Delta Electronics set a record NT$197.1 billion quarter; Vicor's ITC case targets the same AI server modules

Delta Electronics printed a second straight record quarter on AI server power, yet profit grew slower than sales, four banks cut its Thai unit's targets and the shares fell 9.8%. On the same modules, Vicor's royalty take is built to rise as its US trade case advances: the question for AI-power investors is no longer demand, it is who keeps the margin.

Richard TangRichard Tang · 4 min read
Share
Patrizio Vinciarelli, Vicor's founder and chief executive, whose patent-licensing case against Delta Electronics and other AI-power suppliers is before the US International Trade Commission
1 / 6Slide 1 of 6
Patrizio Vinciarelli, Vicor's founder and chief executive. His company's Section 337 case over vertical power delivery modules names Delta Electronics among the respondents.

Delta Electronics−9.80% — Delta Electronics, down 9.80 percent today, the Taiwanese power-and-thermal supplier inside AI servers and data centers, posted a second straight record quarter this week: NT$197.1 billion of revenue, up 31% year over year 1. Profit rose more slowly than sales, and gross margin slipped to 34.1% 12. Four banks cut their targets on the company's Thai listing the same week, and the Taipei shares closed down 9.8% 34. The buildout is still handing Delta volume; the week's verdict was about Delta's margin.

Demand is delivering volume, and it is concentrating

Delta builds the server power shelves and liquid cooling that AI racks run on, and it is working with Nvidia−4.86% — Nvidia, down 4.86 percent today on the 800-volt DC architecture those processors will draw from 3. When cloud operators build data centers, the power has to flow through this equipment, and the quarterly mix now shows it: the power-and-components division grew 40% year over year and now carries most of Delta's sales, with infrastructure, the data-center systems business, up 25% 1. Record revenue is exactly what an AI buildout should print for its power supplier.

Power and components now carry Delta's growth

  • Power & components105.953.7%
  • Infrastructure65.933.4%
  • Automation15.98.1%
  • Other9.44.8%
Data
SliceValueShare
Power & components105.953.7%
Infrastructure65.933.4%
Automation15.98.1%
Other9.44.8%
Delta Electronics Q3 2026 revenue by division, NT$ billions; 'Other' is the remainder of the NT$197.1 billion total. Source: TokenPost [1].1

The supplier is absorbing the cost of getting racks built

The squeeze shows in the Thai listing, Delta Electronics Thailand, which consolidates much of the group's manufacturing. Operating margin fell to 10.4% from 14.1% a year earlier as selling costs jumped 69% 4. The same quarter absorbed a THB 1.9 billion inventory provision, up from THB 0.8 billion in the second quarter 5, plus freight, US customs duties and a THB 1.4 billion charge under the OECD's Pillar Two global minimum tax 4. Thai net profit of THB 7.76 billion missed the Bloomberg consensus of THB 8.73 billion 4.

Four banks cut their Delta Thailand targets after the results

  • Before the results
  • After the results
0100200300400Macquarie290370-22%JPMorgan320360-11%Citi315367-14%UBS300320-6.3%
Data
Before the resultsAfter the resultsChange
Macquarie370290-21.6%
JPMorgan360320-11.1%
Citi367315-14.2%
UBS320300-6.3%
Analyst target prices for Delta Electronics (Thailand) before and after 3Q26 results, THB per share. Source: Kaohoon International [4].4

Macquarie, UBS, JPMorgan and Citi−3.43% — Citi, down 3.43 percent today cut their targets 4, and Bualuang cut its 2026 core-profit forecast by 18% 5. The bull's best rebuttal is already in the record: through nine months, revenue grew 37% and net profit 62%, so profit is still outgrowing sales on the year 2.

The third quarter is the inflection to watch, not an established trend; the gap came from a lower gross margin and declining nonoperating income 12. Bualuang still expects fourth-quarter profit to recover as supply constraints ease and backlog ships 5. That recovery call, not the demand line, is the test.

The licensor's rates rise as the case advances

Vicor's−9.10% — Vicor, down 9.10 percent today royalty quarter is not the news: the $66.6 million figure and the interest from two hyperscalers, the largest cloud operators, were already on the record last week 67. What moved since is the machinery around that line. On October 9 the US International Trade Commission, the US trade agency that can bar imports of infringing products, instituted Vicor's second Section 337 investigation, this one over vertical power delivery, the converter stage that steps voltage down right beside the AI processor 8.

