Texas cleared Hut 8 to build the second half of its 1-gigawatt AI campus, but Phase 2 has no bonds yet

The November 24 Notice of Intent clears the 500 MW half of the one-gigawatt campus, whose $9.8 billion lease still has no priced bonds. ERCOT and the PUC rule on Texas power for 6.5 GW of load on December 10, and the equity carries the gap.

Vincent JiangVincent Jiangtwo-minute read

Drafted with AI from the documents listed under Sources, then edited and fact-checked by Vincent Jiang. How we work

Share
Rows of Hut 8 mining containers on gravel under a cloudy sky at the company's Medicine Hat, Alberta site
Hut 8's BlockBox mining containers at Medicine Hat, Alberta, its original bitcoin mining site. The campus the story covers, Beacon Point, is a leased AI development in Nueces County, Texas.

Hut 8's+2.61% — Hut 8, up 2.61 percent today Texas expansion cleared a regulatory step 15. On November 24 the Texas Commission on Environmental Quality, the state's environmental regulator, issued a Notice of Intent authorizing construction of Beacon Point Phase 2, site preparation is under way, and Hut 8 expects to energize an initial 700 MW in the first quarter of 2027, with about 1,900 construction jobs and 230 permanent roles projected 15.

The $7.5 billion of project bonds covers only Phase 1

Beacon Point is a one-gigawatt AI campus in Nueces County, Texas, split into two 500 MW phases of 352 MW of IT load each, leased to an unnamed investment-grade tenant for a combined $19.6 billion 124. But the $7.5 billion of non-recourse project bonds that made this model fundable covers only River Bend ($3.25 billion) and Beacon Point Phase 1 ($4.25 billion) 2.

Each phase carries a $9.8B lease, but bonds sit behind only Phase 1

  • Lease value
  • Project bonds
$0B$5B$10BBeacon Point Phase 1Beacon Point Phase 2$9.8B$0B
Data
Lease valueProject bonds
Beacon Point Phase 1$9.8B$4.25B
Beacon Point Phase 2$9.8B$0B
Lease value against non-recourse project bond financing for Beacon Point's two 500 MW phases, US$ billions. Phase 2 had no financing arranged at the third-quarter 2026 print. Sources: Global Data Center Hub, Startup Fortune.2,4

Phase 2's financing was still being arranged at the third-quarter print, when Hut 8 reported negative $455.7 million of free cash flow and $156.9 million of unrestricted cash against $6.4 billion of restricted project funds 2. The lease book behind it, including River Bend's Google-backed Fluidstack lease, was laid out in our November 21 piece on the Louisiana side 2.

Hut 8 has burned cash every quarter for two years, and the burn is deepening

-$0.6B-$0.4B-$0.2B-$0B$0.2BQ3 '24Q1 '25Q3 '25Q1 '26Q3 '26Break-even-$0.45B
Data
Free cash flow
Q2 '24-$0.02B
Q3 '24-$0.11B
Q4 '24-$0.06B
Q1 '25-$0.1B
Q2 '25-$0.09B
Q3 '25-$0.04B
Q4 '25-$0.29B
Q1 '26-$0.08B
Q2 '26-$0.59B
Q3 '26-$0.45B
Hut 8 quarterly free cash flow, US$ billions, from its SEC filings: negative in all ten quarters, deepest at about minus $0.59 billion in Q2 2026 and about minus $0.45 billion in Q3 2026. Source: Hut 8 filings.6

The power ruling lands December 10

ERCOT, the Texas grid operator, and the Public Utility Commission of Texas are expected to rule on December 10 on Batch Zero designations covering more than 6.5 GW of Texas large load, Hut 8 among the applicants, and Needham sees a high risk some of those projects are never completed as approvals tighten into 2027 3. Governor-elect Gina Hinojosa has called for a moratorium on new approvals, though proposed pauses would spare permitted projects, and Phase 2 now holds its permit 4.

Lenders will read the lease term closely

The November 24 announcement still describes both Beacon Point leases as 15-year, while the third-quarter disclosure says the Phase 2 term was extended to 17 years 12. That matters because project bonds are underwritten against the lease's term: a 17-year rent stream supports a larger or longer repayment profile than a 15-year one, so the term on the bond documents will show whether lenders took the extension 12.

Phase 2's bonds are unpriced; watch the December 10 power ruling and the financing terms that follow, not the headline lease value 123. Our November 3 piece on the second $9.8 billion lease and the Keefe Bruyette downgrade covers the stock's history here 123.

Sources

  1. 1Data Center Bulletin, 'Hut 8 gets Texas approval to build Beacon Point phase two', 25 November 2026
  2. 2Global Data Center Hub, 'Hut 8 Signed 949 MW. Now It Must Deliver.', 26 November 2026
  3. 3Yahoo Finance / Blockspace, '6.5 GW of Texas data center load faces December 10 ERCOT Batch Zero decision: Needham', 23 November 2026
  4. 4Startup Fortune, 'Hut 8 and MARA shares plunge as bitcoin slips under $60,000 and AI stocks sell off', 26 November 2026
  5. 5RootData, 'Hut 8 announced that Beacon Point Phase II AI Park has been approved for construction, and on-site preparations have begun', 25 November 2026
  6. 6Hut 8, quarterly figures from its SEC filings, retrieved 26 November 2026

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading HUT

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    CleanSpark's $90 million Two Prime bitcoin loan implies a 92% loan-to-value, past its 80% liquidation trigger

    The $90 million Two Prime loan is collateralized by bitcoin that, near $59,000, implies a 92% loan-to-value, past the disclosed 80% liquidation trigger, while the 7.875% notes bill interest eight months before Meta-linked rent begins.

    Data Center

    Schneider Electric's cooling chief says data centers carry three to five layers of unneeded cooling margin

    Tuan Hoang says silicon allows coolant at 45°C but three to five stacked safety buffers push facilities colder, eroding free cooling. The same vendor just doubled European liquid-cooling capacity, so investors must judge how much of the AI cooling boom is heat and how much is specification.

    Data Center

    Foxconn sells $1.25 billion of convertible bonds as AI server growth burns $3.8 billion of cash

    A zero-coupon $1.25 billion bond priced the same session Hon Hai's stock hit Taipei's 10 percent limit, and it settles what the record quarter left open: 46 percent revenue growth on a 3.83 percent operating margin does not fund its own factories. The money at stake is shareholders', through dilution the convert embeds.

    Data Center

    Moody's lifts Coherent to Ba1 and sets a cash test its buyback can break

    The next notch needs free cash flow above 10 percent of debt and conservative shareholder distributions, and the board authorized $2 billion of buybacks six days before the upgrade. Secured bank lenders now hold investment-grade Baa3 paper; the holders of $990 million of 2029 notes sit two notches lower at Ba2.

    Data Center

    Amphenol doubled its credit line with JPMorgan to $5 billion as its valuation hit a five-year low

    Amphenol doubled its credit line to $5 billion and raised its commercial paper caps the same week its forward multiple touched a five-year low, funding a record AI-driven order book into an uncertain 2027.

    Data Center

    Applied Digital signed a $5.4 billion lease, then delivered 25 megawatts of it

    Two days after a lease took contracted revenue past $41 billion, Applied Digital handed over 25 MW of a 200 MW deal, with interest already outrunning rent and a 300 MW year-end goal one hall from failure.

    Subscribe to TheInference for free