Xcel runs two price books for AI data centers: one public, one confidential

Colorado opened hearings this week on Xcel's public rulebook for big power customers, while the confidential custom contracts that could carry the biggest loads get only a 120-day review. Minnesota's attorney general wants the same question answered in the open: who pays if the AI boom cools.

Vincent JiangVincent Jiangthree-minute read
Share
Minnesota Attorney General Keith Ellison
1 / 6Slide 1 of 6
Minnesota Attorney General Keith Ellison, whose office says ratepayer exposure to the Xcel-Google Pine Island deal could exceed $1 billion, wants the contract's terms argued in the open. (Lorie Shaull, CC BY-SA 4.0)

Hearings opened on the public rulebook

Colorado's utility commission opened hearings on Wednesday on the rulebook that will govern every big power customer Xcel Energy−0.95% — Xcel Energy, down 0.95 percent today signs in the state, and the sharpest question is about the deals the rulebook might never see.

Xcel, Colorado's largest electric utility with 1.6 million customers, filed a "large load tariff" in April for any new customer needing 50 megawatts or more: a $120,000 application fee, a 15-year contract, a commitment to pay for at least 80% of projected power, minimum monthly bills the company sizes at $22 million for a 500-megawatt center, and an exit fee covering every remaining bill 1.

The complication sits in the same filing

A parallel "custom contract" pathway would let Xcel negotiate confidential deals, reviewed by the commission in 120 days, that need not carry the tariff's safeguards 1. Xcel estimates it needs 2 gigawatts of new generating capacity just for data centers by 2030, against just over 7 gigawatts of total capacity today 1. Where those gigawatts run, through the public tariff or the confidential pathway, is the fight.

Even the contract length is contested: 10, 15 or 20 years

0 yrs5 yrs10 yrs15 yrs20 yrsData Center Coalition10 yrsXcel Energy15 yrsSame length as the Google dealPUC staff20 yrs
Data
Value
Data Center Coalition10 yrs
Xcel Energy15 yrs
PUC staff20 yrs
Proposed contract terms in years for Xcel's Colorado large-load tariff, from testimony and filings before the Colorado PUC. Sources: The Colorado Sun, October 21, 2026 [1].1

The other price book is public but not yet approved

Google's proposed 780-megawatt data center in Pine Island, Minnesota, would be backed by 1,900 megawatts of new wind, solar and storage; Google+1.01% — Google, up 1.01 percent today would pay at least 75% of its contracted capacity every month and up to 96 months of on-peak demand charges if it walks 24. That contract is pending before the Minnesota Public Utilities Commission 2.

Xcel values the deal at about $1.1 billion in net benefits to other customers 2. Minnesota Attorney General Keith Ellison's office counters that ratepayer exposure could exceed $1 billion once the contract ends or Google exits early, and faults Xcel for redacting nearly every dollar figure in the filing 2.

Xcel chief executive Bob Frenzel told analysts in April that the company's hyperscaler partnerships "set a high bar for responsible large load development," and that large-load growth "doesn't increase costs for our existing customers" 5.

The scale explains the urgency

Xcel's five-year capital plan is $60 billion 5, and its quarterly capital spending has nearly doubled in ten quarters 6. The company already has 2 gigawatts of data centers contracted or under construction and told analysts it hopes to sign another 6 gigawatts by the end of 2027 5. Ellison's office, reading the same strategy from the Minnesota filing, says the promise that big customers pay their own way is not yet demonstrated there 2. Both commissions are being asked to decide whether that promise holds before the next gigawatts get signed 12.

Xcel's quarterly capital spending has nearly doubled in ten quarters

1.5B2B2.5B3B3.5BQ2 '24Q4 '24Q2 '25Q4 '25Q2 '262.95B
Data
Capital spending
Q1 '241.54B
Q2 '241.83B
Q3 '241.78B
Q4 '242.22B
Q1 '251.99B
Q2 '252.43B
Q3 '253.06B
Q4 '253.44B
Q1 '263.02B
Q2 '262.95B
Quarterly capital expenditures in USD billions, Xcel Energy SEC filings, Q1 2024 through Q2 2026, as compiled by company_series, retrieved October 22, 2026 [6].6

The middle ground, contested

Jack Ihle, Xcel's vice president for data centers and large loads, defended the tariff he filed in April as "a reasonable and balanced middle ground" between approaches that would impose commercially impractical obligations and ones that would shift costs to existing customers 1. The Data Center Coalition, an industry trade group, wants 10-year terms; commission staff want 20 1.

The company also points to residential bills rising 1.55% a year since 2013, below inflation, and has offered to freeze Minnesota base rates until November 2028 to blunt the affordability backlash 23. But eight Colorado municipalities have imposed or are weighing data center caps, and a 5,000-signature petition reached the commission this month 1.

What to watch next

Minnesota's commission has not ruled on the Google contract; Colorado's hearings run for several days 12. The number to watch is routing: how much of Xcel's data-center load gets signed under the public tariff and how much in confidential custom contracts 12. Whatever lands there is what ratepayers, and the investors betting on Xcel's $60 billion buildout, are left holding 12.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading XEL

Reader comments

0 comments

    Power

    First Solar's CEO put $150 million into India, toward $1 billion, as capex fell for eight straight quarters

    Investors bid up First Solar on a friendlier Washington the same week its chief executive put another $150 million into India and said policy certainty is "absolutely critical". The capital is speaking louder than the stock.

    Power

    Vistra guided 2027 EBITDA to $7.7 to $8.5 billion with 98% of output hedged before the Texas vote

    Vistra's first 2027 outlook landed with about 98% of next year's output already hedged before the Texas election, and the market that had marked the stock down 16% on the governor's race paid up for a year a January inauguration cannot touch. The open fight starts in 2028, where the hedges run out.

    Power

    Kinder Morgan's Southeast Connector just got bigger: 20 shippers, 48-inch pipe, 3.7 Bcf/d in sight

    Two weeks after a $3.1 billion FID sized the pipe at 2.6 Bcf/d, Kinder's bulletin board shows another 1.1 Bcf/d of shipper awards and 20 takers. The land fight along the 150-mile Tennessee route has not started yet; the commercial demand already beat the plan.

    Power

    Walmart invested in Base Power, which claims 100 megawatts a month on a $13 billion valuation

    Base Power announced backup batteries for nearly 6,500 North Texas homes, a Walmart investment, and a 100 MW-a-month install pace, all on a $13 billion valuation. Homeowners fund the fleet; Base pools it and sells it back to the grid.

    Power

    Oklo raised $2.25 billion selling stock at $70.19; the market values everything it builds at $700 million

    The Q3 filing holds Oklo's build guidance and posts record construction spending; at a $3.8 billion market value against $3.13 billion banked, the market carries everything the company does beyond holding cash at roughly $700 million.

    Power

    MARA moved 1,650 bitcoin worth $132.8 million as its $1.5 billion gas plant deal finds no AI tenant

    The bitcoin miner moved 1,650 coins to institutional venues the same day FERC cleared its $1.5 billion gas plant deal, and the stock sank 14% anyway. Its AI pivot runs on bitcoin-backed debt, and the promised AI lease still has no tenant.