Generac's Amazon warrant is worth $112.5 million, more than its quarter's profit, and cuts Amazon revenue

The generator maker's 10-Q prices the warrant it gave Amazon at $112.5 million and books it against Amazon revenue as the generators ship, more than the quarter's entire profit. The same filing shows how far the $4.5 billion backlog sits from the accounting.

Vincent JiangVincent Jiang · 3 min read
Share
A Generac XT8000E portable generator mounted on a vehicle
1 / 7Slide 1 of 7
A Generac XT8000E generator. The company's data-center machines, not these portables, are what the Amazon deal and its warrant are priced against.

A sentence the deal paperwork never had

Generac's−9.90% — Generac, down 9.90 percent today 10-Q, the quarterly report filed on November 3, 2026, carries one line the deal's earlier paperwork did not 1. The warrant the backup-power maker granted a subsidiary of Amazon.com on September 16 was worth $112.5 million on its grant date, priced by the Black-Scholes option model at $66.40 a share, and Generac "will recognize the grant-date fair value of the Warrant as a reduction of revenue from Amazon+6.52% — Amazon, up 6.52 percent today as control of the related goods or services are transferred" 1.

That is more than the quarter's entire $109.2 million of net income 23. The September 8-K gave the share count and the strike; the October release gave the backlog 23. Neither priced the equity 23.

Two currencies in one order book

The warrant covers up to 1,693,745 shares, about 2.9% of the 58,988,982 shares outstanding on the filing's cover, at a strike of $200.9266, exercisable in cash or in shares at Amazon's election through September 16, 2033, with the share count protected by anti-dilution adjustments 12. Only 307,954 shares vested at signing; the rest vest in tranches as Amazon's payments for data-center generators accumulate toward $8 billion 2. Generac has booked $20.4 million of the value as an asset to offset future Amazon revenue; the remaining $92.0 million depends on Amazon actually spending 1.

Amazon's equity costs 1.4 cents of every dollar it must spend to vest it

The warrant's grant value is 1.4% of the $8 billion Amazon must pay to earn it

$0M$2,000M$4,000M$6,000M$8,000MPayments to vest it fully$8,000MInitial deliveries, 2027-28$2,400MWarrant value at grant$112.5M
Data
Value
Payments to vest it fully$8,000M
Initial deliveries, 2027-28$2,400M
Warrant value at grant$112.5M
Dollar values in millions from the September 16, 2026, transaction agreement and Generac's Q3 2026 10-Q; warrant value is grant-date fair value before anti-dilution adjustments.1,2

The backlog is a statement, not a schedule

The quarter itself was a record: net sales of $1.2948 billion, up 16%, with the Commercial & Industrial segment up 28% to $552.1 million on data-center demand 13. Chief executive Aaron Jagdfeld put the data-center backlog at about $4.5 billion, nearly triple July's $1.6 billion 346.

The word backlog appears nowhere in the 10-Q 12. Its closest filed measure, remaining performance obligations, the revenue Generac still expects from signed contracts, totals about $330 million, and the $2.4 billion of initial Amazon deliveries expected in 2027 and 2028 is not in that line 12. The filing does not explain the gap 12.

A record $1.30 billion quarter ends a flat two-year run

Sales slid through 2025, then set a record as data-center demand arrived

$0.8B$1B$1.2B$1.4BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26Amazon deliveries begin in 2027
Data
Net sales
Q4 '23$1.06B
Q1 '24$0.89B
Q2 '24$1B
Q3 '24$1.17B
Q4 '24$1.24B
Q1 '25$0.94B
Q2 '25$1.06B
Q3 '25$1.11B
Q4 '25$1.09B
Q1 '26$1.06B
Q2 '26$1.17B
Q3 '26$1.3B
A record $1.30 billion quarter ends a flat two-year run1,7

The incentive, and the seller

The bull case is cheap lock-in: the equity costs about 1.4% of the $8 billion Amazon must spend to vest it, and Jagdfeld says it creates "a material incentive for Amazon to continue leveraging Generac as a supplier"; a second, unnamed hyperscaler could match the $700 million he expects from it in 2027 4.

Jagdfeld sold 5,000 shares on November 2 at $200.61, 32 cents under the strike, his fourth such monthly sale since August under a pre-scheduled trading plan adopted December 4, 2025, months before the deal existed 56. The readings that decide it start in 2027, when deliveries begin and Amazon's payments start flowing back off Generac's own revenue line 56.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AMZN

Reader comments

0 comments

    Power

    Morgan Stanley: data centers outbuy utilities on batteries in 2030; Tesla's energy backlog is $10.7 billion

    Morgan Stanley now expects data centers to buy more batteries in 2030 than utilities do, against a power shortfall above 80 gigawatts by 2029. Tesla is the obvious seller, and its storage line is the one part of the AI story already earning the money.

    Power

    AEP built the machine for its AI load before the load exists, and Jacobs gets paid either way

    In one week AEP hired the builders for its $37 billion transmission program and created a unit to sign contracts with the very customers driving the load. The 84 gigawatts are agreements, not meters, and the equity is already raised.

    Power

    Brookfield's $95/MWh hydro deals put a price on AI power hunger

    Two 10-year hydro PPAs at about $95/MWh are the clearest price yet on AI-era power demand, even as Brookfield sells pieces of that same fleet to fund batteries and new build.

    Power

    Meta Buys Williams Power; Blackstone's $5.34 Billion Builds It

    Barron's named Meta on November 3 as the buyer of 400 megawatts of behind-the-meter gas power from Williams. The plants are financed with $5.34 billion of Blackstone-led capital because Williams' leverage, at 3.80 times, already sits under a four-times ceiling that now governs executive pay.

    Power

    First Solar's 16% election rally ignored a December 4 import floor that moves production to Gaffney

    The election rally priced a Congress that cannot touch either federal lever behind First Solar's results before the Section 232 import floor lands on December 4. The floor relocates production to Gaffney, South Carolina, and the credit, not Congress, holds the margin.

    Power

    xAI bought jet engines for Colossus 2, but its legal power is cut in half by July 2027

    xAI's Colossus 2 cluster is racing toward 1.2 million GPUs on power it is legally scheduled to lose: a July 30, 2026, order cuts its turbines from 2.7GW to 1.24GW by July 2027, and SemiAnalysis sees a gap of upwards of 300MW.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.