Riot Platforms jumps 8.3% as Starboard says the Anthropic leases will bring $2.3 billion of rent by 2028
Riot Platforms closed up 8.3% on the pitch, the market's first answer. Starboard says the market pays less than what Riot's signed rent from Anthropic is worth, and the unproven half is $6.1 billion to $7 billion of project debt, under a lease clause that lets Anthropic charge 12% a year if it never arrives.
Vincent Jiangthree-minute read
Starboard Value chief executive Jeff Smith took the stage at the 13th Annual Capitalize for Kids Investors Conference in Toronto on Wednesday with a landlord's pitch: Riot Platforms+8.45% — Riot Platforms, up 8.45 percent today, the bitcoin miner the activist has pressed toward AI data centers since 2024, is worth more than the market pays 1 2 3. Riot (NASDAQ: RIOT) closed up 8.3% that day 1 2. The same evening, Anthropic$350B — Anthropic, private, latest valuation $350B, the maker of the Claude chatbot and Riot's main tenant, priced the largest stock offering on record at $83 a share, raising $81.3 billion, a listing Starboard had cited as a catalyst 2 6.
Signed rent alone tops the Street's 2028 revenue
Starboard expects Riot's announced leases to generate about $2.3 billion of rental income by mid-to-late 2028, with a real estate investment trust conversion or a sale to a data-center operator as further upside 1 2. The leases carry the arithmetic. Anthropic signed a 15-year, roughly $28 billion lease on the 910-megawatt Corsicana campus in Texas, about $1.9 billion a year, and a 20-year, $9.1 billion lease at Rockdale worth about $455 million a year 1 4.
Riot's quarterly filing names Anthropic as tenant on 1,101 of the company's 1,151 contracted megawatts; chipmaker AMD+6.83% — AMD, up 6.83 percent today holds the other 50 4. At Tuesday's close, Riot traded at 8.2 times forward sales, its share price against the revenue analysts expect over the next year, roughly half its June peak of 16.2 1.
Starboard's rent estimate tops what the Street models for all of Riot's 2028 revenue
Signed rent alone exceeds the consensus for Riot's whole 2028 business
- Estimate
Data
| Value | |
|---|---|
| Street 2027 revenue, est. (estimate) | $854M |
| Street 2028 revenue, est. (estimate) | $1,760M |
| Starboard 2028 rent, est. (estimate) | $2,300M |
The buildings are the bet
The leases are signed; the buildings that must earn that rent are not built. Corsicana needs about $5.5 billion of development spending, and Riot expects $6.1 billion to $7.0 billion of project debt to fund the Corsicana and Rockdale builds 1 4. Operations have burned cash for 11 straight quarters, and Riot sold 20,264 bitcoin for about $1.5 billion this year to keep building 4 8.
Riot's operations have burned cash in 11 straight quarters
Cash burn ran through the year Riot sold 20,264 bitcoin to fund the build
Data
| Operating cash flow | |
|---|---|
| Q4 '23 | $45.04M |
| Q1 '24 | -$57.85M |
| Q2 '24 | -$42.51M |
| Q3 '24 | -$56.33M |
| Q4 '24 | -$98.36M |
| Q1 '25 | -$122.06M |
| Q2 '25 | -$231.32M |
| Q3 '25 | -$114.01M |
| Q4 '25 | -$105.53M |
| Q1 '26 | -$182.65M |
| Q2 '26 | -$90.14M |
| Q3 '26 | -$214.33M |
The lease even prices the shortfall. If debt is not available on acceptable terms, Anthropic can fund up to about $3.6 billion of the build itself and recover the money from rent, with interest at 12% a year 4 5.
KBW stepped back; TeraWulf got a backstop
Keefe, Bruyette & Woods analyst Stephen Glagola cut Riot to Market Perform, KBW's neutral rating, on November 11, noting Anthropic sits behind nearly all of the roughly $38 billion Riot has contracted 5. Rival developer TeraWulf+5.40% — TeraWulf, up 5.40 percent today, by contrast, announced credit backing from Alphabet, rated AA+, on November 4 for the debt behind its own $19 billion Anthropic campus in Hawesville, Kentucky 7.
The Street is split, and the tenant is now public
The bull case is wider than one activist. B. Riley raised its Riot price target to $37 on November 11, and Jefferies−0.33% — Jefferies, down 0.33 percent today upgraded the stock to Buy a day earlier at $28, against a Street consensus near $32 5. Management says it does not currently expect to issue equity for the announced projects 4 5.
What settles the argument is already named: a Corsicana financing cheap enough to leave the 12% clause dormant 4. The first block of the initial 400 megawatts is targeted for June 28, 2027, and the full 400 megawatts must arrive by September 2027, after which most of the rent begins 1 4 5. Anthropic's stock starts trading on the Nasdaq Thursday under ticker ANT 6.
Get Data Center by email, free
Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.