Nebius says customers prepay for all new capacity, but $4.04 billion of receivables is uncollected
Nebius's CEO says customers now fund the $40–45 billion 2027 build before the machines arrive, the same answer CoreWeave gave on November 10. The catch for NBIS and CRWV holders: third-quarter operating cash flow went negative and $4.04 billion of bills sit uncollected.
Vincent Jiangthree-minute read
A 16% selloff, answered with a billing term
Arkady Volozh opened Nebius's−12.27% — Nebius, down 12.27 percent today earnings call with the question that had just knocked 16% off his stock: "How fast can AI build-out happen, and who will pay for it?" 15 The November 12 report had lifted 2026 capex guidance to about $27 billion and set 2027 spending at $40–45 billion, where the FactSet+0.30% — FactSet, up 0.30 percent today consensus sat at $28.77 billion 1. His answer on who pays: prepayments on new contracts "now cover more than 100% of the capital needed to bring this contracted capacity online," up from 50–60% last quarter 1. The Inference covered the numbers; the funding answer is what is new since.
Customers are paying before the machines arrive
The plan leans on cash arriving ahead of the steel. Nebius expects $10 billion of committed prepayments this year and $17–20 billion in 2027, and its shareholder letter says prepayments plus asset-backed loans on investment-grade contracts should fund 75–85% of 2027 capex 134. Third-quarter deals carried annual contract value above $25 million per megawatt, up from $20–25 million, with payback shortened to one year and seven months 12. Customers have signed more than $12 billion of new contracts since the quarter began, on top of commitments above $40 billion led by Microsoft−0.28% — Microsoft, down 0.28 percent today at up to $19.4 billion 23.
Prepayments cover about a third of 2026 capex, and under half of 2027's
- Capex guidance
- Committed prepayments
- Estimate
Data
| Capex guidance | Committed prepayments | |
|---|---|---|
| 2026 (estimate) | $27B | $10B |
| 2027 (estimate) | $42.5B ($40–45B) | $18.5B ($17–20B) |
The cash has not landed
The third-quarter tape is the counterweight. Operating cash flow, above $2 billion a quarter in the first half, flipped to negative $273 million against $465.8 million of adjusted EBITDA, its first negative quarter in a year 19.
Receivables hit $4.04 billion on September 30, up $3.76 billion in one quarter and nearly four times the period's $980.8 million of revenue, while deferred revenue rose $3.43 billion 1.
Delivery is slipping too: colocation sites including New Jersey are behind schedule, pushing planned revenue into 2027 and trimming the 2026 revenue guide to $3.0–3.2 billion 125. CFO Dado Alonso's answer: "We have no doubt that this capacity will be sold. Clients are looking for capacity already for 2028" 5.
Operating cash flow flipped negative as capex hit $7.3 billion
Customer cash outran the build for three quarters, then flipped negative in Q3
- Operating cash flow
- Capex
Data
| Operating cash flow | Capex | |
|---|---|---|
| Q4 2025 | $0.83B | $2.06B |
| Q1 2026 | $2.26B | $2.47B |
| Q2 2026 | $2.25B | $5.65B |
| Q3 2026 | -$0.27B | $7.3B |
CoreWeave made the same argument two days earlier
CoreWeave−8.55% — CoreWeave, down 8.55 percent today (CRWV), the other big listed neocloud, as the GPU-rental firms are known, gave the same answer on November 10 67. "We will not use the unsecured debt market to fund our business at current yields, nor do we need to," CEO Michael Intrator said, alongside about $9 billion of customer prepayments expected over three months 67.
Bond investors are the holdouts: some CoreWeave yields traded above 15% before the print, on $46.9 billion of debt 67. Jasper Zhang, CEO of GPU marketplace Hyperbolic, says the market is punishing delivery, execution and leverage, not GPU demand 8. Nebius carries $14.19 billion of debt excluding leases against $7.43 billion of cash 1.
CoreWeave has spent $40.8 billion against $9.4 billion of operating cash flow since mid-2024
- Operating cash flow
- Capex
Data
| Operating cash flow | Capex | |
|---|---|---|
| Q2 2024 | -$0.12B | $2.25B |
| Q3 2024 | $0.64B | $1.22B |
| Q4 2024 | $0.19B | $3.5B |
| Q1 2025 | $0.06B | $1.41B |
| Q2 2025 | -$0.25B | $2.45B |
| Q3 2025 | $1.69B | $2.39B |
| Q4 2025 | $1.56B | $4.06B |
| Q1 2026 | $2.98B | $7.7B |
| Q2 2026 | $0.68B | $6.42B |
| Q3 2026 | $1.98B | $9.44B |
December's bank statement decides it
Atreides Management's Gavin Baker set the scoreboard on November 10: when customers prepay, "OCF to EBITDA is the most important metric," and a company collecting up front should run cash ahead of earnings 1. If the $4.04 billion of receivables clears by December 31, fourth-quarter operating cash flow swings back above EBITDA, right where the bulls need it 1. The 75–85% answer is only as good as December's bank statement 1.