onsemi scraps its $2 billion Czech fab as quarterly capex shrinks to $19 million

onsemi and the Czech ministry killed the $2 billion Roznov fab on November 6, with quarterly capital spending already down to $19 million. The next day the chief executive re-anchored silicon carbide on Korea, and Wolfspeed's own quarter shows the wafer market onsemi walked away from.

Vincent JiangVincent Jiangthree-minute read
Share
Hassane El-Khoury, president and chief executive of onsemi
1 / 5Slide 1 of 5
onsemi chief executive Hassane El-Khoury re-anchored the company's silicon carbide strategy on its Bucheon plant in Korea the day after scrapping the Czech fab

The promise lasted 29 months

On November 6, onsemi+0.78% — onsemi, up 0.78 percent today and the Czech Industry Ministry agreed not to proceed with the silicon carbide (SiC) expansion at its Roznov pod Radhostem site, a project initially valued at as much as $2 billion 1. Announced in June 2024, it was billed as the biggest single foreign investment in the Czech Republic since the 1993 split of Czechoslovakia, with jobs at the site set to rise from 1,700 to 3,000 3. The plan covered end-to-end SiC production, from crystal growth to finished power devices 2. The promise lasted 29 months 2.

Both sides blame the market

The company and the ministry cited evolving market dynamics and project economics 2. First Deputy Prime Minister and Industry Minister Karel Havlíček tied the decision to current conditions across the global semiconductor market 2. Existing silicon and SiC operations at Roznov stay open, and onsemi says it will keep hiring and investing there and at its Brno development center 2.

onsemi's site at Roznov pod Radhostem in the Czech Republic
The Roznov pod Radhostem site, where existing silicon and SiC operations stay open after onsemi and the Czech ministry cancelled the $2 billion expansion.Hugo, CC BY 4.0

The cash went to deals instead

The cancellation lands four days after onsemi agreed to buy Ferric, an integrated voltage regulator startup, for $600 million in cash plus up to $175 million in revenue milestones, a deal that lifted its 2030 AI data center revenue target above $3 billion 4. In October it moved the Synaptics+0.26% — Synaptics, up 0.26 percent today acquisition to an all-cash $123 per share, roughly $5.7 billion, backed by a committed $2.45 billion Morgan Stanley term loan 5.

The Inference reported on November 3 that the buyback had been cut to $19.9 million 6. Meanwhile the fab budget has nearly vanished: capital spending was $19 million in Q3 2026, down 95% from the $385 million spent in Q4 2023 10.

onsemi's capital spending is down 95% from Q4 2023

Capex fell 95% from Q4 2023 as the Czech fab plan died

$0B$0.1B$0.2B$0.3B$0.4BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$0.02B
Data
Capital spending
Q4 '23$0.39B
Q1 '24$0.23B
Q2 '24$0.14B
Q3 '24$0.16B
Q4 '24$0.15B
Q1 '25$0.15B
Q2 '25$0.07B
Q3 '25$0.05B
Q4 '25$0.04B
Q1 '26$0.02B
Q2 '26$0.03B
Q3 '26$0.02B
onsemi quarterly capital expenditure, USD billions, from its SEC filings10

The market it left was already shrinking

Wolfspeed's+16.60% — Wolfspeed, up 16.60 percent today own quarter posted the numbers that back the exit: substrate revenue fell 41% year over year to $38.2 million while its own device line fell 11%, and non-GAAP gross margin stood at -13% 7. onsemi's quarter, by contrast, brought $1.72 billion of revenue at a 41.4% GAAP gross margin 7. A diversified power franchise can walk away from a bet a leveraged pure-play cannot.

Deals get $6.3 billion while the $2 billion fab is scrapped

Deals get $6.3 billion while the $2 billion fab is scrapped

$0M$2,000M$4,000M$6,000MSynaptics acquisitionCzech SiC fab (scrapped)Ferric acquisitionQ3 '26 capex$19M
Data
Committed value
Synaptics acquisition$5,700M
Czech SiC fab (scrapped)$2,000M
Ferric acquisition$600M
Q3 '26 capex$19M
Committed deal values and quarterly capital spending, USD millions1,4,5,10

The day-after answer runs through Korea and the data center

The next day, November 7, chief executive Hassane El-Khoury told ChosunBiz that the Bucheon plant in Korea "plays a pivotal role in Onsemi's long-term SiC strategy"; a 2023 expansion there of about 1.4 trillion won targets more than 1 million 200mm wafers a year 8. He projected AI data center revenue would more than double this year 8. Analysts spent earnings week cutting targets, Evercore−1.89% — Evercore, down 1.89 percent today to $90 from $137 and Goldman−0.12% — Goldman, down 0.12 percent today to $85 from $95, yet the average target still sits at $96.16 against Friday's close of $63.31 9.

What decides it

Company guidance puts Q4 revenue at $1.72 billion to $1.82 billion 9. The tell is not onsemi's device line; it is whether substrate demand recovers at all, measured next in Wolfspeed's materials line and Infineon's ordering. Infineon extended its Wolfspeed wafer agreement to 200mm on October 15, so the bears are not unanimous 7.

Automotive was 51.4% of onsemi's revenue mix 9; if AI data center power keeps compounding while that book stalls, the scrapped fab becomes the cheapest decision El-Khoury ever made. If AI demand also stalls, he will have killed the fab and levered the balance sheet in the same quarter.

Get Chips by email, free

How AI demand is reshaping chipmakers, memory and the fabs behind them. In our daily email, every weekday.

Loading ON

Reader comments

0 comments

    Chips

    Aehr tripled its revenue in a quarter and Wall Street still cut its price targets

    Aehr Test Systems tripled quarterly revenue, raised its year to $150 million and jumped 26.5% in a day, yet two analysts cut price targets into the rally and the 10-Q names the risks the multiple has to outrun.

    Chips

    Amkor's $12 billion Arizona campus: customers prepay, Washington has paid $0, the utility has no spare power

    A dozen customers are paying upfront for space in Amkor's Peoria campus, the federal CHIPS award has paid nothing, and the utility serving the site says it has no spare power. The stock's 57% fall has repriced that funding structure, taking the shares from 2.9 times sales to 1.1.

    Chips

    Avnet's record quarter came with $8.2 billion of inventory and an $842 million cash burn

    The record quarter came with an $842 million operating cash burn, $2.1 billion of memory-priced inventory and a $650 million convertible struck at $70.27, all ahead of Wishbone's November 20 vote.

    Chips

    The AI selloff mislabeled Vishay: its record quarter came from factories and weapons programs

    Democrats' post-midterm calls for a data-center moratorium knocked 15.2% off the component maker alongside Seagate and Western Digital. AI is a single-digit share of Vishay's sales; the record quarter was industrial power and defense, with customers ordering 18 months ahead.

    Chips

    A trader paid $12.5 million for Micron calls expiring January 15 at $600 after a 17.46% drop

    A $12.5 million block of January 2027 $600 calls went off at the ask the day after Micron's worst one-day drop of the year, while the company itself splits its capital: $31 billion of new Singapore capacity moving ahead, a $4.5 billion Taiwan plant paused. The December quarter guide is the number both camps must beat.

    Chips

    Broadcom tops Anthropic's $895 billion compute bill and guarantees up to $72 billion of its debt

    Anthropic's amended S-1 names Broadcom the biggest counterparty in $895.4 billion of compute commitments, and the only supplier guaranteeing the financing behind them. The same filing shows compute costs rising faster than revenue, and ARK sold the stock into the rout.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.