AI's $750 billion buildout now waits on a Virginia county board

Loudoun County, home to more data centers than anywhere on earth, moved on 15 September to defer new applications for up to a year, and Bank of America now ranks local opposition as the buildout's rising risk. Order books from GE Vernova's $176 billion backlog to Eaton's 307-gigawatt pipeline still turn into revenue only as fast as county boards allow.

Vincent JiangVincent Jiangthree-minute read
Share
Aerial view of dozens of large data center buildings and a power substation in Ashburn, Virginia
1 / 7Slide 1 of 7
Data centers pack the landscape in Ashburn, in Loudoun County, Virginia, the densest data center market in the world.

The pause defers decisions, not applications

On 15 September 2026, with the hearing room standing room only, Loudoun County's Board of Supervisors voted 7-1-1 to draft a resolution deferring new data center and substation applications for up to 12 months, with the final vote set for the board's 20 October business meeting 12. Loudoun hosts more data centers than anywhere else in the world 3.

Virginia law bars a moratorium, so the county works inside the state's own review clock: applications are still accepted, decisions are deferred, and new data center rules are due by July 2027 1. By-right projects are untouched, and 18.2 million square feet of by-right data center space keeps moving through staff-level review 1.

No source prices what a frozen queue does to what is already through it. But the mechanics run one direction: that by-right space and every standing approval become the only capacity that can still move, and in the world's densest data center market, scarcity bids up the value of what incumbents already hold.

The money is committed; the sites are not

Four hyperscalers plan between $735 billion and $760 billion of 2026 capital spending, depending on where Alphabet−1.54% — Alphabet, down 1.54 percent today and Meta+2.23% — Meta, up 2.23 percent today land: Amazon−1.16% — Amazon, down 1.16 percent today at $220 billion, Microsoft−0.28% — Microsoft, down 0.28 percent today near $190 billion, Alphabet at $195–205 billion, Meta at $130–145 billion, up from roughly $410 billion in 2025 4.

$0B$100B$200B$300BAmazonAlphabetMicrosoftMeta$137.5B
Data
Planned 2026 capex
Amazon$220B
Alphabet$200B
Microsoft$190B
Meta$137.5B
Planned 2026 capex at guidance midpoints. The four plans sum to $735–760 billion, up from roughly $410 billion in 2025, depending on where Alphabet and Meta land.4

Backlogs convert at the speed of permits

Bank of America's industrials team, writing on 17 September after a data center conference, reiterated Buy ratings on Eaton, GE Vernova and Vertiv−5.48% — Vertiv, down 5.48 percent today and said local opposition has become "an increased risk factor over the last 6-9 months," with similar reviews in other Virginia counties and Georgia cities 3.

The order books behind those ratings are enormous and slow. GE Vernova's backlog hit a record $176 billion in the second quarter, and management says it is "mostly sold out" through 2030 5. Eaton's US data center backlog is near 307 gigawatts, but only about 20% converts to near-term work, and the majority delivers from 2028 6.

Vertiv's 17% single-day drop on 29 July came on a revenue miss the company called timing, even as it raised 2026 sales guidance to $13.8–14.2 billion 7. A backlog is a promise a county board has not yet countersigned.

Opposition now extracts water, noise and ratepayer concessions

The loudest opponents are local. IBEW Local 26 counts 1,018 members living in Loudoun, and the county Chamber of Commerce warned that "the rules here can freeze without warning" 1. The county's own stake is $1.1 billion of annual data center tax revenue, almost 40% of its general fund 8.

Developers are paying for goodwill they did not budget a year ago. The House voted 417-3 on 16 September to codify the White House Ratepayer Pledge, signed by Amazon, Google, Meta, Microsoft, OpenAI$1.18T — OpenAI, private, latest valuation $1.18T, Oracle−2.86% — Oracle, down 2.86 percent today, xAI$200B — xAI, private, latest valuation $200B and 300-plus organizations 8. Dominion's Virginia data shows the shift already running: residential share of transmission costs down 27% while data centers' share rose 148% 8.

A CoreWeave−8.55% — CoreWeave, down 8.55 percent today pitch, relayed in the BofA note: "We use less water than a swimming pool, we signed the Ratepayer Pledge so your electricity bill is not going up, and our fans are 40 decibels" 3.

Oct 20 and the Senate set the near-term pace

The watch list is short and dated: the final vote at the 20 October business meeting 12, the Senate's handling of the ratepayer bill 8, and nine pending Loudoun applications that hit their 12-month deadlines before 15 September 2027, where the board must act or the applicant must voluntarily defer 1.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading GOOGL

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Akamai's founder-CEO bought $2.6 million of its stock at $85.08, no trading plan

    F. Thomson Leighton paid $85.08 a share in cash on the open market, with no trading plan, a day after Akamai closed $2.5 billion of 1% convertible debt. Every other claim on the company's upside starts above $102; his entry marks where the man running the AI build-out values the equity.

    Data Center

    Legrand raises 2026 outlook again to 11-13% organic growth as data centers grow near 40%

    Legrand lifted its 2026 organic growth target to 11-13% after nine-month sales of €8.33 billion, and UBS turned buyer with a €170 target. Investors are now paid an 8% discount to Schneider Electric and ABB to hold a group whose growth sits in one product line.

    Data Center

    Cipher Digital fell 20% in a week on a Texas data-center moratorium aimed at campuses it has not leased

    A fifth of Cipher's value vanished in a week on a risk aimed at campuses it has not leased, while rent on the ones it has is now being booked. The exposure that reaches shareholders is funding the next build, behind $6.7 billion of debt and a spent-down bitcoin treasury.

    Data Center

    Fujikura banked ¥235 billion, mostly from AI fiber, then guided to ¥194 billion in the second half

    The AI data-center fiber supplier banked ¥235 billion of operating profit by September, raised its full-year revenue outlook and doubled the dividend, yet its own ¥429 billion guide plans a smaller, lower-margin second half. Investors deciding whether that is prudence or slowdown are the ones whose money moves.

    Data Center

    Accelevation's owners took $318.4 million in nine months and left $4.5 million of equity behind

    The AI data center builder's first public balance sheet shows $318.4 million taken out by its owners in nine months, $648.8 million of debt, $4.5 million of equity left behind, and 66% revenue growth that produced a 77% profit decline.

    Data Center

    Akamai paid $284 million to keep $2.5 billion of new debt at 1%

    The closing terms itemize the cost of Akamai's cheap money: $284.4 million for the hedge, warrants on 23.3 million shares struck up to 40% above the market, and a race between an Anthropic-backed build-out and a $1.15 billion maturity next September.

    Subscribe to TheInference for free