Modine starts its largest chiller plant in Texas; data-center orders topped $1 billion in a quarter

The plant runs one shift today with four 2MW lines targeted by fiscal year end, and Modine's shareholders fund that ramp on debt, with first-half free cash flow of negative $145.6 million, in a state where new data center permits have been frozen since September.

Richard TangRichard Tangtwo-minute read
Share
Airedale by Modine executives and staff cutting the ribbon at the opening of its U.S. chiller plant serving the data center market
1 / 6Slide 1 of 6
Airedale by Modine's U.S. chiller plant dedication in 2022; the new Grand Prairie, Texas plant, its largest, began commercial production this month.

Modine's+1.87% — Modine, up 1.87 percent today biggest chiller plant began commercial production in Grand Prairie, Texas this month. The company announced on November 11 that the 682,000-square-foot facility, expected to be its largest Airedale chiller plant, is now making 2MW and 3MW chillers for data centers, with one shift running and a three-shift model planned 1. It targets four operational 2MW lines by fiscal year end 1. That capacity answers a record order book, but the ramp spends cash first, and the plant sits in the one state whose permitting politics now hangs over new orders.

The order book is booked; the new lines are not

Demand is real and already committed. Data center orders passed $1 billion in a single quarter for the first time, a fourth consecutive record, and one hyperscaler committed to more than $400 million of custom air handling units running through calendar 2027 2.

Revenue is still compounding: $647.2M to $994.4M in seven quarters

0$M500$M1,000$MQ1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26994.4$M
Data
Revenue
Q1 '25647.2$M
Q2 '25682.8$M
Q3 '25738.9$M
Q4 '25805$M
Q1 '26954.4$M
Q2 '26874.1$M
Q3 '26994.4$M
Modine total revenue by fiscal quarter, millions of dollars, calendar quarters labelled. Source: Modine, quarterly figures from its SEC filings, retrieved November 11, 2026.6

Chillers get ordered when a project is far enough along to need one, so the backlog sits in halls already permitted. Lines two through four fill only if the next set of projects gets approved. Wells Fargo+0.49% — Wells Fargo, up 0.49 percent today estimates Texas holds about 27% of planned US data center capacity; permits there have been frozen since September pending an audit; and the governor-elect won on November 3 after vowing "a moratorium, a ban, on all data center approvals" 3.

The margin has to close the cash gap

Data Centers sales rose 95% to $439.7 million in fiscal Q2, but segment gross margin fell 470 basis points to 19.7% on higher material, component and tariff costs 2. Segment EBITDA margin slipped to 15.4% from 18.1% a year earlier, against management's promise of at least 20% by the fourth quarter, while first-half free cash flow was negative $145.6 million on $573.7 million of net debt 4. New lines add fixed cost and working capital before they add margin. The shares hit a 52-week low of $99.61 after the earnings miss 5.

Modine's data center EBITDA margin must rise from 15.4% to its 20% target

Segment EBITDA margin fell to 15.4% and management has promised 20% by fiscal Q4

  • Data Centers EBITDA margin
  • Estimate
0%5%10%15%20%Q2 FY2026Q2 FY2027Q4 target15.4%
Data
Data Centers EBITDA margin
Q2 FY202618.1%
Q2 FY202715.4%
Q4 target (estimate)20%
Modine Data Centers segment EBITDA margin, fiscal Q2 year over year, and management's fiscal Q4 target, percent, dashed where a target. Source: ad-hoc-news, Modine's Order Boom Meets Its Margin Test as New Leadership Takes the Reins, November 7, 2026.4

What to watch on November 18

The investor day on November 18 is where the 20% marker gets defended 4. Two things decide whether this plant pays for itself: the fill rate on lines two through four, and whether cash flow turns positive before Texas policy reaches the order book. Modine is doing the builder's work the AI chain needs, turning demand into physical cooling capacity; its reward depends on orders it cannot yet book.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading MOD

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Nvidia's $6.3 billion CoreWeave order survives a Huang exit, but the next financing does not

    A day after CoreWeave beat guidance and swore off bond markets, D.A. Davidson told investors to stay away because Jensen Huang was the real backstop. The filings say the order outlasts him; the next financing round is what would miss him.

    Data Center

    Johnson Controls and Armada ship first modular AI data center from Dublin to Norway on just 9 MW of orders

    A Johnson Controls plant in Dublin is now continuously building modular AI data centers, and the first unit has left for Fossefall in Norway. One buyer stands behind the firm orders, and the same morning JPMorgan turned wary on AI-linked industrials.

    Data Center

    Keefe Bruyette downgrades Riot Platforms on Anthropic tenant risk, $23 target vs Jefferies' $28

    A day after Jefferies more than doubled its target to $28 on the Corsicana lease, Keefe, Bruyette & Woods cut Riot to Market Perform at $23 over tenant credit. The 10-Q names the tenant Anthropic PBC, and Anthropic prices its IPO on November 18.

    Data Center

    CoreWeave named VAST Data a partner, then agreed to buy SSDs directly from Solidigm; backlog $132.5 billion

    CoreWeave's Q3 filing names VAST Data a partner and, in the same document, commits to buying SSDs directly from Solidigm, against a $132.5 billion backlog and $37-39 billion of capex. The question is what a storage software layer is worth when its biggest customer class buys the hardware itself.

    Data Center

    Oracle spent its $20 billion funding cap in five days, then lost Tencent and Microsoft

    Washington killed a $7 billion Tencent chip lease and Microsoft switched off its rented Oracle servers, days after Oracle spent the entire $20 billion it promised not to exceed through fiscal 2030. Bernstein says no more funding is needed; the mid-December quarter report now carries that whole argument.

    Data Center

    IREN's 3-year-old Nvidia H100s re-rented at double the price; $6 billion of its $15 billion build unfunded

    The doubled rent on three-year-old H100s is IREN's proof that GPU collateral holds value. It lands in front of lenders just as $6 billion of the company's $15 billion build still needs raising, and the form of that money decides who carries the risk.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.