The named respondents include Delta Electronics, Infineon, Luxshare, Monolithic Power Systems−0.17% — Monolithic Power Systems, down 0.17 percent today, Flex−8.21% — Flex, down 8.21 percent today, Celestica−7.69% — Celestica, down 7.69 percent today, Quanta and Foxconn−1.01% — Foxconn, down 1.01 percent today 9, and Vicor has asked for a limited exclusion order that would keep infringing modules out of the United States 9. Vicor's release also states that any equipment maker or cloud operator whose systems use VPD parts from the respondents will need a license to import them 9.

Management now treats royalties as recurring: at least $43 million in Q4 7, with stage-3 license rates rising roughly 5% a month once an ITC investigation is under way 79. Vicor's consolidated gross margin stands at 68.3% 7. Its take rises with enforcement while Delta's margin absorbs the costs of getting racks built.

Vicor's gross margin has climbed 18 points as licensing took hold

40%50%60%70%Q3 '24Q1 '25Q3 '25Q1 '26Q3 '2668.3%
Data
Gross margin
Q2 '2449.8%
Q3 '2449.1%
Q4 '2452.4%
Q1 '2547.2%
Q2 '2565.3%
Q3 '2557.5%
Q4 '2555.4%
Q1 '2655.2%
Q2 '2658%
Q3 '2668.3%
Vicor consolidated gross margin by quarter, percent of revenue, Q2 2024 to Q3 2026, as reported in its SEC filings. The Q3 2026 figure of 68.3% includes $66.6 million of royalty revenue. Source: Vicor quarterly figures from its SEC filings, retrieved 30 October 2026 [10].10

Where the margin settles

In one quarter Delta's Thai unit absorbed an inventory provision, freight, customs duties and a global minimum tax 45; Vicor's license rates are built to climb as its US case advances 79. The buildout is real, and the builders who turn power engineering into deployed racks deserve the reward for it. But the quarter showed where the bargaining power sits: the supplier's costs are episodic, while a settled royalty rate, or an exclusion order, would move a slice of every AI rack's margin permanently.

Holders of Delta, and by read-across Monolithic Power Systems, a respondent in the same case 9, and Vertiv−6.58% — Vertiv, down 6.58 percent today, should track which side captures the next point of margin. If Bualuang's fourth-quarter recovery lands, Delta buys time; if Vicor's stage-3 escalation runs first, the take compounds 9.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading 2308.TW

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Furukawa Bets 100 Billion Yen on Fiber While Corning's Customers Lock Supply Through 2032

    TrendForce counts a 180 million fiber-kilometer global shortfall for 2026 and data-center fiber prices above five times their 2025 levels. Furukawa Electric's 100 billion yen four-country expansion answers it, but the new lines ship from late fiscal 2028, after Corning's customers have already locked supply through 2032.

    Data Center

    Hut 8 shareholders carry River Bend's interest and tax bill until the first hall opens in 2027

    The Louisiana campus's tax terms went public this week: a $7 billion Google-backstopped lease funds the build, while note interest and a smaller tax break than Meta received sit on Hut 8 shareholders until the first hall delivers in mid-2027.

    Data Center

    Fermi's $6.5 billion lease comes due Friday, and the only news this week was a rerun

    The TensorWave lease closes, extends or dies on October 31. One day out there is no closing, no financing, and the one company story circulating this week was a year-old gas press release.

    Data Center

    A short seller says Iron Mountain's data center bet barely covers its interest bill. The stock rose.

    JCapital Research shorted Iron Mountain on October 28, arguing 81% of capex buys 13% of revenue at 1.7x interest cover. The filings agree with the arithmetic; the stock rose anyway.

    Data Center

    CoreWeave's stock has halved since Core Scientific shareholders refused its $9 billion bid

    A year after voting down the $9 billion all-stock sale, Core Scientific's holders hold a refused bid worth about $7.90 a share against a $14.42 stock. The standalone bet's first public test arrives on November 5.

    Data Center

    Nebius reports November 12. Its $3.5 billion Citi loan comes due October 2027.

    The Amsterdam AI cloud, up 103% in 2026, dropped 6 to 7 percent this week after Microsoft said third-party GPU capacity is arriving late. Its November 12 report now has to show customer prepayments outrunning a $3.5 billion loan due October 2027.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.