 6 8-K grows the regulated build and pledges 6%-8% earnings growth through 2030 with no new equity, yet the large-load contracts behind the demand story are still unsigned, PJM's utilities just cut 6.5 GW from their forecasts, and the bill for the wait lands on New Jersey ratepayers through 2028.

    Power

    Constellation Energy CEO calls data-center demand forecasts massively overstated; GE Vernova stock fell 7.4%

    Two power CEOs told the market within three days that the grid-queue numbers behind the AI buildout were padded by speculation. The repricing lands on developers and equipment makers; the incumbents with power already sold are watching their contracts, not the queues.

    Power

    SpaceX asks its company town for a tax break on a $24 billion gas plant and data center

    Starbase's three-member commission, two of whom work for SpaceX, votes December 9 on the property tax abatement for the plant that would power the company's fast-growing compute business. The notice never prices the giveaway, and the governor-elect who campaigned against data centers takes office in January.

    Power

    Duke Energy wins 29 lenders' consent to merge its Carolinas utilities

    An amendment to Duke's $10 billion credit line, signed November 9, clears Duke Energy Progress to vanish into Duke Energy Carolinas on January 1, 2027. One borrower will now front the rate cases that decide who pays for Duke's $103 billion data-center build.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.