Cipher Digital booked $5.85 million of first AI rent against $6.7 billion of debt

Cipher's first quarter booking HPC rent produced $27 million of revenue and negative $10 million of adjusted EBITDA, against $16.6 billion of contracted leases and $6.7 billion of debt. Analysts cut their targets on November 3 and kept calling the shares undervalued; both halves are right.

Vincent JiangVincent Jiang · 3 min read
Share
Aerial view of a large Cipher data center campus under construction in West Texas
1 / 7Slide 1 of 7
A Cipher HPC campus under construction: the sites behind $16.6 billion of signed leases must still be delivered, with Barber Lake and Black Pearl due in the first quarter of 2027.

Cipher Digital's−20.87% — Cipher Digital, down 20.87 percent today first quarter as a landlord is on the record, and it is thin: revenue of $27 million, adjusted EBITDA of negative $10 million, and the first $5.85 million of high-performance-computing rent, booked after tenants began paying at the Black Pearl campus 12. Behind those small numbers sit two large ones. Roughly $16.6 billion of contracted rent sits in signed leases averaging 17.3 years, which management pegs at about $864 million of average annualized net operating income 2.

And roughly $6.7 billion of debt stands in front of a market capitalization of about $3.5 billion 2. The shares, down about 68 percent from a late-July close near $22.66 to $6.86 on November 2, sit under both numbers 23.

The mining era is winding down on the income statement

The company used to be Cipher Mining, a bitcoin miner, and the filings show the pivot in real time. Mining-era revenue peaked at $71.7 million in the third quarter of 2025 and fell to $24.8 million by the second quarter of 2026, before the landlord quarter lifted the total back to $27 million, with $5.85 million of it, the first HPC rent ever booked, coming from leases rather than machines 16. The replacement business leases campuses to AI labs and hyperscalers for up to two decades at a time.

Cipher's revenue bottomed at $24.8M, then the first rent arrived

Mining-era revenue decay ended with the first landlord quarter at $27 million

20M40M60M80MQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '2626.7M
Data
Revenue
Q1 '2448.1M
Q2 '2436.8M
Q3 '2424.1M
Q4 '2442.2M
Q1 '2549M
Q2 '2543.6M
Q3 '2571.7M
Q4 '2559.7M
Q1 '2634.8M
Q2 '2624.8M
Q3 '2626.7M
Quarterly total revenue in US$ millions. Q1 2024 through Q2 2026 from SEC filings via company_series; Q3 2026 of $26.7 million, including $5.85 million of first HPC leasing revenue, from Cipher's third quarter 2026 business update. Sources: [1][6].1,6

The contract got bigger, and so did the bill

The promise grew this quarter. An amended Barber Lake lease adds a second ten-year term directly with a leading AI lab, lifting contracted revenue at that site to about $9.1 billion, including $5.2 billion of incremental rent, and restoring projected yield on cost to about 15 percent from about 13 percent 13. But the same tenant's design changes pushed Barber Lake's expected cost to about $13 million per critical IT megawatt from about $10.4 million, with $409 million of change orders of which the tenant reimburses only about $50 million 23.

More debt now stands in front of the equity

Total borrowings sit near $6.7 billion, including about $4.5 billion of non-recourse project notes and $2.2 billion of parent-level convertibles, against that $3.5 billion market capitalization; adding the debt takes enterprise value to roughly $8.4 billion, the number the leases must justify 2.

In October Cipher sold $850 million of 0.000% convertible notes due 2032, priced to convert at $15.31 with capped calls lifting the effective conversion price to $28.35, and swapped $165.9 million of 1.750% notes into about 40.7 million shares, adding more than 10 percent to the share count 123. The new money pays no interest unless the stock more than doubles from here.

