Generac's Amazon warrant is worth $112.5 million, more than its quarter's profit, and cuts Amazon revenue

The generator maker's 10-Q prices the warrant it gave Amazon at $112.5 million and books it against Amazon revenue as the generators ship, more than the quarter's entire profit. The same filing shows how far the $4.5 billion backlog sits from the accounting.

Vincent JiangVincent Jiangthree-minute read
Share
A Generac XT8000E portable generator mounted on a vehicle
1 / 7Slide 1 of 7
A Generac XT8000E generator. The company's data-center machines, not these portables, are what the Amazon deal and its warrant are priced against.

A sentence the deal paperwork never had

Generac's−3.06% — Generac, down 3.06 percent today 10-Q, the quarterly report filed on November 3, 2026, carries one line the deal's earlier paperwork did not 1. The warrant the backup-power maker granted a subsidiary of Amazon.com on September 16 was worth $112.5 million on its grant date, priced by the Black-Scholes option model at $66.40 a share, and Generac "will recognize the grant-date fair value of the Warrant as a reduction of revenue from Amazon−1.14% — Amazon, down 1.14 percent today as control of the related goods or services are transferred" 1.

That is more than the quarter's entire $109.2 million of net income 23. The September 8-K gave the share count and the strike; the October release gave the backlog 23. Neither priced the equity 23.

Two currencies in one order book

The warrant covers up to 1,693,745 shares, about 2.9% of the 58,988,982 shares outstanding on the filing's cover, at a strike of $200.9266, exercisable in cash or in shares at Amazon's election through September 16, 2033, with the share count protected by anti-dilution adjustments 12. Only 307,954 shares vested at signing; the rest vest in tranches as Amazon's payments for data-center generators accumulate toward $8 billion 2. Generac has booked $20.4 million of the value as an asset to offset future Amazon revenue; the remaining $92.0 million depends on Amazon actually spending 1.

Amazon's equity costs 1.4 cents of every dollar it must spend to vest it

The warrant's grant value is 1.4% of the $8 billion Amazon must pay to earn it

$0M$2,000M$4,000M$6,000M$8,000MPayments to vest it fully$8,000MInitial deliveries, 2027-28$2,400MWarrant value at grant$112.5M
Data
Value
Payments to vest it fully$8,000M
Initial deliveries, 2027-28$2,400M
Warrant value at grant$112.5M
Dollar values in millions from the September 16, 2026, transaction agreement and Generac's Q3 2026 10-Q; warrant value is grant-date fair value before anti-dilution adjustments.1,2

The backlog is a statement, not a schedule

The quarter itself was a record: net sales of $1.2948 billion, up 16%, with the Commercial & Industrial segment up 28% to $552.1 million on data-center demand 13. Chief executive Aaron Jagdfeld put the data-center backlog at about $4.5 billion, nearly triple July's $1.6 billion 346.

The word backlog appears nowhere in the 10-Q 12. Its closest filed measure, remaining performance obligations, the revenue Generac still expects from signed contracts, totals about $330 million, and the $2.4 billion of initial Amazon deliveries expected in 2027 and 2028 is not in that line 12. The filing does not explain the gap 12.

A record $1.30 billion quarter ends a flat two-year run

Sales slid through 2025, then set a record as data-center demand arrived

$0.8B$1B$1.2B$1.4BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26Amazon deliveries begin in 2027
Data
Net sales
Q4 '23$1.06B
Q1 '24$0.89B
Q2 '24$1B
Q3 '24$1.17B
Q4 '24$1.24B
Q1 '25$0.94B
Q2 '25$1.06B
Q3 '25$1.11B
Q4 '25$1.09B
Q1 '26$1.06B
Q2 '26$1.17B
Q3 '26$1.3B
A record $1.30 billion quarter ends a flat two-year run1,7

The incentive, and the seller

The bull case is cheap lock-in: the equity costs about 1.4% of the $8 billion Amazon must spend to vest it, and Jagdfeld says it creates "a material incentive for Amazon to continue leveraging Generac as a supplier"; a second, unnamed hyperscaler could match the $700 million he expects from it in 2027 4.

Jagdfeld sold 5,000 shares on November 2 at $200.61, 32 cents under the strike, his fourth such monthly sale since August under a pre-scheduled trading plan adopted December 4, 2025, months before the deal existed 56. The readings that decide it start in 2027, when deliveries begin and Amazon's payments start flowing back off Generac's own revenue line 56.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AMZN

Reader comments

0 comments

    Power

    Evergy Sees $4 Billion of Generation Behind a Deal Digital Realty Has Not Signed

    A 1.4-gigawatt letter of intent at a former Kansas ammunition plant is the durable news in a weather-inflated quarter. The funding decisions that come first are a Missouri rate order in December and a new capital plan in February; the contract is not expected until the first half of 2027.

    Power

    China's turbine export push aims at GE Vernova's 122-gigawatt queue as Dongfang books 30 in Canada

    Beijing wants an independently controlled gas-turbine supply chain by 2030, and Dongfang Electric booked 30 turbines for Canadian data centers in late October. The five-year queue GE Vernova monetizes, 122 reserved gigawatts inside a $197 billion backlog, sits on the other side of that plan.

    Power

    Michigan AG asks regulators to reopen DTE Energy's 1-gigawatt Google deal, with $44.2 billion riding on it

    Dana Nessel's November 2 petition attacks the protections behind Michigan's October approval of DTE's Google contracts; the utility's $44.2 billion capital plan and roughly $1 billion a year of new equity ride on that gigawatt.

    Power

    Virginia Democrats ask regulators to reject NextEra's $67 billion Dominion takeover

    The comment window closed with commission staff, the governor and five House Democrats against the deal, and Dominion's own 10-K shows the data-center risk priced thinner than the marketing: 28% of sales, a conditional 2027 contract regime, and $463 million of new rider recovery on the table.

    Power

    Siemens orders jump 58% to a record €34.8 billion as AI data centers wait five years for power gear

    Data-center orders doubled in Siemens's record quarter, and the backlog behind it rests on customers waiting more than five years for power equipment. Beijing has told its turbine makers to use that shortage to break Western dominance by 2030, which is what investors in Siemens, GE Vernova and Mitsubishi Heavy now have to price.

    Power

    Centrus begins commercial HALEU sales as revenue falls 26% and contingent fuel orders reach $5.4 billion

    The output runs on rights the Department of Energy granted and can revisit, even as DOE's own purchases shrink. Centrus enters its December 7 investor day with about $2.2 billion of cash, a widening gross loss, and a $5.4 billion order book that is mostly contingent and mostly conventional reactor fuel.

    Subscribe to TheInference for free