Riot signed a $28 billion, 15-year Texas lease as Cipher's odds of signing one were halved after the vote

Democrat Gina Hinojosa won Texas on a pledge to pause new data centers until the legislature acts. Within hours, KBW had halved Cipher's lease odds while Riot signed a $28 billion lease in the same state.

Vincent JiangVincent Jiangthree-minute read
Share
Gina Hinojosa, governor-elect of Texas, smiling at the LBJ Presidential Library's Future of Texas forum in Austin in February 2017.
1 / 6Slide 1 of 6
Gina Hinojosa, then a Texas state representative, at the LBJ Presidential Library's Future of Texas forum in 2017. On Tuesday she won the governor's race on a pledge to stop what she calls the data center takeover.

Texas voted, and the landlord trade split

Democrat Gina Hinojosa won the Texas governor's race on Tuesday on a pledge to "stop the data center takeover": a moratorium on new data centers until the legislature passes community protections, plus an end to their tax incentives 1. Outgoing Governor Greg Abbott had already frozen environmental permits in September, with the grid-connection queue near 474 gigawatts 5.

The tape sorted the sector in one session

The split came within hours. Hut 8−8.83% — Hut 8, down 8.83 percent today fell 22.3%, Cipher Mining−6.85% — Cipher Mining, down 6.85 percent today 18.8%, CleanSpark−5.26% — CleanSpark, down 5.26 percent today 13.7% and Galaxy 11.8%, while Riot Platforms−3.93% — Riot Platforms, down 3.93 percent today rose 15.3% 27. Riot had signed, before the open, a 15-year lease of its entire 910-megawatt Corsicana campus to an unnamed frontier AI lab: about $28 billion over the term, roughly $1.8 billion a year of rent at an estimated 99% margin, and no equity issuance expected 3.

Only Riot, holding a signed lease, rose on the day

Riot rose 15.3% on its signed lease; unleased Texas pipelines fell up to 22.3%

-30%-20%-10%0%10%20%Hut 8-22.3%Cipher Mining-18.78%CleanSpark-13.68%Galaxy-11.76%IREN-8.89%TeraWulf-4.59%MARA-2.66%Riot Platforms15.3%
Data
Value
Hut 8-22.3%
Cipher Mining-18.78%
CleanSpark-13.68%
Galaxy-11.76%
IREN-8.89%
TeraWulf-4.59%
MARA-2.66%
Riot Platforms15.3%
Intraday share-price moves, late-morning quotes on November 4, 2026, as reported in the cited articles; Riot had announced its Corsicana lease before the open.2,7

One bank halved the odds before lunch

KBW downgraded Cipher and CleanSpark to Market Perform, halved its odds of Cipher signing the Reveille lease within 12 months to 50% from 100%, and cut CleanSpark's Sealy and Brazoria to 50% from 65%; Riot's rating went under review 4. Two days earlier the same desk had warned of a "lease catalyst drought" 9.

Morgan Stanley+0.55% — Morgan Stanley, up 0.55 percent today named Cipher, MARA and Galaxy the most Texas-exposed, noting a governor can pause projects by executive order and appoint the grid regulators whose terms open in 2027 5. Cantor Fitzgerald now expects Cipher's next lease to be signed outside Texas 6.

KBW halved its Texas lease odds overnight

Cipher's Reveille odds fell 100% to 50%; Sealy and Brazoria 65% to 50%

  • Before the election
  • KBW on November 4
0%20%40%60%80%100%Cipher's Reveille lease50%100%-50%CleanSpark's Sealy andBrazoria50%65%-23%
Data
Before the electionKBW on November 4Change
Cipher's Reveille lease100%50%-50.0%
CleanSpark's Sealy and Brazoria65%50%-23.1%
KBW analyst-assigned probabilities of leases signing within 12 months, before the election versus November 4, 2026.4

The buyers' case: contracted megawatts

Rosenblatt's Chris Brendler called the result "a sort by MW quality rather than a reason to sell the group" 7. His protection test is contracted revenue: $16.6 billion of Cipher's sits outside Batch Zero, the review tranche now separating exposed sites from protected ones, and his clear favorite is TeraWulf−5.69% — TeraWulf, down 5.69 percent today, whose 401-megawatt Kentucky campus for the AI lab Anthropic$350B — Anthropic, private, latest valuation $350B already carries state approval 7. TeraWulf added its own receipt that morning, with Google agreeing to backstop the project debt behind the roughly $19 billion Anthropic leases 8.

The catch in the split

Riot's lease is in Texas too. Its phases deliver through July 2028, all under the new governor, and Morgan Stanley flags even Riot's proposed projects for the same policy risk 35. The market did not sell Texas; it sold the Texas nobody had signed for.

The tell is a Texas lease under the new governor

Hinojosa takes office in January as the 90th Legislature convenes: a pause can come by executive order, while repealing the sales-tax exemption needs lawmakers 45. December brings the first rulings on the big-load queue, IREN−9.09% — IREN, down 9.09 percent today reports Thursday and MARA on Monday 26. The tell is whether any Texas lease prints under the new governor, and Riot's $28 billion says the labs still want the power 26.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading HUT

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Akamai's founder-CEO bought $2.6 million of its stock at $85.08, no trading plan

    F. Thomson Leighton paid $85.08 a share in cash on the open market, with no trading plan, a day after Akamai closed $2.5 billion of 1% convertible debt. Every other claim on the company's upside starts above $102; his entry marks where the man running the AI build-out values the equity.

    Data Center

    Legrand raises 2026 outlook again to 11-13% organic growth as data centers grow near 40%

    Legrand lifted its 2026 organic growth target to 11-13% after nine-month sales of €8.33 billion, and UBS turned buyer with a €170 target. Investors are now paid an 8% discount to Schneider Electric and ABB to hold a group whose growth sits in one product line.

    Data Center

    Cipher Digital fell 20% in a week on a Texas data-center moratorium aimed at campuses it has not leased

    A fifth of Cipher's value vanished in a week on a risk aimed at campuses it has not leased, while rent on the ones it has is now being booked. The exposure that reaches shareholders is funding the next build, behind $6.7 billion of debt and a spent-down bitcoin treasury.

    Data Center

    Fujikura banked ¥235 billion, mostly from AI fiber, then guided to ¥194 billion in the second half

    The AI data-center fiber supplier banked ¥235 billion of operating profit by September, raised its full-year revenue outlook and doubled the dividend, yet its own ¥429 billion guide plans a smaller, lower-margin second half. Investors deciding whether that is prudence or slowdown are the ones whose money moves.

    Data Center

    Accelevation's owners took $318.4 million in nine months and left $4.5 million of equity behind

    The AI data center builder's first public balance sheet shows $318.4 million taken out by its owners in nine months, $648.8 million of debt, $4.5 million of equity left behind, and 66% revenue growth that produced a 77% profit decline.

    Data Center

    Akamai paid $284 million to keep $2.5 billion of new debt at 1%

    The closing terms itemize the cost of Akamai's cheap money: $284.4 million for the hedge, warrants on 23.3 million shares struck up to 40% above the market, and a race between an Anthropic-backed build-out and a $1.15 billion maturity next September.

    Subscribe to TheInference for free