Fermi's $6.5 billion TensorWave lease must close by October 31, and the financing is still not raised

Fermi's first tenant lease at Project Matador must close by October 31 or either party can walk away, and three days out there is no closing, no second extension and no announced guaranty. The stock sits near its lows, a $350 million convertible is in the market, and the phase-one financing that closing requires has not been raised.

Vincent JiangVincent Jiangfour-minute read
Share
Lee McIntire, chief executive of Fermi Inc
1 / 6Slide 1 of 6
Fermi CEO Lee McIntire, who said in September that finalizing the lease guaranty with an investment-grade counterparty was the remaining work before closing.

The founder sold, then the company came for more money

On October 20 Toby Neugebauer, the Fermi co-founder+3.90% — the Fermi co-founder, up 3.90 percent today whose family trust and investment vehicle hold a 10% stake, sold 420,749 shares at prices between $3.00 and $3.095, about $1.3 million, and reported the sale to the SEC two days later 1. That same week the stock touched a 52-week low of $2.99 3.

On October 22 the company put $350 million of convertible senior notes up for sale, and the shares fell more than 18% after hours 2. On Friday, October 31, the lease meant to become Fermi's first real revenue either closes or it does not 4. Three days out, no closing and no second extension has been announced.

The stakes: $6.5 billion of contracted revenue, still on paper

The lease was signed on August 10 5. TensorWave, an AI cloud that runs only on AMD+6.53% — AMD, up 6.53 percent today Instinct GPUs, agreed to take 222 megawatts of total power, 156 megawatts of it critical IT load, at Project Matador, Fermi's behind-the-meter private-grid campus in Carson County, Texas 5.

The paper value is about $6.5 billion of contracted revenue over a 15-year initial term, rent rising 2.5% a year, two five-year renewals, and phased delivery from the fourth quarter of 2027 into early 2028 5. Fermi, which has spent more than $1.5 billion on a campus it expects to scale to 17 gigawatts, puts phase-one operating margins at 75% to 80%, a company estimate 56.

The complication: a backstop that has not started and money that has not arrived

A lease this size does not close on a signature. It closes when work letters and guaranties are executed, boards approve, and project financing sufficient to build the leased facility is secured, which is why the parties pushed the closing date from September 30 to October 31 on September 22 4. CEO Lee McIntire said then that the remaining work was finalizing the lease guaranty with an investment-grade counterparty 4.

On October 13 AMD signed credit support, and Fermi called it a key step toward project financing 5. Read the fact sheet Fermi furnished to the SEC and the support looks different from a guaranty: AMD's obligation begins only after construction is complete and rent starts on the final delivery phase, and it ends early if TensorWave or its guarantor holds investment-grade ratings for 12 straight months 5. It backs financing. It is not the financing, and as of October 20 that phase-one financing had not been raised 5.

Down 71% this year, then a $350 million note sale

From $30.02 to under $3 inside a year

$0$10$20$30$4052-week highOct 20 closeOct 26 closeOct 28 intraday$2.65
Data
FRMI share price
52-week high$30.02
Oct 20 close$2.99
Oct 26 close$2.54
Oct 28 intraday$2.65
FRMI share price, US dollars. Intraday NASDAQ quote at 10:26 AM EDT October 28, 2026; closes as dated. Sources: Stocktwits ticker page (October 28, 2026), Investing.com (October 20, 2026), Yahoo Finance/Simply Wall St (October 27, 2026).3,7,8

The market has been repricing the wait. The stock closed at $2.99 on October 20, a 52-week low at the time 3; its 52-week low now stands at $2.44 7. It last closed at $2.54 on October 26, down about 44% in a month and about 71% this year 8.

Into that slide Fermi is marketing $350 million of notes due 2031, plus a $52.5 million option for the initial purchasers, with proceeds partly earmarked for general corporate purposes 2. The whale move sits with Neugebauer, who sold at an average $3.04 into the weakness 1. The slide itself is not new; it was underway at $3.42 two weeks before the notes offering 9.

The bull case rests on AMD's name and TensorWave's cap

The bull case is not nothing. AMD, rated A by S&P and A1 by Moody's−0.07% — Moody's, down 0.07 percent as of its last quote, put its name on the credit support and signed a framework for expansion past 650 megawatts 5. TensorWave has more than 2 gigawatts of secured capacity across its platform and raised a $350 million Series B with AMD among its investors 5.

Shares jumped 14% on the AMD news on October 13 7. Both companies said on September 22 they remain "fully committed" 4. But that commitment was the same sentence that came with the first extension a month ago, and the guaranty McIntire called the remaining work is still not done 4. The lease's own risk disclosure says either party may terminate if the closing conditions are not satisfied 4.

The close, the money and the earnings call

Three things settle this. The close, on Friday, October 31 4. The money, whether the $350 million note deal prices and at what coupon 2. And the earnings call on November 12, where Fermi must account for a quarter in which its only signed lease had not closed 5. Either side can walk on Friday. The $1.5 billion already poured into the dirt cannot 6. Deep dive below for the documents behind each number.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading AMD

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    CoreWeave's Q4 interest bill of up to $1.15 billion closes in on its full-year adjusted operating income

    Third-quarter revenue of $3.66 billion beat the company's own guidance and lifted the backlog to $132.5 billion, which answers the demand question for now. The same filing names who funds the next stretch of the build: customers, convertible holders and new shareholders.

    Data Center

    TeraWulf sues its host town of Lansing over public records

    The petition lands a week before Lansing votes on a local law that would prohibit data centers outright, the use TeraWulf's unleased 320 MW Lake Hawkeye campus depends on. Roughly 2.1 GW of the company's controlled capacity has no tenant, and WULF holders own that risk at around $12.

    Data Center

    Rackspace triples capex to $104 million with $92 million of fresh stock while AMD commits to buy nothing yet

    The filing will not say how much of the quarter's $104 million of capital spending went to the AMD GPU build, and the AMD agreement commits the chipmaker to nothing up front: for an agreed deployment it would buy only residual unsold capacity, capped per deployment. Rackspace bridged the quarter with $92 million of newly issued stock while the cloud business that must pay for it shrank 17.2%.

    Data Center

    Fermi bets its stalled campus on three refurbished New Jersey turbines

    The Amarillo developer has $62.5 million of cash, a going-concern note and an unsigned tenant lease, and it is buying cheap used megawatts to fill the gap. Earnings on November 12 will show whether the construction lender exists.

    Data Center

    Sanmina pushed $3.5 billion of loan maturities to 2031

    The same filing that guided fiscal 2027 revenue to $17.5 billion to $19.5 billion lifted the stock about 20 percent after hours. Its other page shows the bank line under the ramp: a term loan topped back to $1.4 billion, $600 million still drawable into 2027, and a profit guide stated only in adjusted earnings.

    Data Center

    MARA rose 11% on a $3 billion AI pipeline its own filing calls not yet contracted; $79 million is signed

    MARA's Q3 letter names more than $3 billion of AI demand and has signed $79 million of it. Investors bidding the shares 11% higher on Tuesday are paying for a four-gigawatt story whose only contracted AI revenue is one take-or-pay GPU deal.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.