Power

xAI bought jet engines for Colossus 2, but its legal power is cut in half by July 2027

xAI's Colossus 2 cluster is racing toward 1.2 million GPUs on power it is legally scheduled to lose: a July 30, 2026, order cuts its turbines from 2.7GW to 1.24GW by July 2027, and SemiAnalysis sees a gap of upwards of 300MW.

Vincent JiangVincent Jiang · 3 min read
Share
A General Electric CF6 turbofan engine, the core that ProEnergy rebuilds into 50MW turbines for xAI's Southaven power site
1 / 6Slide 1 of 6
A General Electric CF6 turbofan, the engine core ProEnergy rebuilds into the 50MW turbines powering xAI's Colossus 2

The power that runs Elon Musk's AI cloud is on a deadline. On November 3 the New York Times reported, from state permits and satellite imagery, that xAI$200B — xAI, private, latest valuation $200B has installed eight converted jet-engine turbines at the Southaven, Mississippi plant that feeds its Colossus 2 data center cluster near Memphis 71. ProEnergy rebuilt them from CF6-80C2 cores, the same engine that flew on Boeing+2.26% — Boeing, up 2.26 percent today 747s; each is rated 50MW in the state air permit, roughly 400MW together 78.

xAI is now part of SpaceX−4.47% — SpaceX, down 4.47 percent today, and these sites are the foundation of the company's AI cloud. The engines buy speed, and the speed advantage expires on a schedule. A binding requirement signed July 30, 2026, a state order restricting which turbines may run and when, cuts the Southaven site's legal nameplate capacity, its maximum rated output before derates, from 2.7GW today to 1.24GW by July 2027, making 41 permitted turbines the permanent power source 27.

The arithmetic does not close

SemiAnalysis's power model works it this way: the regional utility, the Tennessee Valley Authority (TVA), has received grid service requests of 700MW for Macrohard and 450MW for MiniHard, about 1.2GW that would serve those two of the five Colossus 2 sites in full 2. That leaves roughly 1.3GW of compute to be fed by 1.24GW of nameplate generation, which then takes a further haircut on efficiency and derate 2. Hence SemiAnalysis's conclusion that "there could be a gap upwards of 300MW" 2.

Its proposed fix is a battery field nearing 5.9GWh, lower-power racks and tiered uptime promises 2. None of that is permitted or contracted; it is SemiAnalysis's projection 2. All of it sits on a campus meant to hold about 1.2 million Blackwell GPUs by the end of 2026 23.

Colossus 2's legal power ceiling falls from 2.7GW to 1.24GW by July 2027

Southaven's legal power is cut by more than half before the GPU buildout finishes

  • Estimate
0123Legal nameplate now2.7Legal nameplate July 20271.24Grid request, Macrohard0.7Grid request, MiniHard0.45Gap (SemiAnalysis est.)0.3
Data
Value
Legal nameplate now2.7
Legal nameplate July 20271.24
Grid request, Macrohard0.7
Grid request, MiniHard0.45
Gap (SemiAnalysis est.) (estimate)0.3
Gigawatts of nameplate capacity and grid service requests at the Colossus 2 / Southaven site. The gap bar is SemiAnalysis's conditional estimate ('could be a gap upwards of 300MW'), not a reported figure. Sources: SemiAnalysis Energy Model (4 Nov 2026) [2]; TechCrunch citing the New York Times (3 Nov 2026) [1].2,1

Everyone else is still waiting for the grid

Hooking 100MW up in Northern Virginia takes about seven years, per the International Energy Agency, which is why operators buy jet engines that run in 24 months 1. Entergy+2.46% — Entergy, up 2.46 percent today, the utility whose Mississippi territory holds the site, told investors on November 2 that data-center interest there totals 7 to 12GW with none of it in its base plan 4.

Its Mississippi peak load rose 11 percent as data centers ramped 4. The biggest tenant makes its own power, off the rate base (outside the utility's regulated costs that set customer bills), under a court order: on October 30 Judge Debra Brown let the NAACP's Clean Air Act suit over the portable turbines proceed 84.

The risk is not hypothetical

The NAACP claims the 27 turbines built without permits could emit about 1,700 tons of nitrogen oxides a year and seeks penalties of up to $124,426 a day per violation; a preliminary injunction motion is still pending 8. The jet-engine permits themselves are on appeal: the units may emit double the carbon monoxide allowed for the plant's 33 other turbines and 25 percent more volatile organic compounds, and the Mississippi Permit Board hears that appeal on November 9 71.

More than 100,000 people live within five miles of the sites 7. SemiAnalysis's 13GW-in-2027 and $300 billion-plus ARR scenario for SpaceX rests on megawatts this cluster is scheduled to lose 2. So does Grok Bot, which hit 800,000 paid weekly users in October while Musk called its serving cost "unsustainably high relative to revenue" 5.

For SpaceX holders, the discipline follows from the dates: the November 9 permit appeal and the July 2027 nameplate cut decide whether the compute is actually powered, so the revenue ramp should not be paid for before both settle 27. Until then, what is contracted at Southaven is 1.24GW of legal generation by next summer, and everything above it is projection 27.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading BA

Reader comments

0 comments

    Power

    Brookfield's $95/MWh hydro deals put a price on AI power hunger

    Two 10-year hydro PPAs at about $95/MWh are the clearest price yet on AI-era power demand, even as Brookfield sells pieces of that same fleet to fund batteries and new build.

    Power

    Meta Buys Williams Power; Blackstone's $5.34 Billion Builds It

    Barron's named Meta on November 3 as the buyer of 400 megawatts of behind-the-meter gas power from Williams. The plants are financed with $5.34 billion of Blackstone-led capital because Williams' leverage, at 3.80 times, already sits under a four-times ceiling that now governs executive pay.

    Power

    Generac's Amazon warrant is worth $112.5 million, more than its quarter's profit, and cuts Amazon revenue

    The generator maker's 10-Q prices the warrant it gave Amazon at $112.5 million and books it against Amazon revenue as the generators ship, more than the quarter's entire profit. The same filing shows how far the $4.5 billion backlog sits from the accounting.

    Power

    First Solar's 16% election rally ignored a December 4 import floor that moves production to Gaffney

    The election rally priced a Congress that cannot touch either federal lever behind First Solar's results before the Section 232 import floor lands on December 4. The floor relocates production to Gaffney, South Carolina, and the credit, not Congress, holds the margin.

    Power

    Siemens and AES put their executives in Fluence's top jobs as a $6.4 billion backlog suit nears deadline

    Siemens and AES have put their own executives into Fluence's top two jobs on interim terms while the executives they replaced stand as defendants in a fraud suit over a $6.4 billion backlog. The next test is fixed: fiscal 2026 results on November 23.

    Power

    X-energy buys its first Xe-100 steel before the permit exists: the cash test lands November 12

    The first Xe-100 steam-generator tubing order landed November 4, four days after the NRC closed the safety review and eight days before a Q3 report that must show the cash to pay for long-lead steel.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.