Applied Digital's $7.2 billion AI campus faces a Nov. 19 Louisiana vote on a $575.5 million tax deal

Rapides Parish would start collecting the moment the deal is signed, before the campus exists; the tenant, reportedly Meta, pays only once buildings are delivered. The same board packet proposes up to $4.6 billion of bonds meant to bridge those years, and Applied Digital's shareholders are the ones carrying them.

Richard TangRichard Tangthree-minute read
Share
Wes Cummins, chairman and chief executive of Applied Digital, in a close-up on the CNBC set
1 / 7Slide 1 of 7
Wes Cummins, Applied Digital's chairman and chief executive, on CNBC's Squawk on the Street on November 2, 2026, the day he said the company still needed financing for roughly 800 megawatts over the next twelve months.

Rapides Parish is showing what a community can extract from an AI buildout. On November 19 the England Authority, the public board that runs England Airpark, a former air base in central Louisiana, votes on a tax agreement for Delta Forge 1, Applied Digital's−8.14% — Applied Digital, down 8.14 percent today $7.2 billion, 300-megawatt campus 1. The agreement was introduced unanimously on November 9, and its decisive clause is a date: local taxing bodies start collecting the moment it is signed, before the data center exists 1.

The parish gets paid before the building exists

The Payment In Lieu Of Taxes, or PILOT, agreement sends Rapides Parish taxing bodies $13.8 million in each of 2026 and 2027, rising to $575.5 million through 2052 1. It sets a floor of 75 jobs by 2028 paying about $91,000, one and a half times Louisiana's average wage, growing to 200 jobs by 2031, with a formula that raises Applied Digital's payments whenever hiring falls short 1.

Road repairs, insurance make-wholes and a $50 million community trust are written into the text 1. The chamber and the sheriff's finance officer spoke for it; one activist called the technology "completely unregulated and extremely dangerous" 1. A red-lined draft adding water-use protections is due before the vote 1.

The rent that justifies all of this has not started

The tenant, which Applied Digital names only as a tier-one investment-grade hyperscaler and which reporting identifies as Meta+2.23% — Meta, up 2.23 percent today Platforms, signed a 15-year take-or-pay lease worth about $7.5 billion in April 234. Take-or-pay obliges the tenant to pay for the space whether or not it uses it, once the buildings are delivered. Until then the construction bills belong to Applied Digital, and last quarter showed what that costs: the company collected $65.8 million of base rent 4. Its interest bill was $77.4 million 4, a crossing point we flagged on November 3. Most of the quarter's revenue was one-time fit-out work, not rent 4.

Debt has outrun revenue in every quarter of the AI buildout

Borrowings hit $6.5 billion before a full quarter of rent arrived

  • Total debt
  • Quarterly revenue
$0B$2B$4B$6B$8BQ3 '24Q1 '25Q3 '25Q1 '26Q3 '26$6.48B
Data
Total debtQuarterly revenue
Q2 '24$0.14B$0.04B
Q3 '24$0.43B$0.04B
Q4 '24$0.8B$0.04B
Q1 '25$0.99B$0.05B
Q2 '25$0.91B$0.05B
Q3 '25$0.7B$0.08B
Q4 '25$2.61B$0.13B
Q1 '26$2.83B$0.13B
Q2 '26$5.1B$0.26B
Q3 '26$6.48B$0.34B
Calendar quarters through Q3 2026, the quarter ended August 31, 2026; dollars in billions. Source: Applied Digital quarterly SEC filings.8

The vote unblocks the campus's next financing

The same November 9 packet that carried the tax terms also proposes up to $4.6 billion of Louisiana revenue bonds for Delta Forge 1, repaid from the tenant's rent rather than the builder's credit, with no rate set yet 2. That structure matters: lenders would be pricing Meta's balance sheet rather than a company whose debt now exceeds its market value 25.

Capex has run at more than three times revenue for eight straight quarters

  • Capital spending
  • Revenue
$0B$1B$2B$3BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$2.08B
Data
Capital spendingRevenue
Q4 '23$0.01B$0.04B
Q1 '24$0.04B$0.04B
Q2 '24$0.04B$0.04B
Q3 '24$0.06B$0.04B
Q4 '24$0.17B$0.04B
Q1 '25$0.26B$0.05B
Q2 '25$0.17B$0.05B
Q3 '25$0.25B$0.08B
Q4 '25$0.55B$0.13B
Q1 '26$0.78B$0.13B
Q2 '26$1.29B$0.26B
Q3 '26$2.08B$0.34B
Calendar quarters through Q3 2026, the quarter ended August 31, 2026; dollars in billions, capital spending shown as a positive. Source: Applied Digital quarterly SEC filings.8

Chief Executive Wes Cummins said on November 2 that the company still needs financing for roughly 800 megawatts over the next twelve months 6. About $36 billion of contracted revenue across five campuses is waiting on buildings that do not exist yet 4.

Shareholders carry the years between signing and rent

Everything upstream of the money is signed: demand is real, land is secured, taxes are fixed, the lease exists. What remains is the unglamorous work of turning signed paper into delivered megawatts, and someone always finances those years. Macquarie's preferred equity and the project bondholders rank ahead of the common stock 7, as we laid out on October 23, and the common stock is the paper that has halved since mid-February 5. The two numbers that decide whether that bet pays are the rate the Louisiana bonds finally print 2, and whether base rent passes interest when the company reports in January 5.

The parish gets paid from signature, the tenant pays at delivery, and the shareholder carries everything in between.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading APLD

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Akamai's founder-CEO bought $2.6 million of its stock at $85.08, no trading plan

    F. Thomson Leighton paid $85.08 a share in cash on the open market, with no trading plan, a day after Akamai closed $2.5 billion of 1% convertible debt. Every other claim on the company's upside starts above $102; his entry marks where the man running the AI build-out values the equity.

    Data Center

    Legrand raises 2026 outlook again to 11-13% organic growth as data centers grow near 40%

    Legrand lifted its 2026 organic growth target to 11-13% after nine-month sales of €8.33 billion, and UBS turned buyer with a €170 target. Investors are now paid an 8% discount to Schneider Electric and ABB to hold a group whose growth sits in one product line.

    Data Center

    Cipher Digital fell 20% in a week on a Texas data-center moratorium aimed at campuses it has not leased

    A fifth of Cipher's value vanished in a week on a risk aimed at campuses it has not leased, while rent on the ones it has is now being booked. The exposure that reaches shareholders is funding the next build, behind $6.7 billion of debt and a spent-down bitcoin treasury.

    Data Center

    Fujikura banked ¥235 billion, mostly from AI fiber, then guided to ¥194 billion in the second half

    The AI data-center fiber supplier banked ¥235 billion of operating profit by September, raised its full-year revenue outlook and doubled the dividend, yet its own ¥429 billion guide plans a smaller, lower-margin second half. Investors deciding whether that is prudence or slowdown are the ones whose money moves.

    Data Center

    Accelevation's owners took $318.4 million in nine months and left $4.5 million of equity behind

    The AI data center builder's first public balance sheet shows $318.4 million taken out by its owners in nine months, $648.8 million of debt, $4.5 million of equity left behind, and 66% revenue growth that produced a 77% profit decline.

    Data Center

    Akamai paid $284 million to keep $2.5 billion of new debt at 1%

    The closing terms itemize the cost of Akamai's cheap money: $284.4 million for the hedge, warrants on 23.3 million shares struck up to 40% above the market, and a race between an Anthropic-backed build-out and a $1.15 billion maturity next September.

    Subscribe to TheInference for free