Hut 8 signed a second $9.8 billion Texas lease, then Keefe Bruyette cut the stock to $92 from $154

Hut 8 fully contracted its 1,000 MW Texas campus with a second $9.8 billion lease on October 30, and Keefe Bruyette cut its price target to $92 from $154 two days later, warning no new leases are coming through early 2027. KBW's valuation warning outweighed the new lease in Monday's session.

Vincent JiangVincent Jiangtwo-minute read
Share
Aerial rendering of Hut 8's Beacon Point AI data center campus, two large data halls in green fields in Nueces County, Texas
1 / 5Slide 1 of 5
A rendering of Hut 8's Beacon Point AI data center campus in Nueces County, Texas, whose 1,000 MW interconnection is now fully commercialized.

On October 30, Hut 8+15.34% — Hut 8, up 15.34 percent today signed the lease Keefe Bruyette said no one would sign for months: a second 15-year, $9.8 billion triple-net lease (a lease where the tenant pays taxes, insurance and maintenance) for 352 MW of IT capacity at its Beacon Point campus in Nueces County, Texas, with the same anonymous high-investment-grade tenant doubling its contracted capacity there to 704 MW 1.

The campus is now fully commercialized against its 1,000 MW AEP Texas interconnection, and Hut 8's portfolio stands at 949 MW of contracted IT capacity, $26.6 billion of base-term contract value and more than $1.75 billion of expected average annual net operating income, all leased to or backstopped by investment-grade counterparties 1. The first Phase 2 data hall is due in Q2 2028 1.

The market answered the lease with a sell-off

Phase 1, announced pre-market the same day, sent the stock up more than 35% intraday 2. Two sessions later, the lease was old news. Keefe Bruyette cut targets across seven bitcoin miners turned AI data-center landlords on November 2, warning of a "lease catalyst drought" through early 2027 3.

The firm said the group trades near or below its estimate of contracted lease value. Hut 8 took a cut to $92 from $154, even as KBW acknowledged the company has closed $7.5 billion of investment-grade project financing behind those 949 MW 4. HUT fell 6.77% that session; KBW's valuation warning outweighed the new lease in Monday's trading 4.

KBW cut every target; Cipher and CleanSpark lost over half

  • Target before
  • Target after
0$50$100$150$200$Cipher11.0$28.0$-61%CleanSpark11.5$25.0$-54%Riot20.0$35.0$-43%Hut 892.0$154.0$-40%
Data
Target beforeTarget afterChange
Cipher28.0$11.0$-60.7%
CleanSpark25.0$11.5$-54.0%
Riot35.0$20.0$-42.9%
Hut 8154.0$92.0$-40.3%
KBW price targets before and after the November 2, 2026, reset, in US dollars per share; sources: StockTwits via Yahoo Finance [3][4]3,4

The cuts hit the names with less paper harder

Cipher Digital+17.84% — Cipher Digital, up 17.84 percent today, a fellow bitcoin miner turned AI landlord that does have leases, still took the steepest cut, 61%, to $11 from $28; CleanSpark+7.92% — CleanSpark, up 7.92 percent today fell 54% to $11.50 with an unsigned Texas lease and a governor-ordered audit of data center grid connections; Riot cut to $20 from $35 with a $573 million bridge loan due December 31 34. Analyst Stephen Glagola also flagged Texas regulatory uncertainty weighing on the group 4.

A signed lease may not buy a premium

The open question is whether the market pays Hut 8 a premium for signed leases its peers lack, or whether the whole group trades at KBW's contracted-lease values regardless 13. Watch Hut 8's project-level financing for Beacon Point Phase 1: it is the next proof the leases convert to cash 13.

Deep dive: our October 30 report, "Hut 8 shareholders carry River Bend's interest and tax bill until the first hall opens in 2027," covers the carrying costs behind these leases.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading HUT

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    NetApp counts 350 AI deals instead of reporting AI revenue, and insiders sold 33 times without buying

    NetApp closed its Peak:AIO purchase with no price disclosed, in the same week the books closed on a period of insider selling: 33 sales in six months, not one purchase. The stock's premium rests on an AI business the company has never reported as a revenue line.

    Data Center

    Microsoft can wait out data-center protests; its landlord Pure Data Centres cannot, with $1 billion at stake

    Activists broke into Microsoft's Amsterdam data-center site at the start of a 16-country protest weekend. The exposure is not Microsoft's; it belongs to the developers and miners paying interest before revenue, and Texas just moved against them.

    Data Center

    Texas Governor-elect Gina Hinojosa wants a SpaceX pause as Goldman syndicates $40 billion of chip debt

    Goldman and Apollo are syndicating $40 billion of SpaceX chip debt secured against a Texas buildout that the state's new governor-elect wants paused. Lenders bought pre-election terms into a post-election state.

    Data Center

    Fermi's ousted CEO sold $13 million of stock into a 52-week low, then said it 'should be soaring'

    Toby Neugebauer, ousted as Fermi's chief executive in April, sold 7,657,800 shares for about $13 million in three sessions, 5 million of them on the day the stock touched its 52-week low. The next morning he demanded the company be sold, with its only tenant lease unsigned and $62.5 million of cash against a $737.9 million trailing loss.

    Data Center

    Data-center orders tripled at Carrier, and the cost of rolling its debt doubled

    On November 4 Carrier sold $1.5 billion of notes at more than double the coupon of the paper they retire, between record data-center orders and a $3.1 billion European write-down. The coupon is the market's new price for financing the AI buildout's supply chain.

    Data Center

    Oracle's $165 billion New Mexico campus permit slipped past December 7 as lenders sell the debt

    Oracle's $664 billion backlog assumes its biggest Stargate campus switches on. The New Mexico air-permit decision just slipped past December 7, the project's lenders are heading for the exits, and the stock's 8% drop was blamed on politics instead.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.