Power

Oracle trucks fuel at four times pipeline cost to its AI campuses while Trump posts a power mandate

The Truth Social "mandate" is political cover, not a rule, but it ratifies a system Oracle already runs: fuel-cell power on site, fuel by truck, and the bill on shareholders. Bloom sends some of the money back to Oracle in equity.

Richard TangRichard Tang · 2 min read
Share
Bloom Energy fuel cell servers, the on-site generation Oracle buys for its AI campuses, lined up outside an eBay data center in 2010.
1 / 6Slide 1 of 6
Bloom Energy fuel cell servers outside an eBay data center in 2010. Oracle buys Bloom's fuel cells for on-site power at its AI campuses.

President Trump posted on October 21 that large data centers are "mandated by me to make their own electricity," sell the surplus back to the grid and pay host towns a dividend 1. The mandate is not a rule: it restates the Ratepayer Protection Pledge Oracle−3.53% — Oracle, down 3.53 percent today and six other tech companies joined in March, which experts told the Associated Press is not federally enforceable 1. The plan it describes is real, though, and Oracle is already living it. The money trail says shareholders pay the bill while the supplier collects.

Oracle runs the model, and carries the fuel bill

Oracle self-supplies its AI campuses with Bloom Energy−10.41% — Bloom Energy, down 10.41 percent today fuel cells under an April 13 agreement for up to 2.8 gigawatts 1. At Project Jupiter in New Mexico, a 2.45-gigawatt microgrid, Oracle bears all energy costs and committed $360 million to local schools and infrastructure, the "dividend" Trump described, promised months before he asked 4. The company has proposed cutting the site's permitted emissions about 35% under New Mexico regulator review 3.

The pipe slipped, so the fuel arrives by truck

The catch is fuel and plumbing. The pipeline meant to feed Jupiter slipped to February 2027, so Oracle trucks compressed gas to some sites at roughly four times pipeline cost, and it invoked force majeure on the project in September 1. That converts a ratepayer's power bill into Oracle's cash burn: free cash flow was negative $28.7 billion over the past year and the stock is down about half in 12 months 1.

Oracle's capital spending has run more than twenty fold higher in three years

0102030Q1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '2628.5
Data
Capex
Q4 '231.08
Q1 '241.67
Q2 '242.8
Q3 '242.3
Q4 '243.97
Q1 '255.86
Q2 '259.08
Q3 '258.5
Q4 '2512.03
Q1 '2618.64
Q2 '2616.49
Q3 '2628.5
Capital spending per quarter, in US dollars, from Oracle's SEC filings [5]. Oracle's free cash flow has been negative over the same span, as the text notes.5

Bloom gets paid, partly in a loop

Bloom sits on the paid side of the trade, and the arrangement is circular in a way the filings show plainly. Bloom granted Oracle a warrant for 3.5 million shares, $324.4 million of consideration booked as a reduction of Bloom's own revenue, so the supplier partly pays its biggest customer in equity, and one unnamed customer was 73% of Bloom's Q2 revenue 2.

The next prints decide whether self-power is strategy or subsidy: Bloom's Q3 today, a hearing on Jupiter's air permit October 26, and New Mexico's decision deadline November 23 2. Watch the plumbing, not the post: the AI race now turns on who can get fuel to the front gate 1.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading ORCL…

Reader comments

0 comments

    Power

    AEP's $4 billion Bloom Energy plant has Google buying 20 years of power and a December deadline

    American Electric Power's $4 billion, 702-megawatt Wyoming plant on Bloom equipment, with Google buying the power for 20 years, is the fuel-cell maker's biggest new commitment since Oracle. But the fine print gives the customer a contractual exit in December, and the utility hedged with a rival vendor the day before.

    Power

    Xcel runs two price books for AI data centers: one public, one confidential

    Colorado opened hearings this week on Xcel's public rulebook for big power customers, while the confidential custom contracts that could carry the biggest loads get only a 120-day review. Minnesota's attorney general wants the same question answered in the open: who pays if the AI boom cools.

    Power

    Constellation's nuclear contracts run 20 years; its cash problem is due now

    Google, Amazon and Meta have locked up the largest US carbon-free power producer under contracts as long as 20 years, and the stock is still down 23 percent this year. Free cash flow has been negative for three straight quarters; the November 6 report shows whether $5.9 billion of court-ordered plant sales closes the gap.

    Power

    Missouri just approved 945 MW of grid. Ameren has already signed 2,800 MW of data centers

    The Missouri PSC approved 945 megawatts of batteries and solar on October 21; Ameren's own plan commits 2.8 gigawatts of signed data center load, ramping from the second half of 2027. The $4 billion to $6 billion that closes the gap has no rate order yet, and 1.3 million ratepayers are waiting to see their share.

    Power

    Amazon's Indiana nuclear deal is a study; AEP's 69 GW of sold load is the story

    AEP, Amazon and X-energy will study twelve small reactors at a retired Indiana coal plant, with no cost, date or contract price disclosed. AEP has contracted 69 GW of new load against the 33 GW of capacity it owns or contracts, and its October 28 capital plan prices the gap.

    Power

    DTE asks Michigan regulators for $6.4 billion in gas; Sierra Club says AI data centers drive it

    DTE's 20-year plan asks for 2.1 gigawatts of gas at an estimated $6.4 billion, more than double what its 2023 coal-retirement deal called for, and Earthjustice says data centers drive the gap. The commission already wrote a make-Google-pay template; whether it applies it to the gas plants decides who earns and who pays.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.