Power

Xcel runs two price books for AI data centers: one public, one confidential

Colorado opened hearings this week on Xcel's public rulebook for big power customers, while the confidential custom contracts that could carry the biggest loads get only a 120-day review. Minnesota's attorney general wants the same question answered in the open: who pays if the AI boom cools.

Vincent JiangVincent Jiang · 3 min read
Share
Minnesota Attorney General Keith Ellison
1 / 6Slide 1 of 6
Minnesota Attorney General Keith Ellison, whose office says ratepayer exposure to the Xcel-Google Pine Island deal could exceed $1 billion, wants the contract's terms argued in the open. (Lorie Shaull, CC BY-SA 4.0)

Hearings opened on the public rulebook

Colorado's utility commission opened hearings on Wednesday on the rulebook that will govern every big power customer Xcel Energy+2.75% — Xcel Energy, up 2.75 percent today signs in the state, and the sharpest question is about the deals the rulebook might never see.

Xcel, Colorado's largest electric utility with 1.6 million customers, filed a "large load tariff" in April for any new customer needing 50 megawatts or more: a $120,000 application fee, a 15-year contract, a commitment to pay for at least 80% of projected power, minimum monthly bills the company sizes at $22 million for a 500-megawatt center, and an exit fee covering every remaining bill 1.

The complication sits in the same filing

A parallel "custom contract" pathway would let Xcel negotiate confidential deals, reviewed by the commission in 120 days, that need not carry the tariff's safeguards 1. Xcel estimates it needs 2 gigawatts of new generating capacity just for data centers by 2030, against just over 7 gigawatts of total capacity today 1. Where those gigawatts run, through the public tariff or the confidential pathway, is the fight.

Even the contract length is contested: 10, 15 or 20 years

0 yrs5 yrs10 yrs15 yrs20 yrsData Center Coalition10 yrsXcel Energy15 yrsSame length as the Google dealPUC staff20 yrs
Data
Value
Data Center Coalition10 yrs
Xcel Energy15 yrs
PUC staff20 yrs
Proposed contract terms in years for Xcel's Colorado large-load tariff, from testimony and filings before the Colorado PUC. Sources: The Colorado Sun, October 21, 2026 [1].1

The other price book is public but not yet approved

Google's proposed 780-megawatt data center in Pine Island, Minnesota, would be backed by 1,900 megawatts of new wind, solar and storage; Google−2.34% — Google, down 2.34 percent today would pay at least 75% of its contracted capacity every month and up to 96 months of on-peak demand charges if it walks 24. That contract is pending before the Minnesota Public Utilities Commission 2.

Xcel values the deal at about $1.1 billion in net benefits to other customers 2. Minnesota Attorney General Keith Ellison's office counters that ratepayer exposure could exceed $1 billion once the contract ends or Google exits early, and faults Xcel for redacting nearly every dollar figure in the filing 2.

Xcel chief executive Bob Frenzel told analysts in April that the company's hyperscaler partnerships "set a high bar for responsible large load development," and that large-load growth "doesn't increase costs for our existing customers" 5.

The scale explains the urgency

Xcel's five-year capital plan is $60 billion 5, and its quarterly capital spending has nearly doubled in ten quarters 6. The company already has 2 gigawatts of data centers contracted or under construction and told analysts it hopes to sign another 6 gigawatts by the end of 2027 5. Ellison's office, reading the same strategy from the Minnesota filing, says the promise that big customers pay their own way is not yet demonstrated there 2. Both commissions are being asked to decide whether that promise holds before the next gigawatts get signed 12.

Xcel's quarterly capital spending has nearly doubled in ten quarters

1.5B2B2.5B3B3.5BQ2 '24Q4 '24Q2 '25Q4 '25Q2 '262.95B
Data
Capital spending
Q1 '241.54B
Q2 '241.83B
Q3 '241.78B
Q4 '242.22B
Q1 '251.99B
Q2 '252.43B
Q3 '253.06B
Q4 '253.44B
Q1 '263.02B
Q2 '262.95B
Quarterly capital expenditures in USD billions, Xcel Energy SEC filings, Q1 2024 through Q2 2026, as compiled by company_series, retrieved October 22, 2026 [6].6

The middle ground, contested

Jack Ihle, Xcel's vice president for data centers and large loads, defended the tariff he filed in April as "a reasonable and balanced middle ground" between approaches that would impose commercially impractical obligations and ones that would shift costs to existing customers 1. The Data Center Coalition, an industry trade group, wants 10-year terms; commission staff want 20 1.

The company also points to residential bills rising 1.55% a year since 2013, below inflation, and has offered to freeze Minnesota base rates until November 2028 to blunt the affordability backlash 23. But eight Colorado municipalities have imposed or are weighing data center caps, and a 5,000-signature petition reached the commission this month 1.

What to watch next

Minnesota's commission has not ruled on the Google contract; Colorado's hearings run for several days 12. The number to watch is routing: how much of Xcel's data-center load gets signed under the public tariff and how much in confidential custom contracts 12. Whatever lands there is what ratepayers, and the investors betting on Xcel's $60 billion buildout, are left holding 12.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading XEL…

Reader comments

0 comments

    Power

    AEP's $4 billion Bloom Energy plant has Google buying 20 years of power and a December deadline

    American Electric Power's $4 billion, 702-megawatt Wyoming plant on Bloom equipment, with Google buying the power for 20 years, is the fuel-cell maker's biggest new commitment since Oracle. But the fine print gives the customer a contractual exit in December, and the utility hedged with a rival vendor the day before.

    Power

    Constellation's nuclear contracts run 20 years; its cash problem is due now

    Google, Amazon and Meta have locked up the largest US carbon-free power producer under contracts as long as 20 years, and the stock is still down 23 percent this year. Free cash flow has been negative for three straight quarters; the November 6 report shows whether $5.9 billion of court-ordered plant sales closes the gap.

    Power

    Oracle trucks fuel at four times pipeline cost to its AI campuses while Trump posts a power mandate

    The Truth Social "mandate" is political cover, not a rule, but it ratifies a system Oracle already runs: fuel-cell power on site, fuel by truck, and the bill on shareholders. Bloom sends some of the money back to Oracle in equity.

    Power

    Missouri just approved 945 MW of grid. Ameren has already signed 2,800 MW of data centers

    The Missouri PSC approved 945 megawatts of batteries and solar on October 21; Ameren's own plan commits 2.8 gigawatts of signed data center load, ramping from the second half of 2027. The $4 billion to $6 billion that closes the gap has no rate order yet, and 1.3 million ratepayers are waiting to see their share.

    Power

    Amazon's Indiana nuclear deal is a study; AEP's 69 GW of sold load is the story

    AEP, Amazon and X-energy will study twelve small reactors at a retired Indiana coal plant, with no cost, date or contract price disclosed. AEP has contracted 69 GW of new load against the 33 GW of capacity it owns or contracts, and its October 28 capital plan prices the gap.

    Power

    DTE asks Michigan regulators for $6.4 billion in gas; Sierra Club says AI data centers drive it

    DTE's 20-year plan asks for 2.1 gigawatts of gas at an estimated $6.4 billion, more than double what its 2023 coal-retirement deal called for, and Earthjustice says data centers drive the gap. The commission already wrote a make-Google-pay template; whether it applies it to the gas plants decides who earns and who pays.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.