Power

CenterPoint's grid plan hits $70.7 billion; its $5 billion Houston savings promise has no published math

CenterPoint raised its grid plan to $70.7 billion and promised $5 billion back to Houston ratepayers. Only the first number is money in motion; the second waits on a tariff clause Texas has not finished writing.

Vincent JiangVincent Jiangthree-minute read
Share
Jason P. Wells, chair, president and chief executive officer of CenterPoint Energy
CenterPoint Energy chief executive Jason Wells called data-center demand "unprecedented" as the company lifted its capital plan to $70.7 billion on October 27, 2026.

Two promises, one grid

CenterPoint Energy+0.60% — CenterPoint Energy, up 0.60 percent today, Houston's regulated electric utility (NYSE: CNP), put two big numbers in front of investors this quarter. On October 27 it raised its ten-year capital plan by $4.0 billion, from $66.7 billion to $70.7 billion, and pulled $1.5 billion of that into 2026-2030, chasing what chief executive Jason Wells calls "unprecedented" data-center demand 12.

The other number came first: on its July 28 call, management said 14 gigawatts of new Texas load would save its 2.9 million Houston customers more than $5 billion over a decade, roughly $500 million a year 13. The capital is committed. The saving has no published math behind it: no year-by-year table, no per-customer estimate 1.

The build is funded; the saving is not

The raise came with 2026 earnings guidance lifted to $1.90 to $1.92 a share, 2027 initiated at $2.07 to $2.09, about 9% growth, and that pace extended through 2030 2. Chief financial officer Chris Foster told investors "nearly all" of the new spending could be recovered by passing costs to ratepayers, pending approval from the Public Utility Commission of Texas 4.

A regulated utility earns on the wires either way. GridPermit counts roughly ten CenterPoint rate requests since 2025 seeking more than $8 billion, mostly for storm hardening, and the city of Houston has denied one and delayed another 1. The plan spans several states, and the Texas share is unstated 5.

Quarterly capex runs about 40% above its early-2024 pace as the $70.7 billion plan begins

$0.5B$1B$1.5B$2B$2.5BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$1.18BLatest reported quarter
Data
Capital expenditures
Q4 '23$1.08B
Q1 '24$0.85B
Q2 '24$0.81B
Q3 '24$0.84B
Q4 '24$2.01B
Q1 '25$1.04B
Q2 '25$1.13B
Q3 '25$1.22B
Q4 '25$1.48B
Q1 '26$1.2B
Q2 '26$1.37B
Q3 '26$1.18B
Capital expenditures by calendar quarter, in billions of US dollars, from CenterPoint's SEC filings. The company lifted its ten-year capital plan to $70.7 billion on October 27, 2026. Source: CenterPoint Energy quarterly SEC filings, retrieved November 9, 2026.10

The queue softens as it grows

The pipeline runs from hard to soft: 3.5 gigawatts under construction, 8 expected energized by 2029, 14 assumed by 2030, and 17 submitted into Batch Zero, the Texas grid operator ERCOT's first grouped study of loads above 75 megawatts 13. About 10 gigawatts have cleared both required studies, backed by signed facilities extension agreements and roughly $900 million of customer cash and security already posted 3.

Houston's data-center pipeline thins from steel to paperwork

Only 3.5 GW of the load behind the $5 billion pledge is under construction

  • Estimate
0 GW5 GW10 GW15 GW20 GWUnder construction now3.5 GWBy 2029 (company forecast)8 GWBy 2030 (company forecast)14 GWThe $5B savings pledge assumes this arrivesSubmitted to Batch Zero17 GWApplications in a paused process, not contracts
Data
Value
Under construction now3.5 GW
By 2029 (company forecast) (estimate)8 GW
By 2030 (company forecast) (estimate)14 GW
Submitted to Batch Zero17 GW
Gigawatts of large-load demand on CenterPoint's Houston electric system. The 2029 and 2030 bars are company forecasts from the July 28, 2026, call; the Batch Zero bar is submitted applications. Sources: GridPermit, November 6, 2026; MarketBeat via Yahoo Finance, July 28, 2026.1,3

Then the ground moved. Governor Greg Abbott halted new data-center connections on August 3 pending an audit due in mid-December 46, Batch Zero sits "essentially in a holding pattern" 7, and on November 3 Texas elected Gina Hinojosa, who wants no new approvals until the legislature writes protections 6. Statewide, ERCOT was weighing more than 474 gigawatts of large-load requests, about 90% from data centers 8.

The clause that decides it

The savings mechanism is ordinary arithmetic: fixed grid costs divided by more payers 14. The enforcement is unfinished. On September 18 the PUCT adopted rule 25.194, which takes $50,000 of security per megawatt and refunds it in 20% tranches only as each customer meets its minimum billing demand under rule 25.193 9.

CenterPoint expects about $6 million per gigawatt per month in demand-charge cash once the meters run 3. Hold the minimum bills and Houston gets its $5 billion 3. Soften them and the cost lands where it always has. CenterPoint's 9% growth guide is a bet on a tariff clause, not on data centers 3.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading CNP

Reader comments

0 comments

    Power

    PSEG raises its five-year regulated investment plan to $22.5-25.5 billion

    The November 6 8-K grows the regulated build and pledges 6%-8% earnings growth through 2030 with no new equity, yet the large-load contracts behind the demand story are still unsigned, PJM's utilities just cut 6.5 GW from their forecasts, and the bill for the wait lands on New Jersey ratepayers through 2028.

    Power

    Constellation Energy CEO calls data-center demand forecasts massively overstated; GE Vernova stock fell 7.4%

    Two power CEOs told the market within three days that the grid-queue numbers behind the AI buildout were padded by speculation. The repricing lands on developers and equipment makers; the incumbents with power already sold are watching their contracts, not the queues.

    Power

    SpaceX asks its company town for a tax break on a $24 billion gas plant and data center

    Starbase's three-member commission, two of whom work for SpaceX, votes December 9 on the property tax abatement for the plant that would power the company's fast-growing compute business. The notice never prices the giveaway, and the governor-elect who campaigned against data centers takes office in January.

    Power

    Duke Energy wins 29 lenders' consent to merge its Carolinas utilities

    An amendment to Duke's $10 billion credit line, signed November 9, clears Duke Energy Progress to vanish into Duke Energy Carolinas on January 1, 2027. One borrower will now front the rate cases that decide who pays for Duke's $103 billion data-center build.

    Power

    PPL's Blackstone venture signs first 2GW data-center power deal

    The first proof PPL can turn a 35GW request queue into contracts. The case for the stock now rests on that funnel converting, and on large-load tariffs holding as voters turn on data centers.

    Power

    Crusoe ordered 13 ProEnergy generator sets on GE's own jet engine core, skipping GE Vernova's six-year queue

    GE Vernova's queue makes its pricing power, but the used and converted machines that skip it, some built on GE's own CF6 core, set a ceiling on that power. The bet is whether the queue holds to 2032.

    Get the newsletter