Nebius raised $2.8 billion at $224 a share; the stock now sits at $96.92

Nvidia has made its $32 billion of neocloud commitments conditional and lenders are pulling back. Nebius says customer prepayments already cover more than 100% of new-build capex, but its own funding price just halved, which makes the fourth-quarter report a referendum on dilution.

Vincent JiangVincent Jiangthree-minute read
Share
Arkady Volozh, founder and chief executive of Nebius, in a company portrait against a pale blue background
Arkady Volozh, founder and chief executive of Nebius, says customer prepayments now cover more than 100% of the capital behind new capacity.

Nvidia's−10.86% — Nvidia, down 10.86 percent today interim CEO Colette Kress put a condition on the AI building boom. In prepared remarks with the Nov. 17 results she wrote that neoclouds, the companies that buy Nvidia's chips and rent the compute out, are "growing faster than their balance sheets and long-term credit profiles can support," and that Nvidia's $32 billion of neocloud commitments take effect only if those customers line up financing and get the capacity running 1. On the call she was blunter: if a project runs into trouble, "our guarantee doesn't exist anymore" 1.

The open checkbook is over

The backdrop is chaos at the top. Jensen Huang was ousted as Nvidia's chief executive this month over an alleged affair with a suspected Chinese spy, wiping $1.4 trillion off Nvidia's market value in weeks 2. Via the Wall Street Journal and Carson Group's Nov. 18 show, the message he had delivered to neocloud executives in Berlin last month: "the open checkbook is over 1. If you want GPU allocations, you need to get upfront payments from your customers" 1. Washington added pressure the same week, requiring licenses for overseas neoclouds to serve Chinese customers 3.

Nebius says it already plays that way

Nebius−12.81% — Nebius, down 12.81 percent today CEO Arkady Volozh told investors that prepayments on new contracts now cover more than 100% of the capital needed to bring that capacity online 1. Deferred revenue, money paid before the compute is delivered, hit $9.4 billion at Sept 1. 30, up from $1.6 billion at the end of 2025 1. Nvidia itself put $2.0 billion into Nebius in March 1.

Customer prepayments have quintupled in three quarters, to $9.4 billion

$0B$2B$4B$6B$8B$10BQ4 '25Q1 '26Q2 '26Q3 '26$9.41B
Data
Deferred revenue
Q4 '25$1.58B
Q1 '26$4.78B
Q2 '26$5.98B
Q3 '26$9.41B
Deferred revenue, money customers pay before compute is delivered, in US$ billions by calendar quarter. Source: Nebius SEC filings.6

But customers do not cover everything. Third-quarter revenue rose 571% to $980.8 million while capex ran $7.3 billion, 7.6 times a year earlier, and net debt jumped over 1,243% in the quarter 4. The gap was filled with 12.7 million shares sold through the at-the-market program in Q2 at an average of $224, for about $2.8 billion, plus convertible notes and a 364-day Citi−3.15% — Citi, down 3.15 percent today loan costing up to 3.5 points over SOFR 1.

Nebius's capex has outrun its revenue all year, $7.3 billion against $1 billion in Q3

  • Capital expenditure
  • Revenue
$0B$2B$4B$6B$8BQ4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26$7.3B
Data
Capital expenditureRevenue
Q4 '24$0.42B$0.04B
Q1 '25$0.54B$0.05B
Q2 '25$0.51B$0.11B
Q3 '25$0.96B$0.15B
Q4 '25$2.06B$0.23B
Q1 '26$2.47B$0.4B
Q2 '26$5.65B$0.58B
Q3 '26$7.3B$0.98B
Quarterly capital expenditure and revenue in US$ billions, Q4 2024 through Q3 2026. Source: Nebius SEC filings.6

The price of dilution has halved

Here is the problem with the third funding source. The stock closed Nov. 19 at $96.92, down 9.39% on the day and more than 35% since the end of October 2. The same $2.8 billion raised in Q2 now takes roughly 29 million shares, more than double 52. Nebius also cut its 2026 outlook on third-party capacity delays 5, and the market is repricing the equity before the balance sheet is tested 2.

The Q4 report is the referendum

Two camps want proof. Nvidia and the lenders require customer cash before GPUs or guarantees move; the neoclouds must sell compute in advance to get the chips. Nebius says it has already crossed that line.

The Q4 report, expected early next year, decides it 1. If prepayments still cover more than 100% of the capital behind new deals and the ATM stays shut, $96.92 misprices a company that does not need Nvidia's guarantee 1. If the ATM reopens below $100, every dollar of capex costs more than twice the shares it cost in Q2, and shareholders pay the difference 2. Watch the prepayment coverage line and the share count first.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading NBIS

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Musk warns of an AI cash crunch in 2027, two days after SpaceX sold $32 billion of chip debt

    The chief executive of the company that just borrowed at 8.259% says the industry's cash comes up short in 2027, the same half-year the five-year chip-lease payments begin. Holders of SpaceX (SPCX) price that disagreement before 797.6 million shares unlock on December 8.

    Data Center

    Microsoft's free cash flow fell 27% to $18.6 billion with December-quarter capex guided above $50 billion

    Satya Nadella is promising to keep operating cash flow positive while spending more than $50 billion on December-quarter capex. He is the last hyperscaler chief who can: Amazon, Alphabet, Meta and Oracle all burned cash in their latest quarters, and Nvidia says its neocloud backstops hold only while builds stay on schedule.

    Data Center

    Arista Networks co-founder's preset trading plan sold $56 million of stock two days before a 12% drop

    Andreas Bechtolsheim's preset trading plan averaged $187.04 a share on November 18; two sessions later Arista closed at $167.62, down 11.6 percent. The Form 4 reached EDGAR after Friday's close, so the drop's coverage does not carry it, and it lands on a company that owes suppliers $11.4 billion on the view that AI demand keeps growing.

    Data Center

    Everpure fell 13% after a 51% revenue quarter, trading below its insiders' $98.88 sale price

    Two sessions after a 51% revenue quarter and a third straight guidance raise, Everpure fell 13% on November 20 to near $92, under the $98.88 low of the November 10 insider sales and just above UBS's $89 Sell target. Twenty analysts average $149.53; that $58 gap is the disagreement investors are now pricing.

    Data Center

    Atreides and SCGE paid $423 million for Ciena shares now worth about a third less

    Atreides Management and SCGE Management disclosed the stakes this week, set at Sept. 30 prices weeks before the post-election AI slide. Ciena's December 10 report is the first document that can say who was right.

    Data Center

    Hut 8 fell 15% the day after Anthropic's $119.5 billion IPO; $10.7 billion of River Bend rent is unsigned

    Anthropic closed its second session at $88.30, near its $83 IPO price, and the listing pitched as fresh money for Hut 8's expansion gave back its debut gain within a day. Of River Bend's potential $17.7 billion in lease value, $10.7 billion is renewals that Google does not guarantee and Anthropic has not signed.

    Subscribe to TheInference for free