Power

AEP built the machine for its AI load before the load exists, and Jacobs gets paid either way

In one week AEP hired the builders for its $37 billion transmission program and created a unit to sign contracts with the very customers driving the load. The 84 gigawatts are agreements, not meters, and the equity is already raised.

Richard TangRichard Tangthree-minute read
Share
Line crews string new conductor from a bucket truck, with reel trailers and line trucks parked behind them
1 / 6Slide 1 of 6
Line crews string new conductor from a bucket truck: AEP has now contracted Jacobs and WSP to manage delivery of its $37 billion transmission program, whatever the 84 gigawatts of signed load turn out to do.

American Electric Power−0.79% — American Electric Power, down 0.79 percent today just spent a week building the machine to deliver its AI promises, before a single new gigawatt of that demand is energized. In three moves: a $37 billion transmission delivery contract on October 29, a new contract-based business unit on November 3, and a $100 billion capital plan underneath both. The wires get built either way. The question that decides whose money moves is whether the signed gigawatts show up as billed load on schedule.

Start with the demand claim. AEP signed 15 gigawatts of new customer load commitments in the third quarter, bringing projected incremental contracted demand to 84 gigawatts by 2031, 92% of it data centers and high-density computing including crypto operations 3. But the book counts executed service agreements and letters of agreement, not meters, and AEP discloses no split by state or energization year 4. A signed future load is still waiting for a meter.

This week AEP contracted the builders, not just the wires

Here is what changed this week, and it is real: AEP removed the delivery bottleneck. Jacobs−1.06% — Jacobs, down 1.06 percent today and WSP USA now hold five-year program management roles on the transmission slice, Jacobs leading the seven-state eastern territory and WSP the four-state west, contract values undisclosed 23.

That includes three 765 kV lines to serve SB Energy's planned 10.4-gigawatt campus in Piketon, Ohio, construction starting in the first quarter of 2027 and in service from late 2028 through 2030; the first 800 megawatts ride existing lines 3. Then came AEP Infrastructure under Greg Hall, pulling competitive generation, AEP Energy's data-center work and customer-owned grid projects into one unit, naming a 20-year fuel-cell facility for Google in Wyoming and a proposed Longview Power Plant acquisition 1.

Transmission is the largest named bucket in AEP's $100B five-year plan

The wires get nearly as much capital as the power plants

$0B$10B$20B$30B$40BTransmission$37BGeneration$36BDistribution$22BUnallocated$5B
Data
Value
Transmission$37B
Generation$36B
Distribution$22B
Unallocated$5B
AEP's 2027-2031 capital plan in billions of dollars, as broken out in its Q3 2026 disclosures; the release does not break out the remaining $5 billion.3,4

AEP's capex jumped 48% in 2025, and the new plan implies $20 billion a year

$0B$5B$10B$15B20172019202120232025$11.91B
Data
Capex
2016$4.78B
2017$3.53B
2018$6.31B
2019$6.05B
2020$6.25B
2021$6.43B
2022$7.88B
2023$7.53B
2024$8.03B
2025$11.91B
American Electric Power capital spending by fiscal year, in billions of dollars, from its SEC filings, retrieved 4 November 2026. The 2027-2031 plan averages $20 billion a year, far above the current run rate.5

Who carries the risk, and what to track

So the chain runs: AI load → signed agreements → wires and generation actually built → billed megawatt-hours. AEP has now contracted the third link before the second is proven. Jacobs and WSP hold a five-year revenue annuity regardless of whether the load converts; they get paid to build. AEP shareholders carry the conversion risk, funded with new equity, against a rate base projected to reach $162 billion by 2031 and a residential-protection promise lifted to $21 billion from take-or-pay contracts, up from $16 billion in July 4.

Track two things. Whether the 84-gigawatt book converts to billed load on the Piketon schedule. And whether Hall's contract-based returns beat regulated rate-base returns, which is the test of whether this unit is a growth engine or a way to move risk off the regulated books. Investors get paid on the first; the second tells you what kind of company AEP is becoming.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AEP

Reader comments

0 comments

    Power

    Evergy Sees $4 Billion of Generation Behind a Deal Digital Realty Has Not Signed

    A 1.4-gigawatt letter of intent at a former Kansas ammunition plant is the durable news in a weather-inflated quarter. The funding decisions that come first are a Missouri rate order in December and a new capital plan in February; the contract is not expected until the first half of 2027.

    Power

    China's turbine export push aims at GE Vernova's 122-gigawatt queue as Dongfang books 30 in Canada

    Beijing wants an independently controlled gas-turbine supply chain by 2030, and Dongfang Electric booked 30 turbines for Canadian data centers in late October. The five-year queue GE Vernova monetizes, 122 reserved gigawatts inside a $197 billion backlog, sits on the other side of that plan.

    Power

    Michigan AG asks regulators to reopen DTE Energy's 1-gigawatt Google deal, with $44.2 billion riding on it

    Dana Nessel's November 2 petition attacks the protections behind Michigan's October approval of DTE's Google contracts; the utility's $44.2 billion capital plan and roughly $1 billion a year of new equity ride on that gigawatt.

    Power

    Virginia Democrats ask regulators to reject NextEra's $67 billion Dominion takeover

    The comment window closed with commission staff, the governor and five House Democrats against the deal, and Dominion's own 10-K shows the data-center risk priced thinner than the marketing: 28% of sales, a conditional 2027 contract regime, and $463 million of new rider recovery on the table.

    Power

    Siemens orders jump 58% to a record €34.8 billion as AI data centers wait five years for power gear

    Data-center orders doubled in Siemens's record quarter, and the backlog behind it rests on customers waiting more than five years for power equipment. Beijing has told its turbine makers to use that shortage to break Western dominance by 2030, which is what investors in Siemens, GE Vernova and Mitsubishi Heavy now have to price.

    Power

    Centrus begins commercial HALEU sales as revenue falls 26% and contingent fuel orders reach $5.4 billion

    The output runs on rights the Department of Energy granted and can revisit, even as DOE's own purchases shrink. Centrus enters its December 7 investor day with about $2.2 billion of cash, a widening gross loss, and a $5.4 billion order book that is mostly contingent and mostly conventional reactor fuel.

    Subscribe to TheInference for free