Amkor's $12 billion Arizona campus: customers prepay, Washington has paid $0, the utility has no spare power

A dozen customers are paying upfront for space in Amkor's Peoria campus, the federal CHIPS award has paid nothing, and the utility serving the site says it has no spare power. The stock's 57% fall has repriced that funding structure, taking the shares from 2.9 times sales to 1.1.

Richard TangRichard Tangthree-minute read
Share
Aerial view of Amkor's Peoria, Arizona packaging campus under construction in the desert
1 / 6Slide 1 of 6
Amkor's Peoria, Arizona campus under construction in June 2026, before advanced packaging production is due to start in 2028

Amkor's+7.71% — Amkor, up 7.71 percent today $12 billion Peoria, Arizona packaging campus is being funded three ways, and only one of the three is paying: customers prepay cash to reserve space, the Arizona utility is building power on 25-year contracts it has signed with others, and the federal government has paid nothing yet on a $407 million award 452. The stock's fall of 57% between May 10 and November 6 is the market repricing that funding structure, because the quarter's own revenue was nearly flat 3.

If prepaid capacity converts to revenue on the 2028 schedule Amkor has published, the price now on the screen is too low for 2027 and 2028. The rest of this piece is about who carries the plant until then.

Customers fund the plant, Washington has paid nothing yet

Start with the money, because it is new. CFO Megan Faust said on the October 26 call that a dozen customers have signed advance-payment arrangements since 2025, putting cash up front to lock in multiyear advanced-packaging production space in Korea and Arizona 4. Customers are funding the expansion.

Washington is not: Amkor's October SEC filing shows $553.3 million of construction costs incurred in Peoria through September 30 and zero received from the federal CHIPS award of up to $407 million, which pays only as construction and production milestones are met 2.

The power for the campus is being built on other customers' contracts

On November 4, Pinnacle West, the utility that would serve the campus, said it has no excess generation or transmission capacity anywhere in its territory, and it is raising $700 million of notes and about $235 million of equity to build for chip customers on 25-year direct contracts 5. The one 25-year direct pricing contract it named is TSMC's+7.02% — TSMC, up 7.02 percent today, for about 1.88 gigawatts at full build-out 5.

It cites Amkor's campus only among new manufacturing demand, and uncontracted data center and manufacturing demand remains outside its current plan 5. A power contract for Peoria is still ahead of the company.

The quarter gives the market its case

Revenue was $1,991 million, up 0.2% year on year after 25.6% growth the quarter before, and the fourth quarter is guided flat at $1.9 to 2.0 billion 13. Advanced products revenue fell to $1,632 million from $1,684 million, while mainstream wirebond, the older lower-technology packaging used for simpler chips, rose to $359 million from $303 million 1. The gross margin gain to 18.3% was almost entirely cheaper materials; depreciation and labor took 2.8 points back, and more depreciation arrives as new plants open 1.

Amkor's computing share climbed from 19% to 26% while smartphones fell to 37%

Computing and auto replaced smartphones as Amkor's revenue base in one year

  • Computing
  • Automotive & industrial
  • Communications
  • Consumer
0204060Jul-Sep 2025Jul-Sep 20262622
Data
ComputingAutomotive & industrialCommunicationsConsumer
Jul-Sep 202519165114
Jul-Sep 202626223715
Share of quarterly revenue by end market, July-September 2025 versus July-September 2026, in percent of total revenue. Source: Sector Signals.1

Who carries the plant while it is empty

So who carries it? Customers reserve space and get locked-in capacity; Amkor gets cash for a plant it cannot yet fill; taxpayers have paid nothing; shareholders own the years between groundbreaking and advanced revenue 234.

The repricing has a before and after. Amkor traded at 2.9 times sales at the end of June, the highest multiple of any quarter-end back to late 2016, and by the November 6 close it stood at 1.1 times, with trailing earnings at 13.1 times against 21.8 for the S&P 500 3. That is the price assuming the gap between the plant and its revenue lasts. The evidence to watch is fourth-quarter gross margin and the 2027 capital plan due in February 3.

Get Chips by email, free

How AI demand is reshaping chipmakers, memory and the fabs behind them. In our daily email, every weekday.

Loading TSM

Reader comments

0 comments

    Chips

    IBM's quantum chip beat a supercomputer on a benchmark, but IonQ rose 8.95% while IBM fell 1.73%

    A third-party benchmark showed IBM's commercial quantum chip beating an exascale supercomputer, and its most advanced machine went live in Chicago, yet IBM fell 1.73% while narrative-led IonQ rose 8.95%. The market is pricing optimism, not the dated 2028 revenue line only IBM carries.

    Chips

    Aehr tripled its revenue in a quarter and Wall Street still cut its price targets

    Aehr Test Systems tripled quarterly revenue, raised its year to $150 million and jumped 26.5% in a day, yet two analysts cut price targets into the rally and the 10-Q names the risks the multiple has to outrun.

    Chips

    Avnet's record quarter came with $8.2 billion of inventory and an $842 million cash burn

    The record quarter came with an $842 million operating cash burn, $2.1 billion of memory-priced inventory and a $650 million convertible struck at $70.27, all ahead of Wishbone's November 20 vote.

    Chips

    The AI selloff mislabeled Vishay: its record quarter came from factories and weapons programs

    Democrats' post-midterm calls for a data-center moratorium knocked 15.2% off the component maker alongside Seagate and Western Digital. AI is a single-digit share of Vishay's sales; the record quarter was industrial power and defense, with customers ordering 18 months ahead.

    Chips

    onsemi scraps its $2 billion Czech fab as quarterly capex shrinks to $19 million

    onsemi and the Czech ministry killed the $2 billion Roznov fab on November 6, with quarterly capital spending already down to $19 million. The next day the chief executive re-anchored silicon carbide on Korea, and Wolfspeed's own quarter shows the wafer market onsemi walked away from.

    Chips

    A trader paid $12.5 million for Micron calls expiring January 15 at $600 after a 17.46% drop

    A $12.5 million block of January 2027 $600 calls went off at the ask the day after Micron's worst one-day drop of the year, while the company itself splits its capital: $31 billion of new Singapore capacity moving ahead, a $4.5 billion Taiwan plant paused. The December quarter guide is the number both camps must beat.