PG&E has a 12.87GW AI power queue and a $2 billion hole, so Google pays first and ratepayers pay later

PG&E's Q3 call put hard numbers on California's AI power queue: 12.87 gigawatts of data-center requests, 240 megawatts under construction, a $2 billion capital plan cut, and a Google advance that the filing says ends up on ratepayers' bills.

Vincent JiangVincent Jiang · 2 min read
Share
High-voltage transmission towers on a dry California hillside under a blue sky
1 / 6Slide 1 of 6
Transmission lines cross Interstate 580 in California. The connections behind projects like Google's 250-megawatt San Jose building are what its $150 million advance to PG&E would pay for.

California wants AI data centers, and the power queue shows it. On its third-quarter earnings call, PG&E, the utility serving Northern and Central California, reported 12.87 gigawatts of data-center connection requests, up from 12.71 gigawatts in July 2. What has actually been built is a rounding error beside that: 240 megawatts under construction, up from 140 in June, and 174 megawatts brought online since 2024 2.

Nearly all of PG&E's 12.87GW data-center queue is still paperwork: only 0.24GW is under construction

0GW2GW4GW6GW8GW10GWApplication and preliminary engineering8.35GWFinal engineering3.88GWInterconnection construction agreements0.4GWUnder construction0.24GW
Data
Value
Application and preliminary engineering8.35GW
Final engineering3.88GW
Interconnection construction agreements0.4GW
Under construction0.24GW
PG&E's data-center interconnection queue by phase, in gigawatts, as reported on its third-quarter 2026 earnings call. The bar in gold is work under construction; everything else is awaiting engineering or agreements. Source: Data Center Dynamics.2

The utility that cannot afford to build

PG&E−0.68% — PG&E, down 0.68 percent today would like to serve that queue, and said on the call it is planning for 1.8 gigawatts of data-center demand online by 2030 2. The problem is money. The company cut its 2027 capital plan by $2 billion, to $11.4 billion, citing financing constraints, and warned customers that some projects, including connections for new power demand, could be delayed 3.

Its credit sits below investment grade, and debt issued in that condition since 2017 will add about $4 billion of interest expense over the life of the financing 3. Meanwhile the quarter itself earned $2.285 billion, up from roughly $4 million a year earlier 2. Earnings are fine; borrowing is the bottleneck.

Capex kept climbing to $3.3 billion a quarter even as PG&E cut its 2027 plan by $2 billion

$0B$1B$2B$3B$4BQ3 '24Q4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26$3.3B
Data
Capital expenditure, $B
Q3 '24$2.61B
Q4 '24$2.83B
Q1 '25$2.64B
Q2 '25$3.07B
Q3 '25$2.93B
Q4 '25$3.16B
Q1 '26$3.36B
Q2 '26$2.97B
Q3 '26$3.3B
Quarterly capital expenditure in billions of US dollars, from PG&E Corporation's SEC filings, Q3 2024 through Q3 2026. Spending has risen through 2026 even as the company cut its 2027 plan by $2 billion on financing constraints. Source: PG&E Corporation, quarterly figures from its SEC filings, retrieved 30 October 2026.4

Google's $150 million workaround

Enter a customer who does not need to borrow. Google has agreed to pay $600,000 per megawatt up front, $150 million, to cover the transmission connection for a 250-megawatt building at its Meadow Point campus at 5079 Disk Drive in North San Jose, where construction has already started 1. PG&E's own public estimate for the build portion is $64 million to $137 million 1.

State regulators judged the $600,000 rate appropriate to protect ratepayers from general transmission costs, and the California Public Utilities Commission is scheduled to rule this year; construction would follow about six months later and take roughly two years 1.

Who ends up holding the bill

Read the filing's own words. "As a customer is refunded, the related capital costs are added to PG&E's accounts and ultimately recovered from ratepayers" 1. Google−1.38% — Google, down 1.38 percent today advances the cash now, gets paid back over time, and the capital lands in the rate base that California electricity customers finance.

For PG&E investors the structure is a template: hyperscalers fund the interconnections the utility's credit rating cannot, and the funnel of 12.87 gigawatts becomes billable assets 12. For everyone else with a PG&E bill, the queue is the price tag. Watch the CPUC ruling expected this year; approval would make the Google model the default for the next 12 gigawatts of requests 12.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading GOOGL

Reader comments

0 comments

    Power

    FirstEnergy nearly doubles contracted AI load in nine months to 7.9 GW, and Ohio votes on who pays

    FirstEnergy's contracted data-center load nearly doubled in nine months to 7.9 gigawatts, and management put numbers on the shareholders' share of the $36 billion buildout. Regulators in three states, starting with Tuesday's Ohio vote, decide whether the structure pays.

    Power

    Dominion's AI build puts the power bill on data centers, and the carbon bill on everyone else

    Dominion's third-quarter filing this morning sits under three Virginia dockets and Tuesday's election. The 14-year contracts that put the power bill on data centers leave the carbon bill on everyone else, and February's rider ruling will decide whether the AI build keeps its political license.

    Power

    AEP signs Google and SoftBank to pay for its grid, but only 35 of 84 gigawatts have firm contracts

    The utility's 84-gigawatt AI pipeline is no longer just a load forecast: SoftBank and Google are signing to pay for AEP's lines and plants at a set return, while shareholders still fund the rest. The gap between 84 GW contracted and 35 GW firm is where the next share sale lives.

    Power

    Schneider Electric's record €11.46 billion quarter rides AI data centers, with a third price rise planned

    Schneider Electric posted the strongest quarter in its history selling power and cooling to AI data centers, opened its largest medium-voltage plant in China the same week, and CFO Nathan Fast is already promising a third round of price increases in 2027.

    Power

    Johor's grid cannot keep up with AI, so YTL Power is buying 1,623 acres at Port Klang

    The Malaysian utility that brings its own megawatts to Johor's AI data centers has taken 35% of a RM934 million venture turning oil-palm land in Klang into an industrial park. The filing tests the idea that the next scarce asset in AI infrastructure is land with power already attached.

    Power

    Doosan gets paid to build the reactor NuScale still has to sell

    The only NRC-approved small modular reactor just moved a step closer to hardware, but the money in this deal flows to the Korean factory, not to the American designer still waiting for a single binding customer.