Fermi's fired founder files to sell 2.6 million shares as its first tenant lease misses closing

Fermi Inc. said on November 3 that its TensorWave lease missed its closing date because construction financing is not secured. Hours later, the founder the board fired in April filed notice to sell 2,563,800 more shares into a 52-week low.

Vincent JiangVincent Jiang · 3 min read
Share
Lee McIntire, chief executive of Fermi Inc.
1 / 6Slide 1 of 6
Fermi chief executive Lee McIntire, who told investors both sides of the TensorWave lease remain committed and promised financing details on next week's earnings call.

A notice at 6:41 p.m., hours after the lease slipped

Toby Neugebauer filed papers on November 3 to sell 2,563,800 shares of Fermi Inc−11.06% — Fermi Inc, down 11.06 percent today 12. (NASDAQ: FRMI) through Goldman Sachs+3.59% — Goldman Sachs, up 3.59 percent today, and EDGAR logged the Form 144 at 6:41 that evening 12. Priced at the $2.44 low the stock touched a day earlier, the block is worth about $6.3 million 3. The same day, Fermi, the Dallas builder of the Project Matador power-and-data-center campus in Amarillo, Texas, said its TensorWave lease never became effective 4. The stock closed down 7% at $2.05 5. A Form 144 is a notice of proposed sale, not a completed trade 6.

The seller founded Fermi, and the board fired him

Neugebauer founded Fermi, and the board removed him as chief executive on April 17, later terminating him for cause; he is suing three directors 78. His family group calls itself the largest shareholder at about 22% 7.

October sales came to roughly $14.7 million, and EDGAR shows three more Fermi Form 144 notices between October 13 and 20 16. At the October 30 annual meeting, co-founder Rick Perry, the former Texas governor and U.S. energy secretary, lost reelection to the board, and Fermi blamed "a breach of contractual voting obligations by the Neugebauer shareholders" 9. The stock is down more than 90% from its peak 9.

The lease names the missing piece: construction money

Chief Executive Lee McIntire says both sides "remain committed" and no termination right has been exercised 4. But the closing conditions on the 222-megawatt lease with TensorWave, Fermi's first announced tenant, include "securing project-level financing sufficient to fund construction," and that went unmet by October 31 4910.

A lender is being asked to carry it for a reason: Fermi's quarter-end cash fell from $408.5 million in December to $91.7 million at the end of June, with zero revenue booked since the October 2025 listing 711. The Inference flagged this funding gap on October 10, when the previous 52-week low was $3.42 711.

Fermi's quarter-end cash fell from $408.5M to $91.7M while revenue stayed zero

Cash fell 78% from December to June with no revenue booked

$0M$100M$200M$300M$400M$500MQ2 '25Q3 '25Q4 '25Q1 '26Q2 '26$91.73MCash at June 30; lease awaits aconstruction lender
Data
Quarter-end cash
Q2 '25$40.33M
Q3 '25$182.99M
Q4 '25$408.53M
Q1 '26$243.29M
Q2 '26$91.73M
Quarter-end cash in USD millions from Fermi's SEC filings, Q2 2025 through Q2 2026; the company has reported no revenue since its October 2025 listing.11

September wrote the counterpoint

Neugebauer's own September 11 release said the Neugebauers "have not sold a share since Fermi's IPO," and disclosed that a donor-advised fund would soon fund charitable commitments in Amarillo 7. The October sales may be that pledge executing rather than a verdict on the lease. Either way the arithmetic stands: the largest holder's stake is shrinking while the check that closes the lease stays unwritten.

The earnings call, then the vote count

McIntire promised details "during our earnings call next week" 4. Watch one item above all: a named construction lender. The October 30 vote tallies are due at the SEC within four business days 9. No lender, no lease; no lease, no revenue.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading FRMI

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Democrats won Texas on a data-center pause; Vistra fell as much as 15.5% and CoreWeave's bonds hit 79.5 cents

    Democrats took Congress and Texas elected a governor who campaigned on pausing data centers. The market answered by splitting AI in two: the builder that funds itself hit a record, and the leveraged builders sold off, with CoreWeave's bonds at 79.5 cents.

    Data Center

    Riot signed a $28 billion, 15-year Texas lease as Cipher's odds of signing one were halved after the vote

    Democrat Gina Hinojosa won Texas on a pledge to pause new data centers until the legislature acts. Within hours, KBW had halved Cipher's lease odds while Riot signed a $28 billion lease in the same state.

    Data Center

    One Stop Systems raised guidance twice and filed to sell up to $50 million of stock, 41% of its market value

    The edge-computing maker beat, raised guidance twice and opened a $50 million at-the-market program in the same week. At a $122.68 million market cap, that facility is now about 41% of the company, and retail sentiment has not noticed.

    Data Center

    Cipher Digital booked $5.85 million of first AI rent against $6.7 billion of debt

    Cipher's first quarter booking HPC rent produced $27 million of revenue and negative $10 million of adjusted EBITDA, against $16.6 billion of contracted leases and $6.7 billion of debt. Analysts cut their targets on November 3 and kept calling the shares undervalued; both halves are right.

    Data Center

    Trane booked a $12.5 billion backlog, and the market still sold it

    Trane Technologies beat estimates and raised its revenue guidance, yet the stock fell as much as 11% to a seven-month low. The gap between booked demand and booked margin is where the AI cooling trade now lives.

    Data Center

    WhiteFiber's $865 million lease is signed; delivering it is what the market doubts

    WhiteFiber closed a $60 million land purchase the same week it admitted switchgear problems have delayed billing at its first North Carolina data hall and its project financing still is not signed. The $865 million lease proves the demand; the open question is delivery.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.