Cipher owes $6.7B behind a $3.5B market cap

Debt is nearly double the equity's market value before any lease cash arrives

0B5B10BTotal debtMarket capEnterprise value8.4B
Data
US$B
Total debt6.7B
Market cap3.5B
Enterprise value8.4B
US$ billions as reported in November 2026: about $6.7 billion of total debt, of which $4.5 billion non-recourse project notes and $2.2 billion parent-level convertibles; market capitalization about $3.5 billion; enterprise value about $8.4 billion. Source: [2].2

The sell-side analysts cut targets and kept the buys

On November 3 the banks covering Cipher, sell-side analysts at JPMorgan, Wells Fargo+1.77% — Wells Fargo, up 1.77 percent today, Needham, Cantor Fitzgerald and Rosenblatt, cut their price targets while keeping buy ratings: JPMorgan+4.04% — JPMorgan, up 4.04 percent today to $18 from $22, Wells Fargo to $15 from $25, Rosenblatt and Cantor to $19 and $15 345. Bernstein, another covering firm, cut to $23 from $32 after raising its cost of capital to 15 percent, the discount rate it applies to future cash flows 3.

Every covering bank cut its Cipher target on November 3, all well above $6.86

  • Old target
  • New target
$0$10$20$30$40Bernstein$23$32-28%Wells Fargo$15$25-40%JPMorgan$18$22-18%
Data
Old targetNew targetChange
Bernstein$32$23-28.1%
Wells Fargo$25$15-40.0%
JPMorgan$22$18-18.2%
Price targets in US dollars, before and after the November 3 cuts. Rosenblatt and Cantor Fitzgerald set new targets of $19 and $15 without published prior levels in the cited reports. Sources: [3][4][5].3,4,5

Its own arithmetic shows why the disagreement is narrow: the contracted campuses imply a cap rate, the annual income a property yields on its total cost, of about 11 percent, against 5 to 7 percent for established data-center REITs 3.

Barber Lake and Black Pearl deliveries in the first quarter of 2027 are the dated test of whether that $864 million a year arrives as cash or stays as paper 23. Until then the record offers a choice between two true numbers: a $3.5 billion market capitalization owning $16.6 billion of contracts, and an $8.4 billion enterprise value that owes the debt before shareholders see any of it 2.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading CIFR

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Trane booked a $12.5 billion backlog, and the market still sold it

    Trane Technologies beat estimates and raised its revenue guidance, yet the stock fell as much as 11% to a seven-month low. The gap between booked demand and booked margin is where the AI cooling trade now lives.

    Data Center

    WhiteFiber's $865 million lease is signed; delivering it is what the market doubts

    WhiteFiber closed a $60 million land purchase the same week it admitted switchgear problems have delayed billing at its first North Carolina data hall and its project financing still is not signed. The $865 million lease proves the demand; the open question is delivery.

    Data Center

    S&P priced Meta's $15 billion notes at 220 basis points, nearly twice April's, amid AI debt it cannot see

    S&P stamped Meta's new AA- notes days after warning that $71 billion of projected cash deficits lie ahead, while its own infrastructure chief says the AI debt behind the buildout exceeds what the agency can see. The unrated layer beneath the letters, Jane Street's $19 billion of compute commitments, has already cracked first.

    Data Center

    S&P gave Equinix's new bonds a 6.5x downgrade trigger; its shareholders face 5x and election risk

    On November 3 S&P rated the new notes BBB+ with a 6.5x downgrade trigger, and the same night three data-center states elected governors who want conditions on new builds. The debt holds a covenant-shaped cushion; the equity holds the timetable.

    Data Center

    CDW grew sales 17.7%, but gross margin fell 140 basis points to 20.5% as hardware mix grew

    CDW's third quarter filed November 4 shows enterprise AI hardware moving through the reseller at full speed and at a thinner cut: sales up 17.7 percent, gross margin down 140 basis points, and per-share earnings made below the gross profit line.

    Data Center

    Democrats won the midterms; CoreWeave's $4.4 billion of 2026 debt now waits on Texas

    The election does not touch CoreWeave's signed contracts. It touches the megawatts still to energize this year and the $4.4 billion due before the backlog cash flows, and the bond market has been voting on that for weeks.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.