GE Vernova turned 13 GW of reserved turbine slots into firm orders; backlog hit $197 billion

The quarter answers whether the gas slot book was real demand: 13 gigawatts converted to firm orders, backlog hit $197 billion, and free cash flow guidance jumped to $16-17 billion. What the company does with that cash, and who pays the AI premium, is the trade.

Vincent JiangVincent Jiangthree-minute read
Share
Scott Strazik, GE Vernova's chief executive, in a navy suit and open-collar shirt, smiling at the camera
1 / 7Slide 1 of 7
Scott Strazik, GE Vernova's chief executive. The company converted 13 GW of reserved gas turbine slots into firm orders in the third quarter.

The waiting room is emptying. A quarter ago the question hanging over GE Vernova+0.29% — GE Vernova, up 0.29 percent today, the Cambridge, Massachusetts power-equipment maker spun out of GE, was whether its 116 gigawatts of contracted-and-reserved gas turbine capacity was demand or a queue of tentative tire-kickers 1. This morning's third-quarter filing answers it: 13 GW of slot reservation agreements converted to firm orders, another 11 GW of new gas contracts were signed, and 5 GW of equipment shipped out the door 1. Orders hit $29.3 billion, up 96% organically 1.

The backlog is now $197 billion, and the money is arriving

Total backlog reached $197 billion, up $20 billion sequentially, and management expects it above $200 billion next quarter 1. The cash side converted too: free cash flow of $5.4 billion in the quarter, and full-year guidance raised to $16-17 billion from $11.5-12.5 billion 1. Revenue of $12.6 billion beat the $12.01 billion consensus; earnings per share of $4.81 beat $4.01 4.

Free cash flow has outrun revenue growth for three straight quarters

  • Revenue
  • Free cash flow
051015Q3 '24Q4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '2612.65.4
Data
RevenueFree cash flow
Q3 '248.91
Q4 '2410.60.6
Q1 '2581
Q2 '259.10.2
Q3 '25100.7
Q4 '25111.8
Q1 '269.35
Q2 '2611.15.1
Q3 '2612.65.4
Quarterly revenue and free cash flow, US$ billions, from SEC filings via company_series; Q3 2026 from the October 28, 2026 8-K.5,1

The AI premium shows up in margin, not just volume

Adjusted EBITDA margin of 15.4% rose 690 basis points organically on higher price, volume and productivity; the Power segment alone priced at a 21.4% margin, up 800 basis points 1. Utilities and data centers that need megawatts this decade are paying up for rationed turbine slots, and hyperscalers sit among the named customers of the grid-equipment supplier GE Vernova just agreed to buy 13.

The complication: a $0.6 billion quarter of capex against a $20 billion buyback

Here is what should raise an eyebrow. The board doubled the repurchase authorization to $20 billion, and the company has already spent $9.9 billion buying back stock at about $635 a share 1. Quarterly capital expenditure was $0.6 billion against a $6 billion 2025-28 commitment 1.

Meanwhile a $9 billion acquisition of Trench Group, a high-voltage grid-equipment maker bought from Triton Partners at 13x 2028 EBITDA before synergies, will be funded half with cash and half with debt, and does not close until late 2027 3. The landlord is returning cash and buying suppliers, not breaking ground on factories.

Gas contracts under signature or reservation: 122 GW, with 130 GW promised by year end

  • Equipment backlog
  • Slot reservations
  • Estimate
050100150Prior quarterQ3 2026Year-end 2026 targetCompany target: at least 130 GW6458
Data
Equipment backlogSlot reservations
Prior quarter5363
Q3 20266458
Year-end 2026 target (estimate)7560
Gas power equipment backlog and slot reservation agreements in gigawatts; year-end target is company guidance, shown as an illustrative total split by the Q3 mix. Source: GE Vernova Q3 2026 8-K.1

The counterpoint, and what to watch

Shares rose about 2% premarket on the print 2. The bear case is still alive: Wind remains guided to $400-500 million of segment EBITDA losses in 2026, and Wall Street expects full-year EPS to shrink 38.5% over the next 12 months as growth investments bite 14.

What settles it is on the calendar: Q4 backlog above $200 billion and gas capacity under contract of at least 130 GW by December 31, 2026, both promised in writing 1. If slot money keeps converting into delivered revenue at these margins, the premium holds; a slowdown in data center capex is the thing that empties the queue from the other end.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading GEV

Reader comments

0 comments

    Power

    MARA sold 13,597 bitcoin for $1.1 billion after FERC cleared its $1.5 billion Long Ridge gas plant buy

    FERC's clearance turns December into a double deadline for MARA: close the $1.5 billion Long Ridge gas plant, and sign the AI leases it still lacks. Analysts are split from $11 to $20 on what the unsigned megawatts are worth.

    Power

    Southern Company can sell 12 million shares at any moment as its capital plan could reach $100 billion

    Southern Company, Georgia Power's parent, can now sell stock the moment it chooses after filing an automatic shelf on November 10. The capital plan behind the filing could approach $100 billion, its remaining equity is unpriced, and in January a new Democratic majority arrives on Georgia's utility commission with authority over who pays.

    Power

    Duke Energy asks Florida for 300 MW of solar and a $1 billion savings claim, six days after a data-center loss

    The filing claims $1 billion of lifetime customer savings, but that number is avoided fuel cost, not a bill credit, and it lands six days after the same commission unanimously rejected Duke's data-center cost plan. For Duke shareholders, commissions reading this arithmetic decide whether the $103 billion build gets paid.

    Power

    Talen Energy sells 750 MW of capacity for $100 million a year, keeps the power merchant

    The seven-year Guernsey deal locks in the leg of the business Talen can price and leaves the electricity merchant, in a zone its own 10-Q shows trading far below the PJM market. It de-risks the leveraged AI-power trade that TLN holders own.

    Power

    Gov. Spanberger moves to force NextEra's sealed fitness memo into the $67 billion Dominion merger hearing

    The State Corporation Commission's evidentiary hearing starts November 17 with a ruling due by January 11, while traders who bet on deal spreads treat approval as near-certain. A rate freeze, a rate cap or a fitness finding would reprice both stocks.

    Power

    PG&E freezes $2 billion of grid spending as California's wildfire liability law stalls

    California's utility regulator now calls the liability rule underneath PG&E's hardening boom unsustainable, and a November 19 vote could cut its 5,000-mile burial plan to about 1,100 miles. PCG shareholders are forgoing rate-base growth to protect the balance sheet; ratepayers may pay either way.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.