X-energy buys its first Xe-100 steel before the permit exists: the cash test lands November 12

The first Xe-100 steam-generator tubing order landed November 4, four days after the NRC closed the safety review and eight days before a Q3 report that must show the cash to pay for long-lead steel.

Vincent JiangVincent Jiang · 2 min read
Share
A worker stands inside three huge helical coils of stainless steel tube made by Sandvik, photographed in 1937.
1 / 6Slide 1 of 6
Helical coils of stainless steel tube made by Sandvik, the Swedish steelmaker whose materials business became Alleima, photographed in 1937. Alleima makes the Xe-100 steam-generator tubing ordered this week; Doosan Enerbility bends it into coils like these.

The first order buys steel before a permit exists

X-energy$1B — X-energy, private, latest valuation $1B, the Amazon+6.11% — Amazon, up 6.11 percent today-backed developer of the Xe-100 small modular reactor, executed the program's first purchase order for steam generator tubing on November 4, 2026 1. Alleima, the Swedish specialty-steel maker with about 19 billion SEK of 2025 revenue, makes the tube 12. Doosan Enerbility, the Korean manufacturer that has delivered 34 reactor vessels and 124 steam generators worldwide, bends it into helical coils that carry steam up to 565°C 12.

Those coils are a safety-significant, long-lead component for the first deployment: a four-unit, 800 MWt / 320 MWe plant that Long Mott Energy, a Dow subsidiary, wants to build at Seadrift, Texas under the Department of Energy's Advanced Reactor Demonstration Program 13. The order follows a December 2025 agreement reserving Doosan capacity for 16 sets of Xe-100 pressure vessels and internal components 1. Money is now committed to steel before a construction permit exists.

The permit clock is running

The order lands four days after the Nuclear Regulatory Commission released its Final Safety Evaluation Report for the Seadrift plant on October 30, with the environmental review finished in May and both primary reviews complete 3. The NRC says a construction-permit announcement is "soon" 3.

The sellers did not buy the story

None of this stopped the slide. XE fell 23% in a month, Oklo−5.70% — Oklo, down 5.70 percent today 35% and NuScale 31%, against a 9% drop in the Nasdaq 100 4. The stock traded near $10.77 on November 4 67. Jim Cramer's verdict on Mad Money: "it's losing too much money" 4.

The SMR stocks fell three times harder than the Nasdaq 100

010203040Oklo35NuScale31X-energy (XE)23Nasdaq 1009
Data
Value
Oklo35
NuScale31
X-energy (XE)23
Nasdaq 1009
One-month share-price decline through early November 2026, in percent, for X-energy, Oklo and NuScale, against the Nasdaq 100 index. Sources: Yahoo Finance/TIKR (3 Nov 2026).4

Analyst targets run up to five times the current share price

Wedbush's $17 is the low bar on the Street, yet 58% above the traded price

$0$20$40$60Guggenheim$57Morgan Stanley$34Consensus mean$31UBS$18Wedbush (new)$17XE price, Nov 4$10.77
Data
Value
Guggenheim$57
Morgan Stanley$34
Consensus mean$31
UBS$18
Wedbush (new)$17
XE price, Nov 4$10.77
Price targets in US dollars per share, X-energy (Nasdaq: XE), as of November 3-4, 2026; the last bar is the traded price, not a target. Sources: Yahoo Finance/TIKR (3 Nov 2026); X-energy investor relations quote (4 Nov 2026).4,7

Wedbush split the field on November 3: Outperform on X-energy with a $17 target, Underperform on NuScale at $5, alongside Outperform calls on Oklo and NANO Nuclear 45. The consensus target has slid from $48 at the May coverage start to $31 4.

The cash test is the real deadline

Analysts still model revenue stepping from $210 million this year to $860 million in 2027 4. Wedbush's own $17 works out to just under 9x forward sales, below the stock's 13x post-IPO average 4. A Seeking Alpha analysis in October counted a $1.9 billion cash position 8. That cash must now fund the burn and the steel.

Watch two dates: the construction-permit announcement the NRC has promised 3, and November 12, when X-energy reports third-quarter results 7. The permit decides whether the schedule holds. The cash report decides who pays for the wait.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AMZN

Reader comments

0 comments

    Power

    Morgan Stanley: data centers outbuy utilities on batteries in 2030; Tesla's energy backlog is $10.7 billion

    Morgan Stanley now expects data centers to buy more batteries in 2030 than utilities do, against a power shortfall above 80 gigawatts by 2029. Tesla is the obvious seller, and its storage line is the one part of the AI story already earning the money.

    Power

    AEP built the machine for its AI load before the load exists, and Jacobs gets paid either way

    In one week AEP hired the builders for its $37 billion transmission program and created a unit to sign contracts with the very customers driving the load. The 84 gigawatts are agreements, not meters, and the equity is already raised.

    Power

    Brookfield's $95/MWh hydro deals put a price on AI power hunger

    Two 10-year hydro PPAs at about $95/MWh are the clearest price yet on AI-era power demand, even as Brookfield sells pieces of that same fleet to fund batteries and new build.

    Power

    Meta Buys Williams Power; Blackstone's $5.34 Billion Builds It

    Barron's named Meta on November 3 as the buyer of 400 megawatts of behind-the-meter gas power from Williams. The plants are financed with $5.34 billion of Blackstone-led capital because Williams' leverage, at 3.80 times, already sits under a four-times ceiling that now governs executive pay.

    Power

    Generac's Amazon warrant is worth $112.5 million, more than its quarter's profit, and cuts Amazon revenue

    The generator maker's 10-Q prices the warrant it gave Amazon at $112.5 million and books it against Amazon revenue as the generators ship, more than the quarter's entire profit. The same filing shows how far the $4.5 billion backlog sits from the accounting.

    Power

    First Solar's 16% election rally ignored a December 4 import floor that moves production to Gaffney

    The election rally priced a Congress that cannot touch either federal lever behind First Solar's results before the Section 232 import floor lands on December 4. The floor relocates production to Gaffney, South Carolina, and the credit, not Congress, holds the margin.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.