Power

Oracle volunteers to absorb a $300 million nuclear bill in Wisconsin

Oracle will buy 125 to 250 megawatts of Point Beach, Wisconsin's only nuclear plant, and says taking that bill onto itself spares other customers $300 million through 2033. Every decision that matters now sits with one state commission, and the terms are still unwritten.

Vincent JiangVincent Jiangthree-minute read
Share
Aerial view of the Point Beach Nuclear Plant on the shore of Lake Michigan in Wisconsin
1 / 6Slide 1 of 6
The Point Beach Nuclear Plant on the Lake Michigan shore. Oracle has volunteered to buy 125 to 250 megawatts of its output and absorb $300 million in its rising fuel costs, pending approval by Wisconsin regulators.

A hockey stick finds a volunteer

Since 2007, Wisconsin households have paid an escalating price for a nuclear plant their utility sold 41. On 30 September a buyer volunteered: Oracle−4.06% — Oracle, down 4.06 percent today said it will purchase 125 to 250 megawatts of Point Beach, roughly 10 to 20 percent of the demand of the $15 billion, 1.3-gigawatt campus it is building with OpenAI$1.18T — OpenAI, private, latest valuation $1.18T and Vantage Data Centers at Port Washington 1. Oracle sizes the relief at $300 million in fuel costs for more than 1 million customers between 2027 and 2033, pending approval by the Public Service Commission of Wisconsin 123. The clock starts before any campus load: Aterio's base case has partial grid power around December 2027 and full capacity around October 2028, and the announcement does not say what Oracle does with megawatts it cannot yet use 5.

The escalator Oracle steps in front of

NextEra Energy Resources bought Point Beach, two 625-megawatt reactors, from We Energies in 2007 and sells the output back under a contract whose price per megawatt-hour will have doubled between 2009 and 2027, rising 6 to 8 percent a year through 2033 41. NextEra collects that escalator today and, with licenses renewed to the early 2050s last year, would keep collecting that far if the commission approves the extension We Energies seeks 14.

The contract drives 20 percent of We Energies' proposed $176 million electric increase for 2027 and most of a $59 million fuel rise next year, per public filings 1. The utility says an extension could bring more reasonable terms; it has revealed none, and the proposal reaches the commission this fall 1.

Paying retail beats waiting

Oracle's motive is scarcity, not charity. The campus cannot take load until a new American Transmission Company line clears the same commission, a review reset in August, with the completeness ruling due about 19 October 5. "It's available now. It's a burden on the ratepayers. We need the power. We're going to take it," Oracle's Julia Robin said 1.

Oracle's $300 million pledge is about 1 percent of one quarter's capex

$0B$10B$20B$30BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26Point Beach pledge: $0.3B, 2027–33 (Oracle estimate)$28.5BPledge covers seven years; thispoint is one quarter
Data
Oracle capex
Q1 '24$1.67B
Q2 '24$2.8B
Q3 '24$2.3B
Q4 '24$3.97B
Q1 '25$5.86B
Q2 '25$9.08B
Q3 '25$8.5B
Q4 '25$12.03B
Q1 '26$18.64B
Q2 '26$16.49B
Q3 '26$28.5B
Oracle capital expenditures by fiscal quarter, in billions of US dollars, from Oracle's SEC filings compiled by Sharadar; labels are calendar quarters of the fiscal periods shown. The reference line is the $300 million Point Beach commitment spread over 2027 to 2033.1,6

For Oracle the money is loose change: capital spending ran $28.5 billion in the quarter ended 31 August, roughly 95 times the seven-year pledge 6.

Baby steps, and a stacked calendar

Tom Content of the Citizens Utility Board likened the contract to "a hockey stick that keeps hitting customers year after year" and calls Oracle's move "a step in the right direction," but wants terms: "Until we see more details, it's very hard to know if customers are seeing a big win or baby steps" 1. Patience is thin: 74 percent of Wisconsin voters told Marquette's September poll that data centers cost more than they give 17.

Washington just failed to answer that. The House passed the Ratepayer Protection Act 417 to 3 on 16 September; Senate Democrats blocked it 57 to 43 on 30 September, calling its protections optional 18.

A year-end pile-up at the commission

By year-end the same three-member commission rules on We Energies' proposed 9.25 and 5.5 percent residential increases for 2027 and 2028, a decision unlikely to reflect Oracle's deal because the campus does not fully launch until 2028 91. Oracle files its Point Beach plan by year-end. "There's not a lot to take to the bank," Content said 1.

The escalator that has hit Wisconsin bills since 2007 finally found a customer that wants it.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading ORCL

Reader comments

0 comments

    Power

    BMO upgrades Bloom Energy and cuts its target to $230 as its record quarter burned $181 million of cash

    A long-time skeptic turned bull on Bloom's fuel cells and their milestone-based payments. Those same milestones are why record revenue still burned cash, and the fourth-quarter report, with 2027 guidance, decides which reading holds.

    Power

    Southern's Georgia Power and Alabama Power hold $26.5 billion of federal energy loans, the most in DOE history

    The first published ranking of the Energy Department's loan book puts Georgia Power and Alabama Power first, and the November 18 tally shows the whole $73.2 billion book now finances reactors and wires rather than wind, solar or electric vehicles.

    Power

    Vistra registered 5 million Cogentrix shares, about $624 million, for resale as its buyback grows

    Vistra funded its Cogentrix gas-fleet purchase partly in its own stock, registered for resale Nov 9 with a lock-up ending Jan 30, just as the board added $1.5 billion to the buyback. Shareholders who bought the buyback story face roughly $624 million of incoming supply while only 78% of 2028 output is hedged.

    Power

    Louisiana defers Entergy's private grid hearing for Meta to Dec. 16 as a $12.9 billion gas-plant vote nears

    The same December docket now holds a consultant's verdict on Entergy's next rate increase, a hearing on the private grid serving Meta, and the vote on $12.9 billion of gas plants. Whose money carries it moves ETR shareholders and Louisiana ratepayers alike.

    Power

    PG&E signs 20-year Avantus contracts for 800 MW of solar and storage, pending CPUC approval

    The contracts still need approval from the California Public Utilities Commission, and PG&E's third-quarter filing shows the utility's operating cash running $3.4 billion behind its capital spending over the first nine months of 2026. Avantus's backers at KKR and EIG take the construction risk; the 20-year payment obligation lands on PG&E, its lenders and California ratepayers.

    Power

    NRG Energy sells six gas plants to LS Power for $4 billion, pricing one Texas plant at $1,400 per kilowatt

    The 8x cash offer implies about 40% more for the running Texas plant than NRG says new build costs. Neither the deal filing nor the 2027 guidance, which still counts the six plants, values the 20 GW NRG keeps.

    Subscribe to TheInference for free