Meta Buys Williams Power; Blackstone's $5.34 Billion Builds It

Barron's named Meta on November 3 as the buyer of 400 megawatts of behind-the-meter gas power from Williams. The plants are financed with $5.34 billion of Blackstone-led capital because Williams' leverage, at 3.80 times, already sits under a four-times ceiling that now governs executive pay.

Vincent JiangVincent Jiang · 3 min read
Share
Chad Zamarin, chief executive of Williams Companies
1 / 5Slide 1 of 5
Williams chief executive Chad Zamarin credits the Socrates power project, now serving Meta, for his confidence in the full-year outlook.

Meta is the name on the 400 megawatts

Williams−6.63% — Williams, down 6.63 percent today, the Oklahoma-based natural gas pipeline operator that delivers about a third of the country's gas 1, has a named customer for its power business. Barron's reported on November 3 that Meta+1.50% — Meta, up 1.50 percent today holds a $1.6 billion deal with Williams for two behind-the-meter gas plants, generation built at the customer's own site, totaling 400 megawatts, and that chief executive Chad Zamarin credited the project, which Williams calls Socrates, for his confidence in the full-year outlook 25.

The quarter backs him: adjusted EBITDA, Williams' core profit measure, of $2.039 billion, up 6 percent, tracking the upper half of the $8.3 billion to $8.5 billion range, with Socrates fully online ahead of schedule and a second plant, Plato North, due by mid-November 1. One or two more power projects will be announced before year end, management told analysts 3.

This follows The Inference's November 3 account of the $1.9 billion Williams share block and its October 13 piece on Meta's AI finances. New this week are the customer's name, the partner-payment schedule in the 10-Q, and executive pay tied to the leverage ceiling.

The construction money is private equity's

Outside capital funds about half the build. In July, Williams sold a 49 percent noncontrolling stake in Pantheon, the venture holding its five power projects, for $5.34 billion of committed capital from funds managed by Blackstone+6.18% — Blackstone, up 6.18 percent today Credit & Insurance, with Apollo and KKR alongside 45. Of that, $4.4 billion covers 49 percent of expected growth capex and about $0.9 billion is extra consideration paid to Williams 4. The cash lands in stages: $3.74 billion in July, $1 billion in October, the rest through the first quarter of 2027, all dedicated to construction 4.

The structure exists because the balance sheet has little room. Leverage was 3.80 times adjusted EBITDA at September 30 1, and the new pay framework ties a 10 to 16 percent EBITDA growth target through 2030 to staying at or below four times 3.

Williams' own deal announcement says the partnership lets it keep growing "without stretching corporate leverage," inside a 3.5 to 4.0 times target 5. The 10-Q also carries a $1.6 billion working capital deficit and $2.2 billion of debt due within a year 4. Capex has outrun operating cash flow in three of the past four quarters, and the third-quarter gap was just over $1 billion 6.

Capex has outrun operating cash flow in three of the past four quarters

Third-quarter capex ran $1.0 billion ahead of operating cash flow

  • Capital expenditure
  • Operating cash flow
$0.5B$1B$1.5B$2B$2.5B$3BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$1B more partner cash landed inOctober
Data
Capital expenditureOperating cash flow
Q4 '23$0.69B$1.81B
Q1 '24$0.54B$1.23B
Q2 '24$0.61B$1.28B
Q3 '24$0.73B$1.24B
Q4 '24$0.8B$1.22B
Q1 '25$1.01B$1.43B
Q2 '25$1.01B$1.45B
Q3 '25$0.99B$1.44B
Q4 '25$1.98B$1.58B
Q1 '26$0.99B$1.6B
Q2 '26$1.86B$1.38B
Q3 '26$2.51B$1.51B
Quarterly capital expenditure versus cash flow from operations, US$ billions, as reported. Source: Williams SEC filings.6

Shareholders are paying 2028 prices

The bill arrives before the earnings. The stock trades at 28.4 times trailing earnings against a five-year median of 24.7 7, about 26 times enterprise value to this year's guidance midpoint on AInvest's arithmetic 8, on a free cash flow yield of minus 0.2 percent 7. Insiders sold $11.1 million of stock over twelve months and bought none; the general counsel sold 2,000 shares at $74.17 on November 2 under a selling plan dated September 2025 79.

The bull case is real: dividend coverage of 2.42 times 1, a promote structure that improves Williams' economics as the plants perform, and a buyback right on the partner stake between years seven and fourteen 5. None of that brings the 2028 earnings forward 83. The EBITDA that would justify the multiple is scheduled to inflect in 2028 and beyond 8, while $5.9 billion of long-lead power equipment is already committed 3.

The tells are the leverage ratio printed when the next projects are sanctioned, and whether the new contracts are firm and of Socrates's length, an initial ten years 4. Until then, Williams sells the power to Meta and the construction risk to Blackstone.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading BX

Reader comments

0 comments

    Power

    Morgan Stanley: data centers outbuy utilities on batteries in 2030; Tesla's energy backlog is $10.7 billion

    Morgan Stanley now expects data centers to buy more batteries in 2030 than utilities do, against a power shortfall above 80 gigawatts by 2029. Tesla is the obvious seller, and its storage line is the one part of the AI story already earning the money.

    Power

    AEP built the machine for its AI load before the load exists, and Jacobs gets paid either way

    In one week AEP hired the builders for its $37 billion transmission program and created a unit to sign contracts with the very customers driving the load. The 84 gigawatts are agreements, not meters, and the equity is already raised.

    Power

    Brookfield's $95/MWh hydro deals put a price on AI power hunger

    Two 10-year hydro PPAs at about $95/MWh are the clearest price yet on AI-era power demand, even as Brookfield sells pieces of that same fleet to fund batteries and new build.

    Power

    Generac's Amazon warrant is worth $112.5 million, more than its quarter's profit, and cuts Amazon revenue

    The generator maker's 10-Q prices the warrant it gave Amazon at $112.5 million and books it against Amazon revenue as the generators ship, more than the quarter's entire profit. The same filing shows how far the $4.5 billion backlog sits from the accounting.

    Power

    First Solar's 16% election rally ignored a December 4 import floor that moves production to Gaffney

    The election rally priced a Congress that cannot touch either federal lever behind First Solar's results before the Section 232 import floor lands on December 4. The floor relocates production to Gaffney, South Carolina, and the credit, not Congress, holds the margin.

    Power

    xAI bought jet engines for Colossus 2, but its legal power is cut in half by July 2027

    xAI's Colossus 2 cluster is racing toward 1.2 million GPUs on power it is legally scheduled to lose: a July 30, 2026, order cuts its turbines from 2.7GW to 1.24GW by July 2027, and SemiAnalysis sees a gap of upwards of 300MW.