Furukawa Bets 100 Billion Yen on Fiber While Corning's Customers Lock Supply Through 2032

TrendForce counts a 180 million fiber-kilometer global shortfall for 2026 and data-center fiber prices above five times their 2025 levels. Furukawa Electric's 100 billion yen four-country expansion answers it, but the new lines ship from late fiscal 2028, after Corning's customers have already locked supply through 2032.

Vincent JiangVincent Jiang · 3 min read
Share
Large reels of orange fiber-optic cable mounted on a trailer at a rural fiber installation site, with a bulldozer opening a trench along a dirt road
1 / 5Slide 1 of 5
Fiber-optic cable on reels at an installation site. TrendForce sees demand of 577 million fiber-kilometers in 2026 against a 180 million fiber-km shortfall, and near-term pricing power sits with whoever already has fiber in the ground.

Furukawa Electric−8.45% — Furukawa Electric, down 8.45 percent today, the Tokyo-listed optical fiber and cable maker (TSE: 5801), has laid out a plan to spend about 100 billion yen, roughly $650 million, expanding fiber and rollable ribbon cable output at four units at once: Lightera LLC in the United States, Lightera LatAm S.A. in Brazil, Lightera Japan and Birla Furukawa Fibre Optics in India 1. The plan covers land and buildings alongside manufacturing equipment, and it roughly doubles rollable ribbon cable capacity, in fiber-count terms, against the end of fiscal 2025 1.

Mass production phases in from the second half of fiscal 2028 1.

The market it will enter is already sold out

TrendForce, the Taipei research firm, forecast on October 19 that 2026 global fiber demand reaches 577 million fiber-kilometers against a shortfall of 180 million fiber-km, with the shortage persisting until at least 2028 3. Capacity utilization across the industry's plants sits at 92 percent and inventories have fallen from four months' supply in 2024 to one 3.

Rows of large wooden drums wound with orange fiber-optic cable stored on warehouse racking
Cable drums in a fiber warehouse. Inventories across the fiber industry have fallen from four months' supply in 2024 to one month, per TrendForce. · Fbrandao.1963 via Wikimedia Commons

Pricing follows scarcity: bend-insensitive fiber used inside data centers is projected to average more than five times its 2025 price this year, mainstream telecom fiber about 3.7 times, AI backbone fiber about 2.8 times 3 7. Where the demand comes from is shifting too: data centers account for 18 to 20 percent of fiber consumption this year, a share TrendForce expects to climb to 30 to 35 percent in 2027 3.

Data-center fiber carries the steepest 2026 price multiple

  • 2026 price, multiple of 2025
  • Estimate
0x 2025 price2x 2025 price4x 2025 price6x 2025 priceData-center fiberTelecom fiberAI backbone fiber
Data
2026 price, multiple of 2025
Data-center fiber (estimate)5x 2025 price
Telecom fiber (estimate)3.7x 2025 price
AI backbone fiber (estimate)2.8x 2025 price
Projected 2026 average prices as multiples of 2025 levels, by fiber type, per TrendForce projections reported October 19, 2026. The data-center multiple is stated as more than 5x; charted at 5x. All three figures are projections, drawn dashed. Source: Stocktwits via MSN [3].3

Buyers who signed first, eat first

Preform, the glass rod from which fiber is drawn, takes 18 to 24 months of capacity expansion to bring online 3. A contract signed in 2026 therefore outranks a plant announced in 2026 3.

Corning−5.95% — Corning, down 5.95 percent today, the US fiber leader, agreed in September to supply Verizon+3.22% — Verizon, up 3.22 percent today about 129 million fiber-kilometers, or 80 million fiber miles, through 2032, and signed a more than $3 billion fiber deal with AT&T+2.51% — AT&T, up 2.51 percent today the same month 3. In January, Corning signed a deal worth up to $6 billion with Meta Platforms, which anchors an expansion of Corning's Hickory, North Carolina cable plant 4, running through 2030 5. Furukawa's new lines ship after fiscal 2028, so near-term pricing power stays with whoever has fiber in the ground 45.

The profit signal is partly one-off

On September 24, Furukawa raised its interim profit forecast attributable to owners from 42.5 billion to 58.0 billion yen while holding sales guidance at 720.0 billion yen and operating profit at 49.5 billion yen 2.

The same disclosure covered expected special gains from selling investment securities, so part of that 15.5 billion yen jump is one-off rather than fiber margin 6. A reported INR 45 billion fiber plant in Gujarat, aimed at data-center cable, remains in final discussions rather than signed 2. Meanwhile Corning's shares have lost roughly half their value since a June record despite booming optical sales, a warning on how fast markets price crowded trades 5.

The November 9 checkpoint

Furukawa reports fiscal first-half results on November 9, 2026, at 2:00 p.m 6. JST 6. The test is narrow and dated: whether tight fiber pricing is already lifting operating margins on existing capacity before a single new meter ships. Capacity is the slow lane. Contracts are the fast lane, and the fast lane is booked.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading 5801.T

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Delta Electronics set a record NT$197.1 billion quarter; Vicor's ITC case targets the same AI server modules

    Delta Electronics printed a second straight record quarter on AI server power, yet profit grew slower than sales, four banks cut its Thai unit's targets and the shares fell 9.8%. On the same modules, Vicor's royalty take is built to rise as its US trade case advances: the question for AI-power investors is no longer demand, it is who keeps the margin.

    Data Center

    Hut 8 shareholders carry River Bend's interest and tax bill until the first hall opens in 2027

    The Louisiana campus's tax terms went public this week: a $7 billion Google-backstopped lease funds the build, while note interest and a smaller tax break than Meta received sit on Hut 8 shareholders until the first hall delivers in mid-2027.

    Data Center

    Fermi's $6.5 billion lease comes due Friday, and the only news this week was a rerun

    The TensorWave lease closes, extends or dies on October 31. One day out there is no closing, no financing, and the one company story circulating this week was a year-old gas press release.

    Data Center

    A short seller says Iron Mountain's data center bet barely covers its interest bill. The stock rose.

    JCapital Research shorted Iron Mountain on October 28, arguing 81% of capex buys 13% of revenue at 1.7x interest cover. The filings agree with the arithmetic; the stock rose anyway.

    Data Center

    CoreWeave's stock has halved since Core Scientific shareholders refused its $9 billion bid

    A year after voting down the $9 billion all-stock sale, Core Scientific's holders hold a refused bid worth about $7.90 a share against a $14.42 stock. The standalone bet's first public test arrives on November 5.

    Data Center

    Nebius reports November 12. Its $3.5 billion Citi loan comes due October 2027.

    The Amsterdam AI cloud, up 103% in 2026, dropped 6 to 7 percent this week after Microsoft said third-party GPU capacity is arriving late. Its November 12 report now has to show customer prepayments outrunning a $3.5 billion loan due October 2027.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.