xAI bought jet engines for Colossus 2, but its legal power is cut in half by July 2027

xAI's Colossus 2 cluster is racing toward 1.2 million GPUs on power it is legally scheduled to lose: a July 30, 2026, order cuts its turbines from 2.7GW to 1.24GW by July 2027, and SemiAnalysis sees a gap of upwards of 300MW.

Vincent JiangVincent Jiangthree-minute read
Share
A General Electric CF6 turbofan engine, the core that ProEnergy rebuilds into 50MW turbines for xAI's Southaven power site
1 / 6Slide 1 of 6
A General Electric CF6 turbofan, the engine core ProEnergy rebuilds into the 50MW turbines powering xAI's Colossus 2

The power that runs Elon Musk's AI cloud is on a deadline. On November 3 the New York Times reported, from state permits and satellite imagery, that xAI$200B — xAI, private, latest valuation $200B has installed eight converted jet-engine turbines at the Southaven, Mississippi plant that feeds its Colossus 2 data center cluster near Memphis 71. ProEnergy rebuilt them from CF6-80C2 cores, the same engine that flew on Boeing+0.52% — Boeing, up 0.52 percent today 747s; each is rated 50MW in the state air permit, roughly 400MW together 78.

xAI is now part of SpaceX+9.50% — SpaceX, up 9.50 percent today, and these sites are the foundation of the company's AI cloud. The engines buy speed, and the speed advantage expires on a schedule. A binding requirement signed July 30, 2026, a state order restricting which turbines may run and when, cuts the Southaven site's legal nameplate capacity, its maximum rated output before derates, from 2.7GW today to 1.24GW by July 2027, making 41 permitted turbines the permanent power source 27.

The arithmetic does not close

SemiAnalysis's power model works it this way: the regional utility, the Tennessee Valley Authority (TVA), has received grid service requests of 700MW for Macrohard and 450MW for MiniHard, about 1.2GW that would serve those two of the five Colossus 2 sites in full 2. That leaves roughly 1.3GW of compute to be fed by 1.24GW of nameplate generation, which then takes a further haircut on efficiency and derate 2. Hence SemiAnalysis's conclusion that "there could be a gap upwards of 300MW" 2.

Its proposed fix is a battery field nearing 5.9GWh, lower-power racks and tiered uptime promises 2. None of that is permitted or contracted; it is SemiAnalysis's projection 2. All of it sits on a campus meant to hold about 1.2 million Blackwell GPUs by the end of 2026 23.

Colossus 2's legal power ceiling falls from 2.7GW to 1.24GW by July 2027

Southaven's legal power is cut by more than half before the GPU buildout finishes

  • Estimate
0123Legal nameplate now2.7Legal nameplate July 20271.24Grid request, Macrohard0.7Grid request, MiniHard0.45Gap (SemiAnalysis est.)0.3
Data
Value
Legal nameplate now2.7
Legal nameplate July 20271.24
Grid request, Macrohard0.7
Grid request, MiniHard0.45
Gap (SemiAnalysis est.) (estimate)0.3
Gigawatts of nameplate capacity and grid service requests at the Colossus 2 / Southaven site. The gap bar is SemiAnalysis's conditional estimate ('could be a gap upwards of 300MW'), not a reported figure. Sources: SemiAnalysis Energy Model (4 Nov 2026) [2]; TechCrunch citing the New York Times (3 Nov 2026) [1].2,1

Everyone else is still waiting for the grid

Hooking 100MW up in Northern Virginia takes about seven years, per the International Energy Agency, which is why operators buy jet engines that run in 24 months 1. Entergy+0.23% — Entergy, up 0.23 percent today, the utility whose Mississippi territory holds the site, told investors on November 2 that data-center interest there totals 7 to 12GW with none of it in its base plan 4.

Its Mississippi peak load rose 11 percent as data centers ramped 4. The biggest tenant makes its own power, off the rate base (outside the utility's regulated costs that set customer bills), under a court order: on October 30 Judge Debra Brown let the NAACP's Clean Air Act suit over the portable turbines proceed 84.

The risk is not hypothetical

The NAACP claims the 27 turbines built without permits could emit about 1,700 tons of nitrogen oxides a year and seeks penalties of up to $124,426 a day per violation; a preliminary injunction motion is still pending 8. The jet-engine permits themselves are on appeal: the units may emit double the carbon monoxide allowed for the plant's 33 other turbines and 25 percent more volatile organic compounds, and the Mississippi Permit Board hears that appeal on November 9 71.

More than 100,000 people live within five miles of the sites 7. SemiAnalysis's 13GW-in-2027 and $300 billion-plus ARR scenario for SpaceX rests on megawatts this cluster is scheduled to lose 2. So does Grok Bot, which hit 800,000 paid weekly users in October while Musk called its serving cost "unsustainably high relative to revenue" 5.

For SpaceX holders, the discipline follows from the dates: the November 9 permit appeal and the July 2027 nameplate cut decide whether the compute is actually powered, so the revenue ramp should not be paid for before both settle 27. Until then, what is contracted at Southaven is 1.24GW of legal generation by next summer, and everything above it is projection 27.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading BA

Reader comments

0 comments

    Power

    First Solar's CEO put $150 million into India, toward $1 billion, as capex fell for eight straight quarters

    Investors bid up First Solar on a friendlier Washington the same week its chief executive put another $150 million into India and said policy certainty is "absolutely critical". The capital is speaking louder than the stock.

    Power

    Vistra guided 2027 EBITDA to $7.7 to $8.5 billion with 98% of output hedged before the Texas vote

    Vistra's first 2027 outlook landed with about 98% of next year's output already hedged before the Texas election, and the market that had marked the stock down 16% on the governor's race paid up for a year a January inauguration cannot touch. The open fight starts in 2028, where the hedges run out.

    Power

    Kinder Morgan's Southeast Connector just got bigger: 20 shippers, 48-inch pipe, 3.7 Bcf/d in sight

    Two weeks after a $3.1 billion FID sized the pipe at 2.6 Bcf/d, Kinder's bulletin board shows another 1.1 Bcf/d of shipper awards and 20 takers. The land fight along the 150-mile Tennessee route has not started yet; the commercial demand already beat the plan.

    Power

    Walmart invested in Base Power, which claims 100 megawatts a month on a $13 billion valuation

    Base Power announced backup batteries for nearly 6,500 North Texas homes, a Walmart investment, and a 100 MW-a-month install pace, all on a $13 billion valuation. Homeowners fund the fleet; Base pools it and sells it back to the grid.

    Power

    Oklo raised $2.25 billion selling stock at $70.19; the market values everything it builds at $700 million

    The Q3 filing holds Oklo's build guidance and posts record construction spending; at a $3.8 billion market value against $3.13 billion banked, the market carries everything the company does beyond holding cash at roughly $700 million.

    Power

    MARA moved 1,650 bitcoin worth $132.8 million as its $1.5 billion gas plant deal finds no AI tenant

    The bitcoin miner moved 1,650 coins to institutional venues the same day FERC cleared its $1.5 billion gas plant deal, and the stock sank 14% anyway. Its AI pivot runs on bitcoin-backed debt, and the promised AI lease still has no tenant.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.