Nebius spent $5.65 billion on capex against $582 million of revenue, and now wants GPU-backed loans

The AI cloud's capex ran at nearly ten times quarterly revenue last quarter, just as its CEO conceded some debt channels have closed. COO Ofir Nave's answer this week: loans secured by GPUs and contracts, the one structure lenders still price cheap.

Vincent JiangVincent Jiang · 3 min read
Share
Arkady Volozh, chief executive of Nebius
1 / 6Slide 1 of 6
Nebius chief executive Arkady Volozh acknowledged in late October that some of the company's debt channels had closed.

Nebius+5.77% — Nebius, up 5.77 percent today spent $5.65 billion on property, equipment and intangibles in the second quarter against $2.25 billion of operating cash flow and $582 million of revenue 86. Those numbers show an Amsterdam-listed AI cloud building capacity at nearly ten times its quarterly revenue, in the same weeks its own chief executive and Elon Musk both said the cheap debt is gone 83.

The debt doors are closing one by one

A neocloud, in the plain sense, is a startup that rents out GPU computing capacity by the hour. On October 26, Nebius CEO Arkady Volozh acknowledged that certain secured financing channels and debt sources had temporarily closed 2. On November 2, Musk went further: debt markets have "almost entirely shut off access to money for any company that doesn't have substantial revenue independent of AI data centers," predicting "guppy-level death and consolidation" for the 200-plus neoclouds 3.

The bond market has moved the same way: CoreWeave's+4.78% — CoreWeave, up 4.78 percent today 9.625% notes due 2032 fell below 80 cents on the dollar in October, a yield near 15% 3. Lenders still fund one structure cheaply: a DDTL, a delayed-draw term loan, secured by GPUs and the customer contracts behind them. CoreWeave's GPU-secured DDTL priced under 6% in March while its unsecured coupons hit 9.75% by April 3. That is the rung Nebius is now reaching for.

The asset-backed rung

On November 3, chief operating officer Ofir Nave said asset-backed financing remains available and Nebius expects to use it; any high-yield bond sale would depend on rates and terms 1. The collateral looks real: more than $40 billion of long-term customer contracts, including Microsoft+1.85% — Microsoft, up 1.85 percent today and Meta+2.29% — Meta, up 2.29 percent today, about 70% of second-quarter deals carrying prepayments that covered 50% to 60% of the associated capex, and more than $9 billion of prepayments expected this year 6.

Nebius spent 10 times its Q2 revenue building data centers

  • Revenue
  • Capex
$0B$2B$4B$6BQ3 '24Q4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26$5.65B
Data
RevenueCapex
Q3 '24$0.03B$0.17B
Q4 '24$0.04B$0.42B
Q1 '25$0.05B$0.54B
Q2 '25$0.11B$0.51B
Q3 '25$0.15B$0.96B
Q4 '25$0.23B$2.06B
Q1 '26$0.4B$2.47B
Q2 '26$0.58B$5.65B
Nebius quarterly revenue vs capital expenditure, US$ billions, from SEC filings, Q3 2024 to Q2 2026. Source: [8].8

The funding stack shows who pays. Since 2024, about $2.7 billion has come from share sales to Nvidia+3.14% — Nvidia, up 3.14 percent today and other investors, plus billions in convertible bonds 1, then a $775 million GPU-secured loan in July 6, then a $3.5 billion Citi facility announced October 22, a 364-day line priced off SOFR, the benchmark rate US loans use, with a margin that starts at 2.75% and ratchets to 3.50% over time, as this publication reported on October 30 6.

Every extra month the line stays drawn, Nebius pays more to borrow, so the structure charges rent on delay. Shareholders supply the equity when secured debt is rationed.

What the equity has already paid

The market has priced the risk. Nebius is down 38.83% in a month, 50.5% below its June 22 peak of $299.86, trading near $150.71 and below its rising 200-day average of $177.72 4.

Insiders sold 35 times against 6 buys over the past year, including director John Wilson IV's 333-share sale on October 29 5. The counterpoint deserves its due: Nebius ended June with $8.04 billion of cash against $10.06 billion of debt, a far better ratio than CoreWeave's $51.6 billion of debt against $5.5 billion of cash 63, and its backlog of contracted demand already exceeds $40 billion 6. A backlog, though, is money promised, not money received; the interest bill arrives quarterly.

Nebius carries a fifth of CoreWeave's debt

  • Cash
  • Debt
$0B$20B$40B$60BNebiusCoreWeave$51.6B$10.06B
Data
CashDebt
Nebius$8.04B$10.06B
CoreWeave$5.5B$51.6B
Cash and total debt at quarter-end, US$ billions: Nebius as of June 2026, CoreWeave per its latest reported figures. Source: [6][3].6,3

Third-quarter results land on November 12, before the market opens, and that report is the first print since Volozh conceded some debt channels had closed 2. The figure that settles it is customer prepayments: if they and utilization keep covering the build, the asset-backed market stays open and Nave's sequencing holds. If prepayments stall, the equity tap becomes the only tap left, and the past month has shown how hard that tap can close.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading NBIS

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    S&P's Meta warning just landed on two LLCs holding $40 billion of AI data-center debt

    Four days after S&P put Meta on a downgrade clock over $132 billion of projected cash deficits, the same negative outlook landed on Beignet and Sopaipilla, two Meta data-center financing vehicles carrying about $40 billion of debt. The warning is moving down the financing stack.

    Data Center

    Hut 8 signed a second $9.8 billion Texas lease, then Keefe Bruyette cut the stock to $92 from $154

    Hut 8 fully contracted its 1,000 MW Texas campus with a second $9.8 billion lease on October 30, and Keefe Bruyette cut its price target to $92 from $154 two days later, warning no new leases are coming through early 2027. KBW's valuation warning outweighed the new lease in Monday's session.

    Data Center

    Seagate's record quarter met a 30% drawdown the day Broadcom and Microsoft qualified its SMR drives

    Shares tumbled 30% from their October peak even as Microsoft Azure Storage and Broadcom cleared HAMR+SMR drives.

    Data Center

    Celestica's $128 million of free cash flow was near negative $570 million after backing out invoice sales

    The 10-Q shows $700.8 million of sold receivables counted inside operating cash flow; back them out and Q3 free cash flow was roughly negative $570 million, not $128 million. The $21 billion 2026 and $40 billion 2027 revenue guides rest on rented cash.

    Data Center

    Regal Rexnord explores selling its robot unit after a $119 million write-down, with data-center sales up 307%

    Regal Rexnord's Q3 shows a $119 million write-down on its warehouse-robot bet going up for sale, while data-center sales up 307% and commercial HVAC orders up 47% point the capital the other way.

    Data Center

    Applied Digital's interest bill passed its rent for the first time: $77.4 million vs $65.8 million

    Applied Digital's quarterly interest expense passed its base rent for the first time, and its CEO says 800 megawatts of the buildout still needs financing. The AI buildout's bottleneck has moved from demand to the price of borrowed money, and shareholders are absorbing the difference.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.