Power

Microsoft quit Nscale's UK AI campus over power not due until the 2030s; National Grid reports November 5

Microsoft walked out of Nscale's £2 billion Loughton data center after UK Power Networks said power could not be guaranteed until the early 2030s. National Grid, the listed monopoly building the transmission wires the AI boom needs, reports half-year results on November 5 with the Swiss bank UBS holding a Sell rating into them.

Richard TangRichard Tang · 3 min read
Share
Electricity transmission pylons and power lines running across farmland in England
1 / 6Slide 1 of 6
Transmission pylons in England. Microsoft walked out of Nscale's Loughton campus after UK Power Networks said it could not guarantee the site's 90-megawatt connection until the early to mid 2030s.

Microsoft−2.35% — Microsoft, down 2.35 percent today has quit as anchor tenant of Nscale's flagship data center at Loughton in Essex 1, after UK Power Networks, the local distribution operator, told the Nvidia−4.62% — Nvidia, down 4.62 percent today-backed startup it could not guarantee the site's 90-megawatt connection until the early to mid 2030s 2. That leaves National Grid+2.17% — National Grid, up 2.17 percent today, the listed monopoly building the transmission wires the AI boom needs, reporting first-half results on November 5 with the Swiss bank UBS holding a Sell rating into them 3.

A week ago National Grid's story here was an upgraded earnings growth outlook on one-off venture gains (our October 15 article); what is new since is UBS's Sell, Microsoft's walk and a capitalized interest bill that has more than doubled 3.

Loughton had approval, endorsement and no power date

Loughton was the showcase: a £2 billion campus named in the government's 2025 AI action plan 2. It was due to open early next year with 23,040 Nvidia GB300 GPUs serving Microsoft's Azure in Britain 1. The endorsement bought planning approval and official backing; it did not buy a delivery date for electricity 2.

Microsoft's spokesperson called the exit a decision "related to a single site" 1. Nscale, the party with every reason to shrink the problem, called it instead "a London-wide grid issue" 1, and the regulator's queue data supports the startup's framing. For Microsoft the exit is portfolio management: its finance chief has said land and data center shells are a small part of its spending and can be re-timed 4.

The queue is growing faster than the wires

Demand is not in dispute. Ofgem, the UK energy regulator, counts about 315 data center projects waiting for grid connection, and the demand they represent exceeds the country's entire peak use 2; chief executive John Pettigrew expects National Grid's data center demand to multiply sixfold by 2035 2. Delivery is the constraint. The National Energy System Operator has suspended new connection applications while reforms are prepared 2, and the National Audit Office found 64 of 88 Clean Power 2030 projects still at an early stage 3.

Data center demand waiting for the UK grid exceeds the country's peak use

  • Estimate
020406080100UK peak demand45Ofgem queue (formal)73Ofgem queue (rough est.)100
Data
Value
UK peak demand45
Ofgem queue (formal)73
Ofgem queue (rough est.) (estimate)100
Gigawatts of electricity demand. Queue bars are connection demand from data center projects awaiting the UK grid, per Ofgem figures reported by Tech Times; the 100GW figure is Ofgem's own rough estimate, marked as an estimate. UK peak demand shown for scale. Source: [2].2

Loughton is the first visible price of that queue: a customer left rather than wait up to a decade for electricity.

Record profit, and a bigger bill for waiting

UBS forecasts first-half operating profit of £2.624 billion, up from £2.292 billion, with earnings per share of 35.7p against 29.8p, driven by UK electricity transmission 3. Its Sell rests on valuation, not on earnings: National Grid trades at a premium to the value of its regulated asset base, and the bank expects no near-term deterioration 3. Schedule is the separate risk.

Capitalized interest more than doubled to £424 million in the half 3; the company has committed $1.75 billion to a 2.7 gigawatt captive power project in Texas that UBS expects to pay no cash until the 2030s 3; and its US business is appealing a Federal Energy Regulatory Commission (FERC) order behind about $1.5 billion of customer refunds that National Grid plans to process in 2027 53.

National Grid's capital spending has nearly tripled in seven years

$0B$5B$10B$15BFY2019FY2020FY2021FY2022FY2023FY2024FY2025FY2026$13.23B
Data
Capital spending
FY2019$4.8B
FY2020$5.15B
FY2021$5.76B
FY2022$6.67B
FY2023$7.52B
FY2024$8.79B
FY2025$11.37B
FY2026$13.23B
Capital spending by fiscal year ending March, in US dollars, from National Grid's SEC filings as compiled by The Inference; FY2026 ended 31 March 2026. The build program underlies both the capitalized interest bill and the delivery dates UBS and Microsoft's exit now put in question. Source: [6].6

November 5 is about the delivery schedule

The numbers to watch in the results are the build dates and the interest bill. If the transmission program holds its schedule and capitalized interest stops compounding faster than regulated revenue arrives, the case for owning the wires stands; if not, the demand in Ofgem's queue is likely to be built on grids that deliver sooner, and National Grid collects its returns on wires that arrive late 23.

Ofgem's proposed fix, charging developers to hold queue positions, clears the speculative applications but does not shorten a substation build 2. Until someone can promise power on a stated date, anchor tenants with options will keep pricing that gap, and Microsoft just showed what that pricing looks like. Whoever closes that link, a grid operator or a developer building its own power, earns the boom's money.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading MSFT…

Reader comments

0 comments

    Power

    AEP's $4 billion Bloom Energy plant has Google buying 20 years of power and a December deadline

    American Electric Power's $4 billion, 702-megawatt Wyoming plant on Bloom equipment, with Google buying the power for 20 years, is the fuel-cell maker's biggest new commitment since Oracle. But the fine print gives the customer a contractual exit in December, and the utility hedged with a rival vendor the day before.

    Power

    Xcel runs two price books for AI data centers: one public, one confidential

    Colorado opened hearings this week on Xcel's public rulebook for big power customers, while the confidential custom contracts that could carry the biggest loads get only a 120-day review. Minnesota's attorney general wants the same question answered in the open: who pays if the AI boom cools.

    Power

    Constellation's nuclear contracts run 20 years; its cash problem is due now

    Google, Amazon and Meta have locked up the largest US carbon-free power producer under contracts as long as 20 years, and the stock is still down 23 percent this year. Free cash flow has been negative for three straight quarters; the November 6 report shows whether $5.9 billion of court-ordered plant sales closes the gap.

    Power

    Oracle trucks fuel at four times pipeline cost to its AI campuses while Trump posts a power mandate

    The Truth Social "mandate" is political cover, not a rule, but it ratifies a system Oracle already runs: fuel-cell power on site, fuel by truck, and the bill on shareholders. Bloom sends some of the money back to Oracle in equity.

    Power

    Missouri just approved 945 MW of grid. Ameren has already signed 2,800 MW of data centers

    The Missouri PSC approved 945 megawatts of batteries and solar on October 21; Ameren's own plan commits 2.8 gigawatts of signed data center load, ramping from the second half of 2027. The $4 billion to $6 billion that closes the gap has no rate order yet, and 1.3 million ratepayers are waiting to see their share.

    Power

    Amazon's Indiana nuclear deal is a study; AEP's 69 GW of sold load is the story

    AEP, Amazon and X-energy will study twelve small reactors at a retired Indiana coal plant, with no cost, date or contract price disclosed. AEP has contracted 69 GW of new load against the 33 GW of capacity it owns or contracts, and its October 28 capital plan prices the gap.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.