Power

Exelon's ComEd holds $721 million against a $3.1 billion data-center bill; Illinois rules December 15

ComEd's price for wiring 30 data centers into its northern Illinois grid is $3.1 billion, and developers have deposited $721 million. Consumer groups warn a $2 billion gap could reach household bills, and state regulators rule by December 15.

Vincent JiangVincent Jiang · 3 min read
Share
Calvin Butler, president and chief executive of Exelon Corporation
1 / 6Slide 1 of 6
Exelon chief executive Calvin Butler. His company's ComEd utility has priced the data-center grid bill at $3.1 billion; developers have $721 million on deposit.

ComEd, Exelon's Illinois utility, has priced what the AI buildout costs just to plug in: $3.1 billion of transmission and distribution work to connect 30 data centers, each drawing 50 megawatts or more, built since 2021 or due online through 2031 123. Developers have deposited $721 million, less than a quarter of the bill 1. Who guarantees the rest is now before the Illinois Commerce Commission, the state's utility regulator.

A $2 billion warning aimed at household bills

The Citizens Utility Board and the Environmental Law & Policy Center, whose expert testimony surfaced the figures, say a project that collapses after the wires go up strands its costs on everyone else, and they put the potential exposure at about $2 billion 12. "We don't want to pay for grid bridges to nowhere," CUB general counsel Eric DeBellis said 1.

Their bill in Springfield, the Protecting Our Water, Energy and Ratepayers (POWER) Act, would require data centers to pay 100% of grid costs before connecting; the veto session that could take it up runs mid-November into early December 2.

Deposits cover less than a quarter of ComEd's $3.1 billion hookup bill

Advocates' warned $2B exposure tops the $1.8B of deposits plus TSA credit

$0B$0.5B$1B$1.5B$2BDeposits paid by developers$0.72BTransmission under TSA credit lines$1.1BShortfall consumer groups warn of$2B19 of 30 projects predate the TSA rule
Data
Value
Deposits paid by developers$0.72B
Transmission under TSA credit lines$1.1B
Shortfall consumer groups warn of$2B
ComEd records in a pending Illinois Commerce Commission case, reported October 22–27, 2026; the shortfall is the consumer groups' warning, not a levied bill.1

ComEd counts credit lines that arrived late

ComEd's rebuttal is that the groups skipped $1.1 billion of transmission cost already secured by transmission security agreements, credit lines guaranteeing ten years of payments even if a project dies 1. Two caveats sit in its own records: 19 of the 30 projects were approved before regulators endorsed the TSA requirement in 2025, and the two priciest hookups cost $289 million and $269 million each 1. Deposits will rise as engineering matures, ComEd says, and TSA screening has culled speculative requests; of 11 projects recently reviewed, four survived 14.

Exelon's growth story is the defendant

Exelon+1.63% — Exelon, up 1.63 percent today told investors on October 30 that about 9 of its 11 gigawatts of high probability data center load sits at ComEd, 45% of it TSA-backed by $1.2 billion of collateral, with actual northern Illinois data center demand compounding at about 28% a year since 2022 5.

The parent's $41.7 billion capital plan runs on 7.9% annual rate base growth, yet only about a tenth of that load energizes by 2028 6. Jefferies+5.37% — Jefferies, up 5.37 percent today cut its Exelon target to $46 from $49 on October 28, RBC to $46 from $48 two days earlier, and the stock closed at $45.50 on November 3 7.

The order lands December 15

An administrative law judge has recommended approving ComEd's $15.3 billion grid plan with modifications, and the commission's order is due December 15 6. The same commission rejected ComEd's first grid plan in 2023 as unaffordable 3. Watch the deposits: if they climb toward filed costs, ComEd's model holds; if regulators or the POWER Act force full payment up front, Illinois writes the rule Florida and California are already arguing over 28.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading JEF

Reader comments

0 comments

    Power

    Morgan Stanley: data centers outbuy utilities on batteries in 2030; Tesla's energy backlog is $10.7 billion

    Morgan Stanley now expects data centers to buy more batteries in 2030 than utilities do, against a power shortfall above 80 gigawatts by 2029. Tesla is the obvious seller, and its storage line is the one part of the AI story already earning the money.

    Power

    AEP built the machine for its AI load before the load exists, and Jacobs gets paid either way

    In one week AEP hired the builders for its $37 billion transmission program and created a unit to sign contracts with the very customers driving the load. The 84 gigawatts are agreements, not meters, and the equity is already raised.

    Power

    Brookfield's $95/MWh hydro deals put a price on AI power hunger

    Two 10-year hydro PPAs at about $95/MWh are the clearest price yet on AI-era power demand, even as Brookfield sells pieces of that same fleet to fund batteries and new build.

    Power

    Meta Buys Williams Power; Blackstone's $5.34 Billion Builds It

    Barron's named Meta on November 3 as the buyer of 400 megawatts of behind-the-meter gas power from Williams. The plants are financed with $5.34 billion of Blackstone-led capital because Williams' leverage, at 3.80 times, already sits under a four-times ceiling that now governs executive pay.

    Power

    Generac's Amazon warrant is worth $112.5 million, more than its quarter's profit, and cuts Amazon revenue

    The generator maker's 10-Q prices the warrant it gave Amazon at $112.5 million and books it against Amazon revenue as the generators ship, more than the quarter's entire profit. The same filing shows how far the $4.5 billion backlog sits from the accounting.

    Power

    First Solar's 16% election rally ignored a December 4 import floor that moves production to Gaffney

    The election rally priced a Congress that cannot touch either federal lever behind First Solar's results before the Section 232 import floor lands on December 4. The floor relocates production to Gaffney, South Carolina, and the credit, not Congress, holds the margin.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.